Residential Construction and Building Trades Library
|
Book 01 — Construction Fundamentals: Tools, Safety, Layout, Materials, Math, and Building Science
Project 08 — Capstone Project
Build a Complete Garden Storage Shed Floor Platform
Build one complete 8-foot by 10-foot pressure-treated garden storage shed floor platform on three pressure-treated skids supported by three compacted aggregate strips, using the approved Project 06 layout and the approved Project 07 takeoff, cut plans, and hardware schedule as the controlling documents.
Field Cue System
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework, an unsafe platform, or an unapproved structural condition.
△
Safety Cue
Task-specific safety guidance for ordinary work hazards.
✋
Critical Safety Cue
Serious injury, structural failure, or major damage is possible.
⛑
Field Safety Cue
Practical work-area safety: lifting, footing, weather, and housekeeping.
▤
Code Alert
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
▧
Manufacturer Cue
Follow product-specific instructions for connectors, fasteners, and materials.
▱
Measurement Cue
Clearance, layout, spacing, and reference-point guidance.
Job Overview
This capstone project integrates every skill developed in Projects 1 through 7 into one finished structure: a complete 8-foot by 10-foot pressure-treated floor platform, supported on three skids and three compacted aggregate strips, ready to receive a garden storage shed superstructure in a later book.
The finished platform is a real, useful structure, not a demonstration exercise. It uses the jobsite controls from Project 01, the layout and verification methods from Project 02, the measuring and cutting discipline from Project 03, the fastener and hardware practices from Project 04, the assembly sequencing skills built in Project 05, the approved footprint and skid-line layout from Project 06, and the exact takeoff, cut plans, and hardware schedule approved in Project 07.
You do not re-derive quantities or redesign the platform while building it. You follow the approved Project 06 layout record and Project 07 planning documents exactly, and you stop work if the site or materials do not match those controlling documents.
Skills You Will Demonstrate
CF-043 — Verify the site-control plan, approved footprint, material takeoff, cut plan, and unresolved local requirements before construction.
CF-044 — Prepare and compact the three gravel support strips and establish the skid system level and coplanar.
CF-045 — Cut, lay out, assemble, square, and connect the 8-foot by 10-foot floor frame.
CF-046 — Install the blocking rows, frame-to-skid connectors, and required structural hardware.
CF-047 — Plan, cut, gap, fasten, and inspect the plywood floor deck.
CF-048 — Complete final measurements, punch-list corrections, weather protection, documentation, and project closeout.
Where This Skill Fits
Every earlier project in this book qualifies a single skill: a safe jobsite, accurate layout, accurate cutting, correct fastener and hardware installation, a first integrated assembly, an approved footprint, and an approved material plan. This project is where those separate skills combine into one continuous build sequence, from support-strip excavation through final deck fastening and closeout documentation.
The completed platform becomes the foundation for wall framing, roofing, and building-envelope work covered in later books in this series. This chapter builds and inspects the platform only; it does not extend into that later scope.
Scope and Intended Use
This project covers:
verifying the approved Project 06 layout, the approved Project 07 takeoff and cut plans, and current local site requirements before any excavation or cutting begins
excavating, preparing, and compacting three gravel support strips at the approved skid-centerline locations
placing, aligning, leveling, and bringing three pressure-treated skids into one coplanar bearing surface
cutting and assembling the 96-by-120-inch pressure-treated floor frame, including two end rim joists, two outside side joists, and five interior joists installed in joist hangers
installing two blocking rows beneath the plywood panel end joints and nine frame-to-skid connectors
planning, cutting, gapping, and fastening the three-panel exterior structural plywood deck
completing final measurement, punch-list correction, weather protection, documentation, and jobsite closeout
This project does not authorize the learner to:
improvise a different foundation, anchorage method, member size, spacing, treatment level, or connector schedule than the one approved in the Project 06 and Project 07 documents
proceed with construction when the actual site does not match the approved support conditions, permit status, or utility, drainage, frost, or setback requirements
add walls, a roof, siding, doors, electrical work, plumbing, mechanical systems, insulation, or finishes; this project produces the floor platform only
publish or assume a load rating, structural capacity, or code approval for the finished platform beyond what the approved design documents state
Any site condition that conflicts with the approved Project 06 layout or Project 07 takeoff must stop work until the controlling design documents are revised by an authorized person.
Reference Conventions
Establish these references before construction begins, and do not change them mid-project.
Term
Definition
Selected end baseline
The 10-foot end string established in Project 06, from which skid centerlines are measured at 12, 60, and 108 inches
Selected side reference
The 8-foot side string from which interior joist centerlines are measured at 16, 32, 48, 64, and 80 inches
Selected platform end
The end of the platform length from which the two blocking-row locations are measured at 48 and 96 inches
Coplanar
All three skid top surfaces lying in one common level plane, verified with a straightedge, string, or approved method across all three skids
Full hanger bearing
A joist seated completely into its joist hanger with the joist end in full contact with the hanger seat and every required hanger hole filled with the approved fastener
Panel strength direction
The 96-inch dimension of each plywood panel, oriented across the 8-foot platform width and perpendicular to the longitudinal joists
Reference and Build Record
Before beginning Phase 1, record the following directly on the project worksheet:
Project 06 layout record confirmed current and unchanged: ______ (Y/N) Project 07 takeoff and cut plans confirmed approved and unchanged: ______ (Y/N)
Date started: ____________ Builder name: ____________ Helper name: ____________
Prerequisites
Completed Project 01 jobsite safety qualification; the capstone work, cutting, material, waste, and access zones are re-established from that plan before construction begins
Completed Project 02 layout and level qualification; the skid and frame work in this project relies on the same reference-face, square, level, and plumb methods
Completed Project 03 measuring and cutting qualification; every joist, blocking piece, and panel cut in this project uses the same reference method and tolerances
Completed Project 04 fastener and hardware identification; hanger, connector, and structural-screw installation in this project follows the same identification and installation rules
Completed Project 05 sawhorse assembly; the matched, sequenced assembly method used there applies directly to the frame assembly in this project
Completed and approved Project 06 footprint layout, with the benchmark, strings, and skid centerlines still valid and undisturbed
Completed and approved Project 07 takeoff, purchase list, cut plans, panel plan, hardware schedule, and cost worksheet, with all materials delivered and inspected
Confirmed site permission, permit status, and all local requirements identified in the Site and Structural Control section below
Project Specification Sheet
A. Finished Project
One complete 8-foot by 10-foot (96-by-120-inch) pressure-treated garden storage shed floor platform, built on three pressure-treated 4×4 skids supported by three compacted aggregate strips, with a fully fastened 23/32-inch or 3/4-inch exterior structural plywood deck. Intended use: a level, square, structurally connected floor platform ready to receive a shed superstructure in a later book. This project does not include walls, roof, siding, doors, or any building system.
B. Component Schedule
Component
Quantity
Material
Finished Size
Preparation
Skids
3
Pressure-treated 4×4
96 in.
Square-cut ends; leveled and coplanar
End rim joists
2
Pressure-treated 2×6
96 in.
Square-cut ends from full-length stock
Outside side joists
2
Pressure-treated 2×6
117 in.
Square-cut ends; cut from 120-in. stock
Interior joists
5
Pressure-treated 2×6
117 in.
Square-cut ends; installed in joist hangers at 16, 32, 48, 64, and 80 in.
Short edge-bay blocks
4
Pressure-treated 2×6
13 3/4 in.
Square-cut ends per Project 07 blocking cut plan
Standard interior-bay blocks
8
Pressure-treated 2×6
14 1/2 in.
Square-cut ends per Project 07 blocking cut plan
Full deck panels
2
Exterior structural plywood
48 × 96 in.
As delivered; strength direction across platform width
Final deck strip
1
Exterior structural plywood
24 × 96 in.
Ripped from a full sheet per Project 07 panel plan
Joist hangers
10
Approved exterior connector
Matched to 2×6 joists
Installed with manufacturer-approved connector fasteners
Frame-to-skid connectors
9
Approved exterior connector
Matched to controlled detail
Installed with manufacturer-approved connector fasteners
C. Material Takeoff
All stock, sheet, hardware, fastener, and aggregate quantities for this project are controlled by the approved Project 07 purchase list. Do not recalculate quantities during construction. If a delivered quantity does not match the approved Project 07 purchase list, stop work and reconcile the discrepancy before proceeding.
Fastener or Connector
Quantity
Installation
Perimeter corner screws, 5 in. exterior structural
12
Three at each of the four perimeter corners
Blocking screws, 3 in. exterior structural
48
Two through each joist into each end of twelve blocks (four per block)
Floor-deck screws, 2 1/2 in. exterior-rated
minimum 200 or the calculated layout count
6 in. on center at supported panel edges; 12 in. on center in the field
Joist hanger connector fasteners
per identified manufacturer schedule
Every required hole filled at each of the ten hangers
Frame-to-skid connector fasteners
per identified manufacturer schedule
Every required hole filled at each of the nine connectors
D. Reference Conventions
Reference end, reference edge, and reference face for every cut component are established using the Project 03 method. Skid centerlines, interior joist centerlines, and blocking-row locations are measured from the selected end baseline and selected side reference established in Project 06, as defined in the Reference Conventions table above.
E. Acceptance Standards
Finished frame width (96 in.) and length (120 in.) within ±1/8 in.
Diagonal difference not more than 1/8 in.
Interior joist centerlines at 16, 32, 48, 64, and 80 in. within ±1/8 in.
Skid centerlines at 12, 60, and 108 in. within ±1/8 in.
All three skids level along their length and coplanar with each other
Every joist fully seated in its hanger with all required fasteners installed
Both blocking rows directly beneath the panel end joints, flush with joist tops
Panel gaps at 1/8 in. unless the identified panel manufacturer requires otherwise
No unsafe rocking, unsupported panel edge, split member, or uncorrected fastener failure
Site and Structural Control
Before permanent work begins, verify and record:
ownership or written permission for the work
utility locate requirements and results
setbacks and easements affecting the approved footprint
drainage direction and any required grading
frost depth and soil conditions at the site
permit requirements for the platform
the required foundation or anchorage method for the actual site
whether the skid-supported design is allowed at the actual location
required wind, seismic, flood, termite, and decay protections
whether a qualified designer or inspector must approve the platform before or after construction
CF-043 – CF-048
Capstone Construction Procedure
Build the Garden Storage Shed Floor Platform
Difficulty: Advanced (capstone)
Estimated Time: 2 working days
Estimated Cost: Per approved Project 07 cost worksheet
Finished Work: Complete, inspected, and documented floor platform
Phase 1 — Preconstruction Control
Review the Project 01 jobsite plan and establish the capstone work, cutting, material, waste, and access zones. Reject the site until every stop-work condition from Project 01 is corrected.
Review the approved Project 06 layout record and confirm the strings, benchmark, skid lines, and work-zone offsets remain valid. Recheck both diagonals against the Project 06 tolerance before continuing.
Review the approved Project 07 takeoff, purchase list, cut plan, panel plan, hardware schedule, assumptions, and exclusions. Confirm the reconciliation checklist shows no missing or unexplained item.
Verify local permit, setback, foundation, anchorage, frost, drainage, and utility requirements. Record confirmation of each item from the Site and Structural Control section.
Stop work if the actual site does not match the controlled support conditions. Contact an authorized person to resolve any conflict before proceeding.
Inspect all lumber, panels, connectors, fasteners, aggregate, and tools before installation. Reject any component that fails the Project 03 lumber-inspection criteria or shows connector or fastener damage.
Protect the material from ground moisture and weather while maintaining the clear access route. Stack lumber flat and off the ground per the Project 01 material-zone method.
Phase 2 — Support-Strip Preparation
Transfer the three skid centerlines at 12, 60, and 108 inches from the selected end baseline. Confirm each transferred mark against the approved Project 06 layout record.
Mark each gravel strip 6 inches on both sides of its centerline. Each strip is 12 inches wide.
Excavate each strip to the depth required to provide 4 inches of compacted aggregate or the greater approved site depth. Confirm the required depth against the Site and Structural Control verification in Phase 1.
Remove organic material, soft spots, standing water, roots, and loose soil from the controlled support area. Do not place aggregate over unremoved organic material.
Install geotextile where required by the approved site plan. Follow the manufacturer's overlap and placement instructions.
Place aggregate in controlled lifts. Do not place the full 4-inch depth in a single uncompacted lift.
Compact each lift before adding the next. Use the tamper across the full width and length of each strip.
Screed the three strips to the required elevation and verify their relationship to the benchmark. Use the line level or approved elevation-transfer method from Project 02.
Confirm drainage is directed away from protected structures and that the strips do not trap water. Correct any low point that would pond water beneath the platform.
Phase 3 — Skid Installation
Place the three 96-inch pressure-treated 4×4 skids on the support strips. Handle each skid with a helper where required.
Align each skid to its centerline and the 8-foot platform width. Confirm alignment against the Project 06 layout strings or transferred corner marks.
Level each skid along its length. Use the spirit level from Project 02 on the full length of each skid.
Use a straightedge, level, string, or approved method to bring all three skid tops into one plane. Check across all three skids, not only adjacent pairs.
Use only approved durable shims or bearing corrections; do not use loose scrap wood, soil piles, or unstable wedges. Confirm every shim is fully supported by the compacted aggregate beneath it.
Recheck skid spacing, parallel condition, end alignment, level, and coplanarity. Correct any skid that fails a check before proceeding.
Record the final skid elevations before assembling the frame. Use the benchmark established in Project 06.
Phase 4 — Frame Preparation
Cut the two end rim joists to 96 inches and the seven longitudinal joists to 117 inches. Follow the Project 07 cut plan and the Project 03 cutting method.
Prepare four 13 3/4-inch blocks and eight 14 1/2-inch blocks from the Project 07 cut plan. Cut from the two reserved 96-inch 2×6 boards.
Mark reference faces and identify the two outside side joists and five interior joists. Label each joist after cutting.
Pair the two end rim joists and transfer the joist layout marks across both members. Clamp them together to transfer marks accurately.
Mark the five interior joist centerlines at 16, 32, 48, 64, and 80 inches. Measure from the selected side reference on both end rim joists.
Mark the correct edge of each joist location so the installed joist centers fall on the stated dimensions. Confirm the hanger will be installed on the correct side of each mark.
Position and fasten the ten joist hangers using only the approved connector fasteners. Fill every required hanger hole per the manufacturer instructions.
Mark the blocking-row locations at 48 and 96 inches from the selected end. Transfer these marks onto the outside side joists.
Phase 5 — Frame Assembly
Assemble the two outside side joists and two end rim joists into the 96-by-120-inch perimeter. Position on a flat assembly surface or directly on the skids as site conditions allow.
Clamp the corners, verify flush top edges, and install three 5-inch exterior structural screws at each of the four perimeter corners. Twelve screws total.
Measure both frame diagonals and adjust the perimeter until they are equal within 1/8 inch. Compare the measured diagonal to the theoretical 12 ft. 9 11/16 in. diagonal as a check.
Install the five interior joists in the hangers and verify their centers at 16, 32, 48, 64, and 80 inches. Confirm full hanger bearing at every joist end.
Check every joist for crown orientation where applicable, full hanger bearing, flush top alignment, and correct fasteners. Correct any joist that is not fully seated before continuing.
Recheck overall width, length, and diagonals after the joists are installed. Correct any drift before moving the frame onto the skids.
Position the frame on the three skids with 12-inch end overhangs beyond the outer skid centerlines. Confirm the overhang matches the Project 06 skid-line spacing.
Align the frame to the Project 06 footprint strings or transferred corner marks. Confirm the frame sits within the approved footprint.
Verify the frame remains level, square, and fully supported at each skid crossing. Correct any gap between the frame and a skid before fastening connectors.
Phase 6 — Blocking and Frame-to-Skid Connections
Install the first blocking row beneath the planned 48-inch panel joint. Use two 13 3/4-inch edge blocks and two or more 14 1/2-inch interior blocks per the Project 07 blocking cut plan.
Install the second blocking row beneath the planned 96-inch panel joint. Use the remaining blocks per the cut plan.
Keep all blocking tops flush with the joist tops and joints tight without forcing the frame out of square. Recheck square before final fastening if any block requires forcing into place.
Fasten each block with two 3-inch exterior structural screws through the joist into each block end, for four screws per block. Forty-eight screws total across twelve blocks.
Recheck joist spacing and diagonal equality after blocking. Correct any shift caused by block installation.
Install the nine approved frame-to-skid connectors at the two outside side joists and center joist over each of the three skids. One connector at each of the three joists over each of the three skid crossings.
Use only the manufacturer-approved connector fasteners and fill every required hole in the controlled schedule. Confirm the fastener type and quantity against the Project 07 hardware schedule.
Complete any separate site-specific anchorage only from the approved local design. Do not improvise anchorage not identified in the Site and Structural Control verification.
Phase 7 — Floor-Deck Installation
Review the panel plan and confirm the 96-inch panel strength direction will run across the platform width and perpendicular to the longitudinal joists. Confirm against the Project 07 panel plan before cutting any panel.
Inspect all three panels and identify the best reference edges and faces. Reject any panel with damaged edges, delamination, or moisture damage.
Rip one 24-by-96-inch strip from the third panel using the Project 03 support and cutting method. Fully support the panel during the rip cut.
Dry-lay the first 48-by-96-inch panel and confirm its edges align with the frame and first blocking row. Do not fasten until alignment is confirmed.
Maintain the required perimeter and panel-joint gaps using controlled spacers. Use 1/8-inch spacers unless the identified panel manufacturer requires otherwise.
Temporarily secure the first panel and recheck frame square before full fastening. Confirm both diagonals remain within 1/8 inch.
Install the second full panel over the 48-to-96-inch platform section. Maintain the required panel-joint gap at the shared edge.
Install the 24-by-96-inch strip over the final 24 inches. Maintain the required gap at the final joint.
Confirm both panel joints are fully supported by the blocking rows. Check that no panel edge overhangs unsupported framing.
Fasten the panels with 2 1/2-inch exterior-rated floor-deck screws at 6 inches on center along supported panel edges and 12 inches on center along field framing, working from a controlled reference and avoiding overdriven heads. Follow the Project 07 deck-fastener layout.
Keep fasteners clear of panel edges by the required distance and ensure every fastener enters framing. Mark joist and blocking centerlines on the panel surface before fastening if needed.
Correct missed framing, proud heads, overdriven heads, damaged panel edges, or incorrect gaps by the supplied repair method. Reset any fastener that missed framing into the correct location.
Phase 8 — Final Inspection and Closeout
Measure and record the final 96-inch width and 120-inch length. Confirm both dimensions within ±1/8 inch.
Measure and record both final diagonals. Confirm the diagonal difference is not more than 1/8 inch.
Check level along the length, width, and major joist lines. Correct any deviation before proceeding to the walk-test.
Check skid bearing, joist alignment, hanger installation, connector installation, blocking, panel support, panel gaps, and fastener seating. Use the Required Final Inspection list below.
Walk the deck only when the controlled assembly and site conditions permit and inspect for movement, bounce, rocking, unsupported edges, or abnormal sound. Stop and investigate any unexpected movement immediately.
Create a punch list identifying every failed dimension, connection, surface, and documentation item. Record each item on the punch-list worksheet.
Correct every punch-list item within the approved project scope. Do not close out the project with an open punch-list item.
Repeat the affected inspection after each correction. Confirm the corrected item now passes.
Photograph the completed support system, frame before decking, hardware, panel layout, and final platform. Retain these photographs with the project record.
Record product identifications, material treatment markings, connector types, fastener types, final dimensions, and unresolved site requirements. Complete the documentation worksheet in full.
Apply required temporary weather protection without trapping water against the platform. Confirm airflow beneath any protective covering.
Clear waste, remove temporary hazards, protect the finished platform, and close the jobsite according to Project 01. Restore the jobsite controls established at the start of this project.
Required Final Inspection
The completed capstone must demonstrate:
approved site and support conditions confirmed and documented
three compacted support strips at the controlled locations
three skids aligned, level, and coplanar
finished frame width and length within ±1/8 in.
diagonal difference not more than 1/8 in.
correct joist locations and full hanger bearing
blocking directly beneath both panel end joints
correct connector models and approved fasteners, with no missing required connector fasteners
full bearing at all skid crossings
plywood strength direction, orientation, gap, support, and fastening as specified
no unsafe rocking, unsupported panel edge, severe crown mismatch, split member, or uncorrected fastener failure
completed punch list and correction record
complete photographic and measurement documentation
protected finished work and restored jobsite controls
Image Placeholder
Recommended image: three compacted gravel support strips at the approved skid centerlines, with elevation reference to the benchmark.
Image Placeholder
Recommended image: three skids aligned and checked for coplanar bearing using a straightedge across all three skids.
Image Placeholder
Recommended image: assembled floor frame with joist hangers, interior joists, and blocking rows installed before decking.
Image Placeholder
Recommended image: completed plywood deck showing panel orientation, panel gaps, and the floor-deck fastener pattern.
Image Placeholder
Recommended image: finished platform from two directions with completed punch list and final measurement record.
Failure Points and Troubleshooting
Cleanup
This project ends with a complete, inspected, and documented floor platform, not a temporary work area.
Clear all waste, offcuts, packaging, and temporary hardware from the work and material zones
Remove temporary hazards, cords, and staging from the platform and surrounding access route
Apply required temporary weather protection without trapping moisture against the platform
File the completed punch list, final measurement record, photographs, and documentation worksheet with the Project 06 and Project 07 records
Store the approved Project 06 layout record and Project 07 planning documents together with the Project 08 closeout record as one controlled project file
Restore the jobsite controls established in Project 01 before leaving the site
Field Terms
Coplanar
All three skid top surfaces lying in one common level plane.
Full Hanger Bearing
A joist seated completely into its joist hanger with full seat contact and every required fastener installed.
Panel Strength Direction
The orientation of a plywood panel's long dimension relative to the supporting framing, chosen to maximize load-carrying capacity across the span.
Frame-to-Skid Connector
An approved exterior connector joining a joist directly to a skid at a support crossing.
Punch List
A recorded list of every failed dimension, connection, surface, or documentation item identified during final inspection, tracked through correction and reinspection.
Coplanar Bearing Check
Verifying that all support points lie in one plane using a straightedge, string, or approved method across the full support system.
Walk-Test
A controlled inspection performed by walking the completed deck to check for movement, bounce, rocking, or abnormal sound.
Skill Check
What must be verified before excavation or cutting begins, and what should happen if the actual site does not match the approved Project 06 and Project 07 documents?
Why must all three skids be checked for a common coplanar bearing surface rather than only checked individually for level?
What is the required corner-screw schedule for the frame perimeter, and what is the required diagonal tolerance?
What does full hanger bearing mean, and how is it inspected at each of the ten joist hangers?
Why must both blocking rows land directly beneath the panel end joints, and how is that confirmed before fastening the deck?
What is the required panel-gap dimension, and why is it maintained even though it appears to weaken the joint?
What is the required floor-deck screw spacing at supported edges and in the field?
What should the learner do if a punch-list item is discovered during the final walk-test?
Why does this project not authorize wall, roof, or superstructure work?
What documentation must be completed and retained before the jobsite is closed out?
Competency Rubric
Competency
Independent Pass Standard
Not Demonstrated
With Assistance
Independently
CF-043
Verifies the site-control plan, approved footprint, material takeoff, cut plan, and unresolved local requirements before construction, with any conflict identified and escalated rather than improvised
CF-044
Prepares and compacts the three gravel support strips at the controlled locations and brings the skid system level and coplanar within the stated tolerance
CF-045
Cuts, lays out, assembles, squares, and connects the 96-by-120-inch floor frame within ±1/8 in. on all dimensions and diagonals
CF-046
Installs the blocking rows, frame-to-skid connectors, and required structural hardware per the approved hardware schedule with no missing fastener
CF-047
Plans, cuts, gaps, fastens, and inspects the plywood floor deck to the specified orientation, gap, support, and fastening schedule
CF-048
Completes final measurements, punch-list corrections, weather protection, documentation, and project closeout with no open punch-list item
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
Inspection Checklist — Final Platform Worksheet
Item
Target
Measured
Pass (Y/N)
Correction (if any)
Frame width
96 in. ±1/8 in.
Frame length
120 in. ±1/8 in.
Diagonal 1
Equal to diagonal 2 within 1/8 in.
Diagonal 2
Equal to diagonal 1 within 1/8 in.
Skid 1/2/3 coplanar check
No gap under verified straightedge
Interior joist centerlines
16, 32, 48, 64, 80 in. ±1/8 in.
Joist hanger bearing (10 hangers)
Full seat contact, all fasteners installed
Blocking rows (2 rows, 12 blocks)
Flush, beneath panel joints, 48 screws installed
Frame-to-skid connectors (9)
All required fasteners installed
Panel gaps
1/8 in. unless manufacturer specifies otherwise
Deck fastener schedule
6 in. edge / 12 in. field, all in framing
Walk-test
No movement, bounce, rocking, or sound
Punch list completed and corrected: ______ (Y/N) Photographic documentation complete: ______ (Y/N)
With every phase complete, review the finished platform against the Required Final Inspection list and confirm approved site and support conditions; three compacted, correctly located support strips; three level, coplanar skids; a frame within ±1/8 in. on width, length, and diagonal difference; correct joist locations and full hanger bearing; blocking directly beneath both panel end joints; correct connector models and fasteners with no missing hardware; full bearing at all skid crossings; correct plywood orientation, gap, support, and fastening; and no unsafe rocking, unsupported edge, split member, or uncorrected fastener failure. Complete the Final Platform Worksheet and correct any failed item, then repeat the affected check before declaring the platform complete. If a check fails, identify whether the error occurred in site verification, support-strip preparation, skid alignment, frame assembly, hardware installation, or deck installation before correcting and re-running the affected check.
Project Closeout
You have completed the capstone of the construction fundamentals sequence: a complete, inspected, and documented garden storage shed floor platform. This project required you to verify the site-control plan, approved footprint, material takeoff, cut plan, and unresolved local requirements before construction (CF-043), prepare and compact the three gravel support strips and establish the skid system level and coplanar (CF-044), cut, lay out, assemble, square, and connect the 8-foot by 10-foot floor frame (CF-045), install the blocking rows, frame-to-skid connectors, and required structural hardware (CF-046), plan, cut, gap, fasten, and inspect the plywood floor deck (CF-047), and complete final measurements, punch-list corrections, weather protection, documentation, and project closeout (CF-048).
This project also integrates every competency built across the book: the jobsite controls from Project 01, the layout and verification methods from Project 02, the measuring and cutting discipline from Project 03, the fastener and hardware practices from Project 04, the assembly sequencing from Project 05, the field layout from Project 06, and the material planning from Project 07.
The completed project is a garden storage shed floor platform only. It does not include walls, roof, siding, doors, electrical work, plumbing, mechanical systems, insulation, or finishes. The supplied skid-supported design does not replace local requirements for permanent foundations, frost protection, anchorage, uplift resistance, setbacks, drainage, soil bearing, termite protection, flood design, permits, or engineering. No walls or shed superstructure may be added until the platform and its support system are approved for the actual site and intended loads.