Prepare and flash one new-construction window rough opening using the approved sill-pan and WRB-integration method, so the opening is dimensionally correct, drained, and fully flashed before the window is installed in Project 05.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework, disputes, or concealed defects.
Task-specific safety guidance for ordinary work hazards.
Serious injury or major structural consequence is possible.
Practical work-area safety: footing, debris, access, and exposure.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for sill-pan, flashing, and WRB systems.
Clearance, dimension, tolerance, and reference-point guidance.
This project qualifies you to prepare and flash one new-construction window rough opening using the approved sill-pan and water-resistive barrier (WRB) integration method before the window itself is installed. The finished work product is a dimensionally correct, drained, and fully flashed rough opening: a sloped or pan-drained sill, sealed corners, jamb flashing or jamb preparation in place, a prepared head interface, and the surrounding WRB integrated in the correct shingle-lap order, together with photographs documenting the completed condition.
You will review the window manufacturer's rough-opening and flashing requirements, recheck the opening accepted in Project 01 against those requirements, clean and prepare the sill and jambs, create or install the required outward sill slope, install and seal the sill-pan flashing, install jamb flashing or jamb preparation, prepare the head interface, integrate the surrounding WRB using the approved cut pattern, inspect every layer for continuity and drainage, and photograph the completed assembly before the window is set.
This project follows directly from the wall-sheathing readiness decision issued in Project 01 and the continuous WRB installed and seam-treated in Projects 02 and 03. It sits immediately before Project 05, which sets the window into the opening flashed here, and Project 06, which completes the window's exterior flange flashing and interior air seal.
Every window in this book depends on the flashing completed here. The sill pan installed in this project is what allows incidental water that reaches the sill, whether from wind-driven rain, condensation, or a future seal failure, to drain back out of the wall rather than into the framing below. The jamb and head preparation completed here also controls how cleanly the window's own flange flashing integrates in Project 06.
The water-shedding sequence practiced here — sill first, then jambs, then head, each layer overlapping the one before it in the direction water will travel — is the same sequence used at every other opening and penetration in this book, including the Chapter 7 door sill pan, the Chapter 9 door flashing, and the Chapter 16 penetration flashing.
This project covers:
This project does not authorize the learner to:
Any rough opening found outside the permitted adjustment range, structurally damaged, or missing required support must stop work at that opening until qualified review or correction is obtained.
Establish these references before any flashing work begins, and do not change them once the opening has passed inspection.
| Term | Definition |
|---|---|
| Sill pan | The sloped, drained flashing layer installed across the full rough-opening sill and extending up both jambs, installed in Steps 6–13 |
| Back dam | The raised interior edge of the sill pan that prevents water from moving inward toward the interior finish |
| End dam | The raised or formed edge at each end of the sill pan that prevents water from escaping around the jambs before reaching the exterior drainage edge |
| Drainage outlet | The exterior edge of the sill pan where water is intended to discharge onto the WRB, left open and unsealed |
| Jamb flashing | The flashing layer or preparation applied to each vertical side of the rough opening, lapping over the sill-pan upturns |
| Head flap | The temporarily secured upper WRB flap above the opening, preserved for integration with head flashing in a later project |
| Shingle-lap order | The water-shedding sequence in which each higher layer overlaps the layer below it: sill, then jambs, then head |
Before beginning flashing at this opening, record the controlling data directly on the rough-opening flashing record:
Opening ID: ______ Window schedule reference: ______ Sill-pan system specified: ______ Flashing product and lot/batch: ______
Date started: ____________ Installer name: ____________
Every opening flashed in this book, whether a window in this chapter or a door sill pan in Chapter 7, follows the same water-shedding order: sill first, then jambs, then head, with each layer overlapping the one installed before it and the WRB integrated around the assembly in the same direction. Learning that order here protects every later opening in this book.
The drainage outlet at the exterior edge of the sill pan must remain open across every step of this project. Do not seal it, tape over it, or create a reverse lap that directs water back into the wall. If a later step in this project or in Project 05 or 06 appears to require covering that edge, stop and confirm the detail against the manufacturer's instructions before proceeding.
Recheck rough-opening width, height, square, level, plumb, sill slope, and header condition immediately before flashing begins, even though the opening passed inspection in Project 01. Framing and sheathing can shift or be disturbed during WRB installation and seam treatment. Do not assume a previously accepted opening remains within tolerance without remeasuring it.
Do not flash an opening that is oversized, undersized, out of square beyond the permitted adjustment, structurally damaged, or missing required support. Flashing over a nonconforming opening conceals the defect and sets up a water-control failure that will not be visible again until the Chapter 19 full exterior inspection or an active leak. Stop work at that opening and obtain qualified review or correction first.
Do not leave the flashed opening exposed to rain or wind longer than necessary before the window is set in Project 05. Stage materials and sequence work so that each opening's flashing is completed and protected within the same work session whenever practical.
Confirm compatibility among the sill-pan membrane or preformed pan, primer, corner-sealing method, WRB, and window flange before beginning work. Do not substitute a flashing tape, primer, or liquid flashing not identified as compatible by the manufacturer's current instructions.
Required inspection hold-points before a window is set over completed rough-opening flashing vary by adopted code and jurisdiction. Verify the current requirement with the authority having jurisdiction and the general contractor before treating this project's inspection as the only required sign-off.
BE-019 – BE-024
Flashing / Water-Control Installation Qualification
Scope: one completed rough-opening flashing assembly for one scheduled window, including sill-pan flashing, sealed corners, jamb flashing or jamb preparation, head-flap preparation, and surrounding WRB integration.
| Document | Source | Confirmation Required |
|---|---|---|
| Window rough-opening requirements | Window manufacturer | Current instructions on site for this specific unit |
| Sill-pan system detail | Sill-pan manufacturer / window manufacturer | Product and installation method confirmed for this opening |
| Flashing product instructions | Flashing manufacturer | Primer, temperature limits, and lap requirements confirmed |
| Window and door schedule | Design professional / plan set | Opening identification, dimensions, and handing confirmed |
| Project 01 envelope-readiness record | Prior project record | Proceed or conditional-proceed status confirmed for this opening |
| Project 02–03 WRB and seam records | Prior project record | WRB and seam treatment confirmed complete at this opening |
| Check | Standard |
|---|---|
| Opening dimensions | Width, height, square, level, plumb, sill slope, and header condition confirmed within the permitted adjustment range immediately before flashing |
| Sill-pan continuity | One continuous sill-pan layer, without a seam in the drainage path, extending across the sill and up both jambs |
| Corner integrity | Back dam, end dams, and corners formed without wrinkles, voids, or incomplete coverage |
| Drainage outlet | Exterior edge of the sill pan open and unsealed, with a defined path to the exterior face of the WRB |
| Jamb and head preparation | Jamb flashing or preparation layers and the head-flap interface complete in the sequence required by the selected method |
| WRB integration | Surrounding WRB cut and lapped according to the approved pattern with no reverse laps |
| Documentation completeness | Photographs and the rough-opening flashing record completed before the window is installed |
Inspect the flashed rough opening using the same checks regardless of which elevation or opening it covers.
Complete the Rough-Opening Flashing Record in the Inspection Checklist section below before Project 05 begins.
Probable cause: the sill flashing was cut short of the controlled length and a second piece was added to reach the far jamb.
Confirmation: inspect the sill pan for any horizontal seam within the drainage path between the back dam and the exterior edge.
Correction: remove the sill pan and reinstall it using one continuous piece cut to the correct controlled length.
Reinspection: repeat the sill-pan continuity and drainage-path check across the full width of the opening.
Probable cause: the membrane was stretched through the corner instead of worked in by hand, or primer open time was not observed.
Confirmation: inspect the corner visually and by hand for full contact and adhesion across the entire formed area.
Correction: remove the affected section and reform the corner using the approved folding, gusset, patch, or liquid-flashing method.
Reinspection: repeat the corner-integrity check after the repair has reached the required condition.
Probable cause: the exterior sill-pan edge was taped or lapped under the WRB below it during jamb or WRB integration work.
Confirmation: inspect the exterior edge of the sill pan to confirm it remains open and laps over, not under, the WRB below the opening.
Correction: remove the sealing material or reverse lap and reinstall the edge so it discharges onto the WRB below.
Reinspection: repeat the drainage-outlet check before proceeding to jamb flashing.
Probable cause: framing or sheathing shifted during WRB installation or seam treatment, or the original Project 01 measurement was recorded incorrectly.
Confirmation: remeasure width, height, diagonals, level, plumb, and sill slope and compare against the window schedule and its permitted adjustment range.
Correction: stop flashing at this opening and obtain qualified review or correction before proceeding.
Reinspection: repeat the dimensional recheck after the documented correction is complete.
Probable cause: jamb flashing was measured and cut before the sill-pan height was finalized, or installed out of sequence.
Confirmation: inspect the transition between the sill-pan upturn and the base of the jamb flashing for a continuous, shingle-lapped overlap.
Correction: remove and reinstall the jamb flashing so it laps over the sill-pan upturn by the required amount.
Reinspection: repeat the jamb-to-sill transition check before integrating the surrounding WRB.
Probable cause: the opening flap was cut using the wrong pattern for the selected flashing method, or flaps were folded in the wrong order.
Confirmation: inspect every WRB flap and cut edge at the opening to confirm each higher layer overlaps the layer below it.
Correction: reposition or replace the affected flap using the approved cut pattern for the selected flashing method.
Reinspection: repeat the shingle-lap check around the full perimeter of the opening.
This project ends with a dimensionally correct, drained, and fully flashed rough opening and a documented flashing record, not with the window installed.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| BE-019 | Correctly prepares a window rough opening for flashing by verifying dimensions, condition, and structural support against the manufacturer's requirements | |||
| BE-020 | Installs sill-pan flashing that slopes outward, forms sealed corners, and establishes a defined drainage path to the exterior | |||
| BE-021 | Flashes the jambs or installs required jamb preparation layers in the correct sequence | |||
| BE-022 | Prepares the head opening interface without fastening through prohibited areas or disrupting the required sequence | |||
| BE-023 | Integrates the surrounding WRB using the approved cut pattern and shingle-lap order without reverse laps | |||
| BE-024 | Correctly inspects the completed water-shedding sequence for continuity, drainage, corner integrity, and dimensional accuracy, and documents the result |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Check | Plan Value / Requirement | Field Value | Within Tolerance (Y/N) | Correction (if any) |
|---|---|---|---|---|
| Opening dimensions recheck | Matches window schedule within permitted adjustment range | |||
| Sill slope | Slopes outward per manufacturer detail | |||
| Sill-pan continuity | One continuous piece, no seam in drainage path | |||
| Back dam / end dams | Formed and sealed at both corners | |||
| Drainage outlet | Open, unsealed, laps over WRB below | |||
| Jamb flashing / preparation | Laps over sill-pan upturn; complete both sides | |||
| Head flap preparation | Positioned per selected flashing method, unfastened at prohibited areas | |||
| WRB integration | Approved cut pattern, no reverse laps | |||
| Photographic documentation | Completed and labeled before window installation |
Open discrepancies attached: ____________ Responsible authority for each: ____________
Rough-opening flashing decision: ______ (Proceed/Conditional-Proceed/Stop-Work) Date: ____________ Installer name: ____________
With document review, opening recheck, sill-pan installation, jamb and head preparation, WRB integration, and inspection complete, review the opening against the Acceptance Standards table and confirm the sill pan is continuous and free of seams in the drainage path, corners are sealed without wrinkles or voids, the drainage outlet remains open, jamb and head preparation are complete in the required sequence, the surrounding WRB is integrated without reverse laps, and photographs and the rough-opening flashing record are complete. Complete and sign the rough-opening flashing record before the window is staged or installed for Project 05. If a discrepancy remains open, identify the responsible authority and required decision before proceeding.
You have completed the fourth project in the building-envelope sequence: flashing a window rough opening. This project required you to prepare the rough opening for flashing (BE-019), install a sloped, sealed, and drained sill-pan flashing system (BE-020), flash or prepare the jambs in the correct sequence (BE-021), prepare the head opening interface without disrupting later work (BE-022), integrate the surrounding WRB using the approved shingle-lap pattern (BE-023), and inspect and document the completed water-shedding sequence (BE-024).
You now have a dimensionally correct, drained, and fully flashed window rough opening with a signed rough-opening flashing record. That decision carries directly into the next project: setting, aligning, fastening, and function-testing the specified new-construction window in this flashed opening.
Protect the sill-pan drainage path, corner seals, and WRB integration established in this project. Project 05 sets the window into this opening and depends on every condition confirmed here.