Safety Cue
Task-specific safety guidance for ordinary work hazards.
Chapter 1
Inspect a framed and sheathed roof from safe positions, evaluate slope, deck condition, edges, and openings against the approved roof plan, complete only authorized minor preparation, and issue a documented roofing-readiness decision before any underlayment, shingle, or flashing work begins.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework or hazards.
Task-specific safety guidance for ordinary work hazards.
Serious injury, fall, or major damage is possible.
Practical work-area safety: footing, weather, housekeeping, and access.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for materials, fastening schedules, and equipment.
Slope, span, clearance, and reference-point guidance.
This chapter qualifies you to inspect a framed and sheathed roof and to issue a documented roofing-readiness decision before any roofing work begins. The finished work product is a completed roof-deck inspection record, a deficiency list with authorized corrections completed and rechecked, and a written proceed, conditional-proceed, or stop-work decision supported by photographs and measurements.
You will confirm that framing and sheathing inspections are complete, identify the safe positions from which the roof may be inspected, examine the deck from both underside and surface positions where access allows, verify slope and deck specification against the approved roof plan, identify every drainage and transition feature on the roof, check clearances at penetrations, remove debris, reset or replace authorized deck fasteners, and document every unresolved item.
This is the first chapter in the book. It establishes the readiness decision that every later chapter depends on: no edge metal, membrane, underlayment, shingle, flashing, ridge, or gutter work may proceed over a deck that has not passed this inspection or been corrected to an authorized condition.
Every chapter that follows in this book — roof-access setup, edge metal, self-adhered membrane, underlayment, layout, starter strips, shingle fields, valleys, flashing, ridge work, ventilation, fascia and soffit, and gutters — is installed onto the deck condition documented in this chapter. A deck that has not been inspected and accepted here is not ready to receive any of those systems.
The readiness decision you issue at the end of this chapter is the gate that Chapter 2 checks before establishing roof access, and that the Chapter 20 capstone checks again before roofing the shed structure carried forward from Book 4.
This chapter covers:
This chapter does not authorize the learner to:
Any deck section that fails this chapter's inspection must be corrected under an authorized repair detail, or the roofing-readiness decision must record it as a stop-work item, before the section receives any roofing material.
Establish these references before recording any finding, and use them consistently across the deficiency list and readiness record.
| Term | Definition |
|---|---|
| Eave | The lower horizontal roof edge, typically over the exterior wall line, where water first leaves the roof plane |
| Rake | The sloped roof edge along a gable end, running from eave to ridge |
| Ridge | The uppermost horizontal line where two roof planes meet |
| Hip | The sloped line where two roof planes meet at an outside corner |
| Valley | The sloped line where two roof planes meet at an inside corner, concentrating water flow |
| Sidewall / Headwall | A vertical wall surface that meets a roof plane along its slope (sidewall) or across its slope (headwall) |
| Penetration | Any pipe, vent, skylight, chimney, or other object passing through the roof plane |
| Cricket / Saddle | A small secondary roof structure built to divert water around a wide penetration or the high side of a chimney |
| Roofing-readiness decision | The documented outcome of this chapter: proceed, conditional-proceed with listed corrections, or stop-work |
Before beginning the inspection, record the controlling documents and site identification directly on the roof-readiness documentation form:
Project / address: ______ Roof plan revision: ______ Framing and sheathing inspection reference: ______
Date started: ____________ Inspector name: ____________
Every readiness decision in this book, from this chapter's deck inspection to the Chapter 20 capstone readiness check, follows the same pattern: confirm the governing documents, inspect from safe positions, compare the field condition to the approved specification, correct only what is authorized, and document what remains. Learning that pattern here, before any material is installed, protects every layer that follows.
Inspect the underside of the deck where accessible for missed fasteners, unsupported edges, excessive gaps, water staining, daylight, delamination, mold, and framing conflicts. Inspect the accessible roof surface for loose panels, damaged edges, raised fasteners, protrusions, debris, contamination, uneven joints, punctures, and soft areas. Mark weak, wet, damaged, or questionable areas without walking on them.
Do not step onto the roof merely to complete this inspection. If compliant roof access, fall protection, surface condition, weather, and rescue provisions have not already been evaluated and accepted, limit the inspection to ground, ladder, lift, attic, scaffold, or another already-approved position. Chapter 2 establishes the access and fall-protection system required before any surface work.
Stop the inspection for rain, frost, snow, ice, or wind conditions that make ladder, attic, or approved surface positions unsafe. Keep ladder feet on firm, level ground and maintain three points of contact while climbing.
Measure roof slope separately on each distinct roof plane using the approved measurement method. Do not assume every plane on the roof shares the same slope, and do not substitute a visual estimate for a measured value.
Structural deck damage, suspected asbestos-containing material, active mold, or wet insulation found during this inspection are outside this chapter's authorized correction scope. Record the finding, stop work on the affected section, and route it to the applicable structural, environmental, or licensed authority before roofing proceeds over that section.
RF-001 – RF-006
Deck Inspection / Readiness Documentation
Deliverable: one completed roof-deck inspection covering every accessible roof plane, one deficiency list with location, condition, required correction, responsible authority, and reinspection method for each item, authorized corrections completed and rechecked, supporting photographs and measurements, and one signed proceed, conditional-proceed, or stop-work roofing-readiness decision.
| Document | Confirmed Current | Notes |
|---|---|---|
| Roof plan | ||
| Framing plan | ||
| Sheathing schedule | ||
| Roofing-system specification | ||
| Product installation instructions | ||
| Prior inspection records | ||
| Approved change documents |
| Check | Standard |
|---|---|
| Framing and sheathing inspection | Confirmed complete and on record before this inspection proceeds |
| Deck material, thickness, span rating, orientation, edge support, fastening | Matches the approved sheathing schedule; deviations recorded as deficiencies |
| Roof slope | Measured on each plane using the approved method and compared to the roof plan |
| Deck surface condition | Free of loose panels, damaged edges, raised fasteners, protrusions, debris, contamination, uneven joints, punctures, and soft areas, or each item listed as a deficiency |
| Underside condition (where accessible) | Free of missed fasteners, unsupported edges, excessive gaps, water staining, daylight, delamination, mold, and framing conflicts, or each item listed as a deficiency |
| Clearances at penetrations | Match the approved specification for chimneys, vents, skylights, flues, electrical conductors, and combustible assemblies |
| Deficiency list | Every item includes location, condition, required correction, responsible authority, and reinspection method |
| Readiness decision | Recorded as proceed, conditional-proceed with listed corrections, or stop-work, signed and dated |
Apply the same checks to every accessible roof plane, regardless of roof size or configuration.
Complete the Roof-Readiness Documentation Record in the Inspection Checklist section below before beginning Chapter 2.
Probable cause: the measurement was taken on the wrong plane, taken from an unlevel reference, or the framing was built to a different slope than the approved plan.
Confirmation: repeat the slope measurement on the identified plane using the approved method and a verified level reference.
Correction: if the remeasured slope confirms a deviation from the plan, record it as a deficiency and route it to the responsible authority for resolution before any roofing-system selection depends on the plan slope.
Reinspection: repeat the slope check on all planes after the deviation is resolved.
Probable cause: a prior roof leak, condensation from inadequate ventilation, or an active leak in progress.
Confirmation: inspect the extent, color, and apparent age of the staining, check for active moisture with an authorized moisture meter, and check attic ventilation conditions.
Correction: record the finding and its location on the deficiency list; do not cover a suspected active leak, wet insulation, or mold with roofing material. Route the finding to the responsible authority for further diagnosis, which may include the Chapter 18 leak-diagnosis procedure.
Reinspection: recheck the affected area only after the underlying moisture source is resolved.
Probable cause: under-driven or missed fasteners from the original sheathing installation, or fastener backout from moisture cycling.
Confirmation: visually and, where an approved surface position allows, physically confirm each raised or missing fastener location against the sheathing fastening schedule.
Correction: reset or replace each fastener using the type, length, and spacing specified in the fastening schedule; do not use a fastener not identified in the schedule.
Reinspection: recheck each corrected location for flush seating before it is recorded as complete.
Probable cause: a field change was made without updating the roof or ventilation plan, or the penetration was mislocated during framing.
Confirmation: compare the observed penetration location and size to the current framing and ventilation plans and to any approved change documents.
Correction: record the discrepancy as a deficiency and route it to the responsible authority for an approved change document before Chapter 12 or Chapter 14 work proceeds at that location.
Reinspection: recheck the location once an approved change document is issued.
Probable cause: the assembly was framed without confirming the required clearance, or trim or blocking was added after framing that reduced the clearance.
Confirmation: remeasure the clearance directly against the approved specification from a safe position.
Correction: record the finding as a deficiency; do not proceed with roofing over the affected area until the responsible authority approves a correction or an alternate detail.
Reinspection: recheck the clearance once the correction or alternate detail is complete.
Probable cause: the available ground, ladder, lift, attic, or scaffold positions do not provide a clear view of every section of a given plane.
Confirmation: review the positions identified in Step 3 against the roof sketch and identify the specific sections that remain unverified.
Correction: record the unverified sections on the deficiency list as an open item and issue a conditional-proceed decision limited to the verified sections, or arrange an additional approved position before issuing a full decision.
Reinspection: complete the inspection of the previously unverified sections once an approved position is available, then update the readiness decision.
This chapter ends with a signed readiness decision and an organized record set, not a pile of loose notes.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| RF-001 | Inspects roof sheathing from only safe, approved interior, exterior, and surface positions, without stepping onto an unprotected roof | |||
| RF-002 | Correctly identifies and records loose panels, damaged edges, raised fasteners, delamination, soft areas, and water staining | |||
| RF-003 | Measures and records roof slope on every distinct roof plane using the approved measurement method and compares it to the roof plan | |||
| RF-004 | Checks and records roof edges, overhangs, and penetration clearances against the approved specification | |||
| RF-005 | Removes debris and completes only authorized minor surface corrections, referring structural deficiencies to the correct authority | |||
| RF-006 | Produces a complete deficiency list, supporting photographs and measurements, and a signed proceed, conditional-proceed, or stop-work decision |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Condition Found | Correction Required | Corrected (Y/N) | Reinspection Result |
|---|---|---|---|---|
| Deck material / thickness / span rating | ||||
| Panel orientation / edge support / fastening | ||||
| Roof slope — Plane 1 | ||||
| Roof slope — Plane 2 | ||||
| Underside condition (attic/interior) | ||||
| Surface condition (approved positions) | ||||
| Fascia / subfascia / rafter tails | ||||
| Penetration clearances | ||||
| Ridge / vent / opening agreement with plans | ||||
| Debris removal | ||||
| Deck fastener reset/replacement |
Roofing-readiness decision: ______ (Proceed / Conditional-Proceed / Stop-Work) Date: ____________ Inspector name: ____________
With the inspection complete, review the deficiency list and the Roof-Readiness Documentation Record against the Acceptance Standards table and confirm every accessible roof plane has been inspected from an approved position, deck material and fastening have been compared to the sheathing schedule, slope has been measured on every plane, all penetration and combustible-assembly clearances have been checked, every deficiency has a recorded location, condition, correction, responsible authority, and reinspection method, and authorized corrections have been completed and rechecked. Issue and sign the roofing-readiness decision before beginning Chapter 2. If any item cannot be verified from an available position, record it as an open item and issue a conditional-proceed decision rather than a full proceed decision.
You have completed the first chapter in the roof-installation sequence: inspecting a roof deck and issuing a documented roofing-readiness decision. This chapter required you to inspect roof sheathing from safe positions (RF-001), identify damaged decking (RF-002), verify roof slope on each plane (RF-003), check roof edges and penetration clearances (RF-004), prepare the surface through authorized correction and debris removal (RF-005), and document roof readiness with a deficiency list, photographs, and a final decision (RF-006).
You now have a documented, signed roofing-readiness record that fixes the deck condition, slope, and feature locations every later chapter will build on. That record carries directly into the next chapter: establishing the roof-access and fall-protection system required before anyone steps onto this roof to install edge metal, membrane, underlayment, or shingles.
Store the completed deficiency list, photographs, and roofing-readiness decision with the project record. Chapter 2 requires this record before establishing roof access.