Chapter 13

Install Ridge Cap Shingles

Prepare a straight, evenly terminated ridge or hip line, select or fabricate compatible cap shingles, and install a fully covered, concealed-fastener ridge-cap system on a non-vented ridge, hip, or separate practice ridge, using the exposure, fastening, and overlap requirements of the approved product instructions.

Field Cue System

These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework or hazards.

△

Safety Cue

Task-specific safety guidance for ordinary work hazards.

✋

Critical Safety Cue

Serious injury, fall, or major damage is possible.

⛑

Field Safety Cue

Practical work-area safety: footing, weather, housekeeping, and access.

▤

Code Alert

Local requirements vary. Verify permit, inspection, and jurisdictional rules.

▧

Manufacturer Cue

Follow product-specific instructions for materials, fastening schedules, and equipment.

▱

Measurement Cue

Slope, span, clearance, and reference-point guidance.

Job Overview

This chapter qualifies you to install a complete ridge-cap shingle system on a non-vented ridge, a hip, or a separate practice ridge assembly. The finished work product is a straight, fully covered ridge or hip line with concealed fasteners, manufacturer-compliant overlaps, and a documented inspection confirming alignment, exposure, side coverage, and terminal detail.

You will confirm the adjoining shingle fields terminate evenly and are secure, select or prepare compatible ridge-cap pieces, establish a starting end and centerline reference, fasten each cap through the designated zone so the next cap conceals the fastener, carry the overlap and exposure pattern through hip geometry changes, and complete the terminal detail with concealed or sealed fasteners.

Ridge caps are the final weather-shedding layer on the roof's highest lines. Every course of field shingles installed in Chapters 8 and 9 terminates here, and this chapter's work is the last opportunity to catch an uneven termination or a fastening defect before the ridge is closed.

Skills You Will Demonstrate

  • RF-073 — Prepare the ridge line by verifying adjoining shingle-field termination and correcting only by approved methods.
  • RF-074 — Cut or select ridge-cap shingles compatible with the field-shingle product and approved for the specific ridge or hip condition.
  • RF-075 — Align cap shingles to centerline and exposure references established from the starting end.
  • RF-076 — Fasten ridge caps through the designated zone using nails of the correct length for the required substrate penetration.
  • RF-077 — Overlap caps by the specified amount so each cap conceals the fasteners of the piece beneath it.
  • RF-078 — Inspect the finished ridge for alignment, exposure, side coverage, fastener concealment, sealing, and damaged tabs.

Where This Skill Fits

This chapter follows the asphalt-shingle field installed in Chapter 8 and the valley work in Chapter 9, and it depends on both roof planes terminating evenly at the ridge or hip. It also depends on the ridge-condition decision made before this work begins: a non-vented ridge is capped directly by this chapter, while a ridge carrying an exhaust-vent system is capped only after Chapter 14 installs the vent.

The completed ridge-cap system feeds directly into the Chapter 20 capstone, which installs ridge-cap shingles over a vent using the sequence this chapter and Chapter 14 establish together.

Scope and Intended Use

This chapter covers:

  • confirming whether the ridge is non-vented or requires Chapter 14's ridge-vent system before capping
  • inspecting adjoining shingle fields for equal termination, adequate coverage, and secure fastening
  • selecting factory-made ridge caps or preparing cap pieces from approved shingles according to the product instructions
  • establishing the starting end, centerline, and exposure references
  • fastening caps through the designated zone with concealed-fastener overlap
  • adjusting cap pieces gradually at hips or other geometry changes
  • completing the final cap or terminal piece using the approved concealed-fastener or sealed-fastener detail
  • inspecting the finished ridge and documenting the completed work

This chapter does not authorize the learner to:

  • cap over a planned ridge-vent slot before the vent is installed; that sequence is governed by Chapter 14
  • trim or repair field shingles beyond the approved correction method identified in this chapter; broader field-shingle defects are governed by Chapter 8 or Chapter 17
  • cut a ridge-vent slot or perform any ventilation-system work; that work is governed by Chapter 14
  • substitute an incompatible cap product, fastener, or sealant for the one identified by the roofing-system specification

Any ridge or hip section where the adjoining shingle fields fail this chapter's termination check must be corrected under the governing chapter before it receives ridge-cap shingles.

Reference Conventions

Establish these references before recording any finding, and use them consistently across the ridge-cap installation and inspection record.

TermDefinition
RidgeThe uppermost horizontal line where two roof planes meet
HipThe sloped line where two roof planes meet at an outside corner
Cap-shingle centerlineThe reference line marking the center of the ridge or hip, used to keep cap shingles straight and evenly split between planes
ExposureThe portion of each cap shingle left uncovered by the next cap, set by the product instructions
Designated fastening zoneThe area of each cap shingle where the manufacturer permits fasteners, positioned so the next cap conceals them
Terminal pieceThe final cap at the end of a ridge or hip run, finished with a concealed-fastener or sealed-fastener detail
Non-vented ridgeA ridge capped directly without an underlying exhaust-vent system

Ridge-Cap Installation Record

Before beginning installation, record the controlling documents and site identification directly on the ridge-cap installation record:

Project / address: ______     Cap-shingle product: ______     Ridge condition (non-vented / vented, per Chapter 14): ______

Date started: ____________     Installer name: ____________

Prerequisites

Common Field Fundamentals

The ridge-cap system is the final layer in the shingle-lap water path established across every earlier chapter of the shingle field. Its job is to cover the exposed upper termination of both roof planes while keeping every fastener hidden beneath the next cap. That pattern — establish a reference, fasten in the concealed zone, cover with the next piece, repeat — governs the entire installation.

Ridge condition checkConfirm non-vented or Chapter 14 vent installed first
Field terminationVerify equal, secure termination of both adjoining roof planes
Starting endSet by prevailing wind or manufacturer-required direction
Centerline & exposureReference lines that keep caps straight and evenly split
Fastening zoneConcealed by the overlap of the next cap
Hip transitionsAdjust cap pieces gradually without splitting or distortion
Terminal pieceConcealed-fastener or sealed-fastener detail at the run's end
Reference methodEvery finding recorded against the manufacturer's cap-shingle instructions

Field Termination and Cap Preparation

Inspect the adjoining shingle fields for equal termination, adequate coverage, secure fastening, and a straight ridge line before selecting or preparing cap pieces. Trim or correct field shingles only by the approved method identified in Chapter 8 or Chapter 17. Select factory-made ridge caps or prepare cap pieces from approved shingles according to the product instructions, and reject cracked, overbent, cold-damaged, or incompatible cap pieces before installation begins.

RF-073 – RF-078

Ridge and Hip Cap Installation

Ridge-Cap Shingle Installation and Inspection Record

Difficulty: Intermediate

Estimated Time: 2–4 hours

Estimated Cost: Moderate

Finished Work: A straight, fully covered ridge or hip cap system with concealed fasteners and manufacturer-compliant overlaps

A. Finished-Work Specification

Deliverable: one continuous ridge or hip cap-shingle run installed from the confirmed starting end to the terminal piece, with centerline and exposure maintained throughout, fasteners concealed beneath each successive cap, hip geometry changes accommodated without splitting or distorting cap pieces, a completed terminal detail, and a documented inspection covering alignment, exposure, side coverage, fastener concealment, sealing, and damaged-tab condition.

B. Governing Documents

DocumentConfirmed CurrentNotes
Cap-shingle product instructions
Approved use / exposure / fastening schedule
Terminal-course detail
Ventilation plan (ridge-vent status)
Roof plan / hip and ridge layout

C. Acceptance Standards

CheckStandard
Field terminationAdjoining shingle fields terminate evenly, with adequate coverage and secure fastening, before capping begins
Ridge-vent statusConfirmed non-vented, or Chapter 14 ridge-vent system installed and accepted before capping
Cap-piece conditionFree of cracks, overbending, cold damage, or incompatibility; defective pieces rejected before installation
Centerline and exposureMarked before the first fastener and maintained within the manufacturer's tolerance along the full run
FasteningEach cap fastened through the designated zone with nails long enough to penetrate the required substrate, fully seated
OverlapEach cap conceals the fasteners of the piece beneath it by the specified overlap
Hip transitionsCap pieces adjusted gradually at geometry changes without splitting or distortion
Terminal pieceCompleted using the approved concealed-fastener or sealed-fastener detail
Finished ridge conditionStraight, fully covered, with no exposed fasteners, damaged tabs, or misaligned caps

D. Required Project Sequence

  1. Review the cap-shingle product, approved use, exposure, fastener length, fastening zone, wind direction, seal requirements, and terminal-course detail. Confirm the product instructions are current and record the exposure, fastener length, and fastening zone on the installation record before proceeding.
  2. Confirm whether the ridge is non-vented or whether Chapter 14 must first install a ridge-vent system. Check the ridge condition against the approved ventilation plan and record the confirmed condition on the installation record.
  3. Do not cap over a planned ridge-vent slot before the vent is installed. If the ridge is designed for a vent system, stop this chapter's work at that ridge line and route to Chapter 14 before continuing.
  4. Inspect the adjoining shingle fields for equal termination, adequate coverage, secure fastening, and a straight ridge line. Walk the full length of the ridge or hip from an approved position and record any uneven termination or loose fastening as a deficiency.
  5. Trim or correct field shingles only by the approved method. Refer any correction beyond the approved method to Chapter 8 or Chapter 17 before capping the affected section.
  6. Select factory-made ridge caps or prepare cap pieces from approved shingles according to the product instructions. Use only the cutting method, dimensions, and bend pattern specified by the manufacturer when field-preparing caps.
  7. Reject cracked, overbent, cold-damaged, or incompatible cap pieces. Set aside defective pieces before staging the accepted caps for installation.
  8. Establish the starting end based on prevailing wind or the manufacturer's required direction. Record the confirmed starting end and direction on the installation record.
  9. Mark the cap-shingle centerline and exposure references. Snap the centerline along the full ridge or hip length and mark exposure intervals from the starting end before fastening any cap.
  10. Position the first cap with the specified overhang or end treatment. Align the first cap to the centerline and starting-end reference and verify overhang before fastening.
  11. Fasten through the designated zones with nails long enough to penetrate the required substrate. Use only the fastener length, quantity, and location specified by the product instructions, and seat each fastener flush without cutting the cap surface.
  12. Cover each fastener with the next cap by the specified overlap. Position each successive cap so the overlap fully conceals the fasteners of the piece beneath it, and verify concealment before moving to the next piece.
  13. Continue along the ridge or hip while maintaining centerline, exposure, and side coverage. Check alignment against the centerline and exposure marks at regular intervals rather than only at the end of the run.
  14. Adjust cap pieces gradually at hips or geometry changes without splitting or distorting them. Make small, incremental adjustments across several pieces approaching a hip intersection or ridge-line change rather than forcing a single piece to absorb the full geometry change.
  15. Prepare the final cap or terminal piece using the approved concealed-fastener or sealed-fastener detail. Use only the terminal method specified by the product instructions for the confirmed ridge or hip condition.
  16. Apply hand sealant only where required by the product or weather conditions. Use only the manufacturer-approved adhesive at the specified locations, and do not substitute sealant for a required fastener or overlap.
  17. Inspect alignment, exposure, side coverage, fastener concealment, sealing, end treatment, and damaged tabs. Walk the full completed run from an approved position and record every finding against the acceptance standards above.
  18. Replace defective or misaligned caps before adhesive strips seal. Correct any finding from Step 17 while the affected caps can still be lifted and repositioned without damage.
  19. Clean the ridge and roof planes of cutoffs and loose fasteners. Remove cutoffs, loose nails, and packaging from the ridge, hip, and adjoining roof planes before documenting completion.
  20. Document product, starting direction, exposure, fastening, terminal detail, and inspection results. Photograph the completed ridge or hip and attach the images and measurements to the installation record.

Common Ridge-Cap Installation Checks

Apply the same checks to every ridge and hip line, regardless of length or roof configuration.

Complete the Ridge-Cap Inspection Record in the Inspection Checklist section below before closing out this chapter.

Image Placeholder
Recommended image: adjoining shingle fields terminating evenly at a ridge line, with the ridge-cap centerline chalked across both planes.
Image Placeholder
Recommended image: a cap shingle positioned at the starting end with the specified overhang, prior to fastening.
Image Placeholder
Recommended image: a cap shingle lifted at the trailing edge showing the designated fastening zone and seated nails before the next cap conceals them.
Image Placeholder
Recommended image: cap-shingle pieces adjusted gradually across a hip intersection, contrasted with an example of a single distorted or split piece.
Image Placeholder
Recommended image: the completed terminal cap piece showing the concealed-fastener or sealed-fastener detail.
Image Placeholder
Recommended image: a straight, fully covered ridge line viewed from ground level after cleanup.

Failure Points and Troubleshooting

Cleanup

This chapter ends with a clean, fully covered ridge and an organized installation record, not loose cutoffs and unresolved fastener findings.

Field Terms

Ridge Cap
The final row of shingles installed over a ridge or hip to cover and seal the termination of both adjoining roof planes.
Cap-Shingle Centerline
The reference line marking the center of the ridge or hip, used to keep cap shingles straight and evenly split between planes.
Exposure
The portion of each cap shingle left uncovered by the next cap, set by the product instructions.
Designated Fastening Zone
The area of each cap shingle where the manufacturer permits fasteners, positioned so the next cap conceals them.
Terminal Piece
The final cap at the end of a ridge or hip run, finished with a concealed-fastener or sealed-fastener detail.
Non-Vented Ridge
A ridge capped directly without an underlying exhaust-vent system.
Hip
The sloped line where two roof planes meet at an outside corner.
Ridge
The uppermost horizontal line where two roof planes meet.

Skill Check

  1. Why must the ridge-vent status be confirmed before any cap shingle is installed?
  2. What condition of the adjoining shingle fields must be verified before ridge-cap installation begins?
  3. Why must the cap-shingle centerline and exposure references be marked before the first fastener is driven?
  4. How does the overlap between successive cap shingles keep every fastener concealed?
  5. Why should hip-geometry changes be absorbed gradually across several cap pieces rather than forced into one piece?
  6. What distinguishes the terminal piece's fastening detail from the fastening method used along the rest of the run?
  7. What must a learner do upon finding a capped ridge-vent slot that was covered before the vent was installed?
  8. Why is hand-seal adhesive not an acceptable substitute for a required fastener or overlap?
  9. What six conditions must the final ridge inspection confirm?
  10. Why is the ridge cap considered the last opportunity to catch a field-shingle termination defect?

Competency Rubric

CompetencyIndependent Pass StandardNot DemonstratedWith AssistanceIndependently
RF-073Verifies adjoining shingle-field termination and corrects only by approved methods before capping
RF-074Selects or prepares ridge-cap shingles compatible with the field product and approved for the specific ridge or hip condition
RF-075Aligns cap shingles to centerline and exposure references maintained across the full run
RF-076Fastens ridge caps through the designated zone with correctly sized, fully seated fasteners
RF-077Overlaps caps by the specified amount so every fastener is concealed by the next piece
RF-078Inspects and documents the finished ridge for alignment, exposure, side coverage, fastener concealment, sealing, and tab condition

Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.

Inspection Checklist — Ridge-Cap Inspection Record

ItemCondition FoundCorrection RequiredCorrected (Y/N)Reinspection Result
Ridge-vent status confirmation
Field termination (both planes)
Cap-piece condition (rejects removed)
Centerline / exposure alignment
Fastener placement / seating
Overlap / fastener concealment
Hip transitions
Terminal-piece detail
Sealant (where required)
Cleanup (cutoffs / loose fasteners)

Ridge-cap completion decision: ______ (Complete / Conditional-Complete / Stop-Work)     Date: ____________     Installer name: ____________

Performance Check

With the ridge-cap run complete, review the finished ridge and the Ridge-Cap Inspection Record against the Acceptance Standards table and confirm both adjoining shingle fields terminated evenly before capping, the ridge-vent status was correctly confirmed, every cap piece is free of cracking or distortion, centerline and exposure are maintained within tolerance along the full run, every fastener is concealed by the correct overlap, hip transitions were adjusted gradually, the terminal piece uses the approved detail, and the ridge and roof planes are clean of cutoffs and loose fasteners. If any item cannot be verified, record it as an open item and issue a conditional-complete decision rather than a full completion decision.

Chapter Closeout

You have completed the ridge-cap installation chapter: covering and sealing a ridge or hip line with the roof's final shingle layer. This chapter required you to verify field termination and correct only by approved methods (RF-073), select or prepare compatible cap shingles (RF-074), align caps to centerline and exposure references (RF-075), fasten each cap through the designated zone (RF-076), overlap caps to conceal every fastener (RF-077), and inspect and document the finished ridge (RF-078).

You now have a documented, straight, fully covered ridge or hip cap system that closes the shingle-lap water path established across the entire field-shingle installation. Where this ridge carries a designed exhaust-vent system, this chapter's work coordinates directly with Chapter 14's ridge-vent installation and the required cap-shingle fastening over the vent.

Store the completed installation record, photographs, and inspection results with the project record. The Chapter 20 capstone references this record when capping the shed's ridge over its installed vent system.