Chapter 7
Install the approved starter-strip system along required eaves and rakes, using the correct product, overhang, adhesive orientation, and joint offset, to seal the first shingle course and establish the working edge for the roof-covering field.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework or hazards.
Task-specific safety guidance for ordinary work hazards.
Serious injury, fall, or major damage is possible.
Practical work-area safety: footing, weather, housekeeping, and access.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for materials, fastening schedules, and equipment.
Slope, span, clearance, and reference-point guidance.
This chapter qualifies you to install the approved starter-strip system that seals and supports the first course of field shingles. The finished work product is a straight, securely fastened starter course along every required eave and, where the approved system calls for it, along every required rake — installed with the correct overhang, adhesive orientation, joint offset from the first field course, and corner transitions, and inspected before the first field course begins.
You will confirm the starter product's compatibility with the field shingles, stage and prepare starter material, mark the required overhang from the drip-edge reference, cut the first section to create the required joint offset, align and fasten successive sections, form eave-to-rake corner transitions, and document the completed starter course.
This chapter follows Chapter 6, which established the roofing layout control grid, and precedes Chapter 8, where the first field course is installed directly onto the starter strip you install here. No field shingle may be installed until the starter course beneath it has passed inspection.
The starter course is the last water-control layer installed before the visible roof-covering field begins, and the first layer that the field shingles depend on for wind resistance along the roof edges. A starter course installed without the manufacturer-required adhesive orientation, overhang, or joint offset compromises the wind-warranty performance of every course installed above it in Chapter 8.
This chapter depends directly on the roof-edge metal from Chapter 3, the underlayment from Chapter 5, and the layout control grid from Chapter 6. It in turn establishes the edge that Chapter 8's first field-shingle course is measured and fastened against.
This chapter covers:
This chapter does not authorize the learner to:
Any eave or rake section that fails this chapter's inspection must be corrected under this chapter's procedure, or the affected section must be held open, before it receives a field-shingle course.
Establish these references before installing any starter section, and use them consistently across the starter installation record.
| Term | Definition |
|---|---|
| Starter overhang | The distance the starter strip projects beyond the drip-edge reference, as specified by the roofing-system instructions |
| Adhesive strip | The factory-applied sealant band on the starter product that bonds the first field course; its required position relative to the roof edge is set by the manufacturer |
| Joint offset | The required horizontal distance between a starter-strip joint and the nearest joint in the first field-shingle course |
| Eave starter | Starter strip installed along the lower horizontal roof edge |
| Rake starter | Starter strip installed along the sloped gable-end edge, where the approved system requires it |
| Corner transition | The point where eave starter and rake starter meet, formed without doubled humps, gaps, or exposed adhesive |
Before beginning installation, record the controlling documents and site identification directly on the starter installation record:
Project / address: ______ Roofing-system specification revision: ______ Starter product identified: ______
Date started: ____________ Installer name: ____________
The starter course exists to do two things the field shingles cannot do for themselves at the roof edge: seal the underside of the first course tabs against wind lift, and support the exposed cutouts of the first course over a continuous surface rather than a bare edge. Every decision in this chapter — overhang, adhesive orientation, joint offset, and corner treatment — serves one or both of those purposes.
Mark the required starter overhang from the drip-edge reference before positioning any section. Confirm the adhesive strip's position relative to the roof edge against the manufacturer instructions before fastening the first section, since this position differs among products. Cut the first starter section to create the required joint offset from the first field-shingle course before installing any full section.
Verify that the selected starter product is identified by the roofing-system instructions as compatible with the field shingles and approved for the specific roof edges being covered before staging any material. Do not substitute a starter product not identified in those instructions.
Mark the required starter overhang from the drip-edge reference established in Chapter 3, not from the edge of the underlayment or the fascia. Measure the required joint-offset distance between each starter joint and the nearest first-course joint before cutting the offset piece.
Direct the utility knife blade away from the supporting hand and body when cutting starter sections. Seat each fastener flush without overdriving or angling it into an adjoining section.
Maintain the fall-protection provisions established in Chapter 2 while working along eaves and rakes. Keep starter bundles staged clear of the roof edge and secured against sliding or wind while not in use.
RF-037 – RF-042
Roof-Covering Installation / Starter Course
Deliverable: one completed starter-strip installation covering every required eave and rake, with the specified overhang, adhesive orientation, fastening, joint offset from the first field course, and corner transitions, inspected and corrected before Chapter 8 begins.
| Document | Confirmed Current | Notes |
|---|---|---|
| Roofing-system instructions | ||
| Starter-product manufacturer instructions | ||
| Chapter 3 roof-edge metal inspection record | ||
| Chapter 5 underlayment inspection record | ||
| Chapter 6 layout record |
| Check | Standard |
|---|---|
| Product compatibility | Starter product matches the roofing-system instructions for the field shingles and edges covered |
| Overhang | Matches the required distance from the drip-edge reference on every eave and rake section |
| Adhesive orientation | Positioned per the manufacturer-required location relative to the roof edge |
| Fastening | Fastener type, quantity, location, and seating match the specified schedule |
| Joint offset | Starter joints offset from first-course joints by the required distance |
| Corner transitions | Formed without doubled humps, gaps, or exposed adhesive |
| Documentation | Starter installation record complete, including corrections, before Chapter 8 begins |
Apply the same checks to every eave and rake receiving starter strip, regardless of roof size or configuration.
Complete the Starter Installation Record in the Inspection Checklist section below before beginning Chapter 8.
Probable cause: the overhang was marked at only a few points and the reference drifted between them, or the drip edge itself is not straight.
Confirmation: remeasure overhang at short, consistent intervals along the full eave and compare each measurement to the required distance from the drip-edge reference.
Correction: remove and reposition the affected starter sections to the correct overhang; if the drip edge itself is out of tolerance, record the finding and route it to the Chapter 3 record for resolution.
Reinspection: recheck overhang along the corrected sections before fastening the first field course.
Probable cause: the offset cut on the first starter section was skipped, measured incorrectly, or the layout lines from Chapter 6 were not referenced during starter installation.
Confirmation: compare the marked starter joint locations to the Chapter 6 layout lines for the first field course.
Correction: remove and replace the affected starter section with one cut to the required offset before installing the first field course over it.
Reinspection: recheck the offset at each corrected joint before proceeding to Chapter 8.
Probable cause: the starter product was installed upside down or reversed relative to the manufacturer's required orientation.
Confirmation: compare the installed adhesive-strip position to the manufacturer instructions confirmed in Step 1 of the sequence.
Correction: remove and reinstall the affected sections in the correct orientation; do not rely on hand-sealing to compensate for a reversed adhesive strip.
Reinspection: recheck adhesive orientation on every corrected section.
Probable cause: the eave and rake starter pieces were not trimmed to fit before fastening, or the corner sequence was installed out of order.
Confirmation: inspect the corner from a safe position for continuous coverage and confirm the adhesive strip is not exposed to weather.
Correction: remove and refit the corner pieces so the starter course remains continuous across the transition without a doubled hump or gap.
Reinspection: recheck the corrected corner before the first field course is installed over it.
Probable cause: incorrect nailer pressure setting, an out-of-zone fastening location, or a fastener driven at an angle.
Confirmation: inspect each fastener for flush seating within the specified fastening zone.
Correction: remove and replace any starter section with a cut, torn, or improperly fastened area; reset the nailer pressure before continuing.
Reinspection: recheck fastener seating and zone placement on all corrected sections.
This chapter ends with an inspected starter course and an organized record set, not scattered offcuts and loose fasteners.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| RF-037 | Selects a starter-strip product confirmed compatible with the approved field shingles and covered roof edges | |||
| RF-038 | Aligns the starter course to the drip-edge reference and required overhang along the full eave and rake length | |||
| RF-039 | Offsets starter joints from first-course joints by the required distance at every joint location | |||
| RF-040 | Fastens starter shingles using the specified fastener type, quantity, location, and seating condition | |||
| RF-041 | Maintains required overhang at eaves and rakes through corner transitions without gaps or exposed adhesive | |||
| RF-042 | Inspects the completed starter course and corrects overhang, alignment, fastening, adhesive orientation, joint offset, and corner defects |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Condition Found | Correction Required | Corrected (Y/N) | Reinspection Result |
|---|---|---|---|---|
| Starter product / compatibility | ||||
| Eave overhang | ||||
| Rake overhang (where required) | ||||
| Adhesive-strip orientation | ||||
| Fastening — type / quantity / location | ||||
| Joint offset from first field course | ||||
| Eave-to-rake corner transitions | ||||
| Protection prior to Chapter 8 |
Starter-course readiness decision: ______ (Proceed to Chapter 8 / Conditional-Proceed / Stop-Work) Date: ____________ Installer name: ____________
With installation complete, review the starter installation record against the Acceptance Standards table and confirm every required eave and rake has starter strip installed at the correct overhang, the adhesive strip is oriented per the manufacturer instructions, every fastener is seated within the specified zone, every starter joint is offset from the nearest first-course joint by the required distance, every corner transition is continuous without gaps or exposed adhesive, and every correction has been rechecked. Sign and date the starter-course readiness decision before beginning Chapter 8. If any section cannot be verified from an available position, record it as an open item and issue a conditional-proceed decision rather than a full proceed decision.
You have completed the seventh chapter in the roof-installation sequence: installing the starter-strip system that seals and supports the first field-shingle course. This chapter required you to select a compatible starter product (RF-037), align the starter course to the drip-edge reference (RF-038), offset starter joints from the first field course (RF-039), fasten starter shingles to the specified schedule (RF-040), maintain overhang through corner transitions (RF-041), and inspect the completed starter course (RF-042).
You now have a documented, inspected starter course that fixes the edge every field-shingle course in Chapter 8 will be measured and fastened against. That record carries directly into the next chapter: installing asphalt shingles on a simple roof plane from this starter course to the upper termination.
Store the completed starter installation record and photographs with the project record. Chapter 8 requires this record before the first field-shingle course begins.