Chapter 1

Inspect a Roof Deck and Prepare for Roofing

Inspect a framed and sheathed roof from safe positions, evaluate slope, deck condition, edges, and openings against the approved roof plan, complete only authorized minor preparation, and issue a documented roofing-readiness decision before any underlayment, shingle, or flashing work begins.

Field Cue System

These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework or hazards.

△

Safety Cue

Task-specific safety guidance for ordinary work hazards.

✋

Critical Safety Cue

Serious injury, fall, or major damage is possible.

⛑

Field Safety Cue

Practical work-area safety: footing, weather, housekeeping, and access.

▤

Code Alert

Local requirements vary. Verify permit, inspection, and jurisdictional rules.

▧

Manufacturer Cue

Follow product-specific instructions for materials, fastening schedules, and equipment.

▱

Measurement Cue

Slope, span, clearance, and reference-point guidance.

Job Overview

This chapter qualifies you to inspect a framed and sheathed roof and to issue a documented roofing-readiness decision before any roofing work begins. The finished work product is a completed roof-deck inspection record, a deficiency list with authorized corrections completed and rechecked, and a written proceed, conditional-proceed, or stop-work decision supported by photographs and measurements.

You will confirm that framing and sheathing inspections are complete, identify the safe positions from which the roof may be inspected, examine the deck from both underside and surface positions where access allows, verify slope and deck specification against the approved roof plan, identify every drainage and transition feature on the roof, check clearances at penetrations, remove debris, reset or replace authorized deck fasteners, and document every unresolved item.

This is the first chapter in the book. It establishes the readiness decision that every later chapter depends on: no edge metal, membrane, underlayment, shingle, flashing, ridge, or gutter work may proceed over a deck that has not passed this inspection or been corrected to an authorized condition.

Skills You Will Demonstrate

  • RF-001 — Inspect roof sheathing from safe interior, exterior, and approved surface positions.
  • RF-002 — Identify damaged decking, including loose panels, raised fasteners, delamination, soft areas, and water staining.
  • RF-003 — Verify roof slope on each roof plane using the approved measurement method.
  • RF-004 — Check roof edges, overhangs, and clearances at penetrations against the approved specification.
  • RF-005 — Prepare the surface for underlayment by removing debris and correcting only authorized minor deficiencies.
  • RF-006 — Document roof readiness with a deficiency list, photographs, measurements, and a proceed, conditional-proceed, or stop-work decision.

Where This Skill Fits

Every chapter that follows in this book — roof-access setup, edge metal, self-adhered membrane, underlayment, layout, starter strips, shingle fields, valleys, flashing, ridge work, ventilation, fascia and soffit, and gutters — is installed onto the deck condition documented in this chapter. A deck that has not been inspected and accepted here is not ready to receive any of those systems.

The readiness decision you issue at the end of this chapter is the gate that Chapter 2 checks before establishing roof access, and that the Chapter 20 capstone checks again before roofing the shed structure carried forward from Book 4.

Scope and Intended Use

This chapter covers:

  • gathering and confirming the governing roof plan, framing plan, sheathing schedule, roofing-system specification, product instructions, and prior inspection records
  • confirming that required framing, sheathing, and structural inspections are already complete
  • inspecting the roof deck from safe positions, both underside and surface, without stepping onto an unprotected roof
  • verifying deck material, thickness, span rating, panel orientation, edge support, fastening, and roof slope against the approved specification
  • identifying eaves, rakes, ridges, hips, valleys, sidewalls, headwalls, penetrations, crickets, saddles, and drainage transitions
  • checking clearances at chimneys, vents, skylights, flues, electrical conductors, and combustible assemblies
  • removing debris and completing only authorized minor surface corrections
  • documenting deficiencies, corrections, and a final roofing-readiness decision

This chapter does not authorize the learner to:

  • step onto the roof surface unless compliant roof access and fall protection are already in place; Chapter 2 establishes that system
  • replace structural decking, correct framing damage, or perform any repair beyond a minor authorized surface correction; refer structural deck replacement to Chapter 19 or an approved repair detail
  • install any edge metal, membrane, underlayment, or roofing product; those tasks begin in Chapter 3 and later chapters, only after this chapter's readiness decision is proceed or conditional-proceed with corrections completed
  • disturb insulation, wiring, ductwork, or other concealed building systems encountered during the underside inspection without the authority that governs that system

Any deck section that fails this chapter's inspection must be corrected under an authorized repair detail, or the roofing-readiness decision must record it as a stop-work item, before the section receives any roofing material.

Reference Conventions

Establish these references before recording any finding, and use them consistently across the deficiency list and readiness record.

TermDefinition
EaveThe lower horizontal roof edge, typically over the exterior wall line, where water first leaves the roof plane
RakeThe sloped roof edge along a gable end, running from eave to ridge
RidgeThe uppermost horizontal line where two roof planes meet
HipThe sloped line where two roof planes meet at an outside corner
ValleyThe sloped line where two roof planes meet at an inside corner, concentrating water flow
Sidewall / HeadwallA vertical wall surface that meets a roof plane along its slope (sidewall) or across its slope (headwall)
PenetrationAny pipe, vent, skylight, chimney, or other object passing through the roof plane
Cricket / SaddleA small secondary roof structure built to divert water around a wide penetration or the high side of a chimney
Roofing-readiness decisionThe documented outcome of this chapter: proceed, conditional-proceed with listed corrections, or stop-work

Inspection and Readiness Record

Before beginning the inspection, record the controlling documents and site identification directly on the roof-readiness documentation form:

Project / address: ______     Roof plan revision: ______     Framing and sheathing inspection reference: ______

Date started: ____________     Inspector name: ____________

Prerequisites

Common Field Fundamentals

Every readiness decision in this book, from this chapter's deck inspection to the Chapter 20 capstone readiness check, follows the same pattern: confirm the governing documents, inspect from safe positions, compare the field condition to the approved specification, correct only what is authorized, and document what remains. Learning that pattern here, before any material is installed, protects every layer that follows.

Eaves & rakesLower and sloped edges; verify overhang and sheathing projection
Ridges & hipsUpper and outside-corner transitions; verify alignment and support
ValleysInside-corner water-concentration lines; verify deck support and width
Sidewalls & headwallsRoof-to-wall transitions; verify clearance and future flashing space
PenetrationsPipes, vents, skylights, chimneys, flues; verify clearance and support
Cricket / saddle locationsConfirm agreement with framing and drainage plan
Fascia & subfasciaVerify readiness to receive edge metal and gutters
Reference methodEvery finding recorded against the approved roof plan and sheathing schedule

Underside and Surface Inspection

Inspect the underside of the deck where accessible for missed fasteners, unsupported edges, excessive gaps, water staining, daylight, delamination, mold, and framing conflicts. Inspect the accessible roof surface for loose panels, damaged edges, raised fasteners, protrusions, debris, contamination, uneven joints, punctures, and soft areas. Mark weak, wet, damaged, or questionable areas without walking on them.

RF-001 – RF-006

Deck Inspection / Readiness Documentation

Roof-Deck Inspection and Roofing-Readiness Record

Difficulty: Beginner–Intermediate

Estimated Time: 3–5 hours

Estimated Cost: Minimal

Finished Work: Completed deficiency list, authorized corrections, and a documented roofing-readiness decision

A. Finished-Work Specification

Deliverable: one completed roof-deck inspection covering every accessible roof plane, one deficiency list with location, condition, required correction, responsible authority, and reinspection method for each item, authorized corrections completed and rechecked, supporting photographs and measurements, and one signed proceed, conditional-proceed, or stop-work roofing-readiness decision.

B. Governing Documents

DocumentConfirmed CurrentNotes
Roof plan
Framing plan
Sheathing schedule
Roofing-system specification
Product installation instructions
Prior inspection records
Approved change documents

C. Acceptance Standards

CheckStandard
Framing and sheathing inspectionConfirmed complete and on record before this inspection proceeds
Deck material, thickness, span rating, orientation, edge support, fasteningMatches the approved sheathing schedule; deviations recorded as deficiencies
Roof slopeMeasured on each plane using the approved method and compared to the roof plan
Deck surface conditionFree of loose panels, damaged edges, raised fasteners, protrusions, debris, contamination, uneven joints, punctures, and soft areas, or each item listed as a deficiency
Underside condition (where accessible)Free of missed fasteners, unsupported edges, excessive gaps, water staining, daylight, delamination, mold, and framing conflicts, or each item listed as a deficiency
Clearances at penetrationsMatch the approved specification for chimneys, vents, skylights, flues, electrical conductors, and combustible assemblies
Deficiency listEvery item includes location, condition, required correction, responsible authority, and reinspection method
Readiness decisionRecorded as proceed, conditional-proceed with listed corrections, or stop-work, signed and dated

D. Required Project Sequence

  1. Obtain the current roof plan, framing plan, sheathing schedule, roofing-system specification, product instructions, prior inspection records, and approved change documents. Confirm the revision or date on each document before using it as a reference, and record the confirmation on the governing-documents table above.
  2. Confirm that roof framing, sheathing, required connectors, and structural inspections are complete before roofing loads are staged. Locate the signed structural or framing inspection record. If it cannot be located or shows an open item, stop this chapter and route the project back to the responsible authority before continuing.
  3. Establish the permitted inspection positions. Use ground, ladder, lift, attic, scaffold, or an already-approved roof-access and fall-protection system as applicable to this site. Record which positions are available and which roof planes each position allows you to inspect.
  4. Do not step onto the roof merely to complete this chapter. If compliant roof access is not already in place, limit the inspection to the safe positions identified in Step 3 until Chapter 2 establishes full roof access.
  5. Inspect the underside of the roof deck where accessible for missed fasteners, unsupported edges, excessive gaps, water staining, daylight, delamination, mold, and framing conflicts. Use the attic or another interior access point and a flashlight, and record the location of every finding using the framing bay or grid reference shown on the framing plan.
  6. Inspect the roof surface for loose panels, damaged edges, raised fasteners, protrusions, debris, contamination, uneven joints, punctures, and soft areas. Perform this inspection from the approved positions established in Step 3, without stepping onto an unprotected roof.
  7. Mark weak, wet, damaged, or questionable areas without walking on them. Use chalk or a marking crayon visible from the approved inspection position, and record each marked location on the deficiency list.
  8. Verify deck material, thickness, span rating, panel orientation, edge support, and fastening against the approved specification. Compare the observed condition on each accessible plane to the sheathing schedule and record any deviation as a deficiency.
  9. Verify roof slope on each plane using the approved measurement method. Measure each distinct roof plane separately and record the measured slope next to the plan slope for that plane.
  10. Identify eaves, rakes, ridges, hips, valleys, sidewalls, headwalls, penetrations, crickets, saddles, and drainage transitions. Mark each on a roof sketch or the roof plan copy attached to the readiness record so later chapters can reference the same feature locations.
  11. Inspect fascia, subfascia, rafter tails, roof edges, overhangs, and sheathing projection for readiness to receive edge metal and gutters. Record alignment, decay, splits, or inadequate bearing as a deficiency requiring Chapter 15 attention where applicable.
  12. Verify required clearances at chimneys, vents, skylights, flues, electrical conductors, and combustible assemblies. Compare each measured clearance to the approved specification and record any shortfall as a deficiency.
  13. Confirm that planned ridge slots, intake vents, penetrations, and roof openings agree with the framing and ventilation plans. Record any planned opening that does not have a corresponding, approved location on the plans as a deficiency requiring resolution before Chapter 14.
  14. Remove loose debris using a method that does not discharge material from the roof edge or damage the deck. Contain and remove debris from the approved inspection positions or a subsequently authorized access, keeping the drop zone below the roof edge clear during removal.
  15. Reset or replace authorized raised or missing deck fasteners using the approved fastening schedule. Use only the fastener type, length, and spacing identified in the sheathing schedule, and record each location corrected.
  16. Complete only minor surface corrections allowed by the plan; refer structural deck replacement to Chapter 19 or an approved repair detail. Do not attempt any correction beyond fastener resetting, minor debris removal, and other corrections explicitly authorized by the roofing-system specification.
  17. Prepare a deficiency list identifying location, condition, required correction, responsible authority, and reinspection method. Enter every unresolved and every corrected item, including items referred to Chapter 19 or another authority.
  18. Correct authorized deficiencies and recheck the affected areas. Complete only the corrections identified as authorized in Step 16, and reinspect each corrected location against the same standard used in the original finding.
  19. Photograph and record roof slope, deck condition, edge condition, openings, penetrations, and unresolved items. Attach photographs to the readiness record and label each with its location on the roof sketch from Step 10.
  20. Issue a proceed, conditional-proceed, or stop-work roofing-readiness decision. Base the decision on the completed deficiency list: proceed only when every item is corrected and rechecked, conditional-proceed when specific listed corrections remain outstanding on specific roof sections, and stop-work when a structural, moisture, or hazardous-material finding requires resolution outside this chapter's scope. Sign and date the decision.

Common Deck Inspection Checks

Apply the same checks to every accessible roof plane, regardless of roof size or configuration.

Complete the Roof-Readiness Documentation Record in the Inspection Checklist section below before beginning Chapter 2.

Image Placeholder
Recommended image: an attic view of the underside of roof sheathing showing correct fastener seating alongside an example of water staining and daylight at a gap.
Image Placeholder
Recommended image: a roof surface viewed from an approved ladder or lift position, showing chalk-marked weak or damaged areas without a worker standing on the roof.
Image Placeholder
Recommended image: a roof-slope measuring tool positioned on a roof plane, with the measured slope reading visible.
Image Placeholder
Recommended image: an annotated roof sketch labeling eaves, rakes, ridges, hips, valleys, sidewalls, headwalls, and penetrations.
Image Placeholder
Recommended image: fascia and rafter-tail condition at a roof edge, contrasted with a decayed or misaligned example.
Image Placeholder
Recommended image: a completed deficiency list entry showing location, condition, required correction, responsible authority, and reinspection method.

Failure Points and Troubleshooting

Cleanup

This chapter ends with a signed readiness decision and an organized record set, not a pile of loose notes.

Field Terms

Roofing-Readiness Decision
The documented outcome of the deck inspection: proceed, conditional-proceed with listed corrections, or stop-work.
Deficiency List
The record identifying location, condition, required correction, responsible authority, and reinspection method for each finding.
Eave
The lower horizontal roof edge where water first leaves the roof plane.
Rake
The sloped roof edge along a gable end, running from eave to ridge.
Ridge
The uppermost horizontal line where two roof planes meet.
Hip
The sloped line where two roof planes meet at an outside corner.
Valley
The sloped line where two roof planes meet at an inside corner, concentrating water flow.
Sidewall / Headwall
A vertical wall surface meeting a roof plane along its slope (sidewall) or across its slope (headwall).
Cricket / Saddle
A small secondary roof structure built to divert water around a wide penetration or the high side of a chimney.
Approved Inspection Position
Ground, ladder, lift, attic, scaffold, or an already-approved roof-access and fall-protection position used for inspection before Chapter 2 establishes full roof access.

Skill Check

  1. Why must the framing and sheathing inspection record be confirmed complete before this chapter's deck inspection proceeds?
  2. Under what condition is a learner authorized to step onto the roof surface during this chapter, and where is that authorization actually established?
  3. What is the difference between a deficiency corrected under this chapter's authority and one that must be referred to Chapter 19 or another responsible authority?
  4. Why must roof slope be measured separately on each distinct roof plane rather than assumed from one measurement?
  5. What five pieces of information must every deficiency-list entry contain?
  6. What must a learner do upon finding suspected active moisture, mold, or wet insulation during the underside inspection?
  7. What are the three possible outcomes of the roofing-readiness decision, and what condition governs each one?
  8. Why must debris removal avoid discharging material from the roof edge?
  9. What information must be recorded before any raised or missing deck fastener is reset or replaced?
  10. Why does the roof sketch created in this chapter matter to later chapters in this book?

Competency Rubric

CompetencyIndependent Pass StandardNot DemonstratedWith AssistanceIndependently
RF-001Inspects roof sheathing from only safe, approved interior, exterior, and surface positions, without stepping onto an unprotected roof
RF-002Correctly identifies and records loose panels, damaged edges, raised fasteners, delamination, soft areas, and water staining
RF-003Measures and records roof slope on every distinct roof plane using the approved measurement method and compares it to the roof plan
RF-004Checks and records roof edges, overhangs, and penetration clearances against the approved specification
RF-005Removes debris and completes only authorized minor surface corrections, referring structural deficiencies to the correct authority
RF-006Produces a complete deficiency list, supporting photographs and measurements, and a signed proceed, conditional-proceed, or stop-work decision

Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.

Inspection Checklist — Roof-Readiness Documentation Record

ItemCondition FoundCorrection RequiredCorrected (Y/N)Reinspection Result
Deck material / thickness / span rating
Panel orientation / edge support / fastening
Roof slope — Plane 1
Roof slope — Plane 2
Underside condition (attic/interior)
Surface condition (approved positions)
Fascia / subfascia / rafter tails
Penetration clearances
Ridge / vent / opening agreement with plans
Debris removal
Deck fastener reset/replacement

Roofing-readiness decision: ______ (Proceed / Conditional-Proceed / Stop-Work)     Date: ____________     Inspector name: ____________

Performance Check

With the inspection complete, review the deficiency list and the Roof-Readiness Documentation Record against the Acceptance Standards table and confirm every accessible roof plane has been inspected from an approved position, deck material and fastening have been compared to the sheathing schedule, slope has been measured on every plane, all penetration and combustible-assembly clearances have been checked, every deficiency has a recorded location, condition, correction, responsible authority, and reinspection method, and authorized corrections have been completed and rechecked. Issue and sign the roofing-readiness decision before beginning Chapter 2. If any item cannot be verified from an available position, record it as an open item and issue a conditional-proceed decision rather than a full proceed decision.

Chapter Closeout

You have completed the first chapter in the roof-installation sequence: inspecting a roof deck and issuing a documented roofing-readiness decision. This chapter required you to inspect roof sheathing from safe positions (RF-001), identify damaged decking (RF-002), verify roof slope on each plane (RF-003), check roof edges and penetration clearances (RF-004), prepare the surface through authorized correction and debris removal (RF-005), and document roof readiness with a deficiency list, photographs, and a final decision (RF-006).

You now have a documented, signed roofing-readiness record that fixes the deck condition, slope, and feature locations every later chapter will build on. That record carries directly into the next chapter: establishing the roof-access and fall-protection system required before anyone steps onto this roof to install edge metal, membrane, underlayment, or shingles.

Store the completed deficiency list, photographs, and roofing-readiness decision with the project record. Chapter 2 requires this record before establishing roof access.