Complete the exterior water-control layers and interior air seal around the Project 05 window without blocking its designed drainage paths, so the unit sheds water, drains its sill, and limits air leakage before rainscreen and siding work begins.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework, disputes, or concealed defects.
Task-specific safety guidance for ordinary work hazards.
Serious injury or major structural consequence is possible.
Practical work-area safety: footing, debris, access, and exposure.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for tapes, flashing, and foam or sealant.
Clearance, dimension, tolerance, and reference-point guidance.
This project qualifies you to complete the exterior flashing and interior air-seal layers around one new-construction window that was set, aligned, fastened, and function-tested in Project 05. The finished work product is a fully integrated window installation that sheds exterior water, preserves sill-pan drainage, limits air leakage at the rough-opening gap, and remains fully operational.
You will review the approved flashing sequence, confirm the window remains level, plumb, square, and secure, inspect the sill pan and lower flange, install jamb flashing tape from bottom to top, install head flashing and integrate the WRB head flap over it, and then work from the interior to install backer rod and low-expansion foam or sealant in the perimeter gap without disturbing the shims or blocking exterior drainage. The project ends with a full inspection of every lap, flashing layer, and air seal, and a photographed, documented record of the completed assembly.
This project assumes the Project 05 window installation has passed inspection and remains level, plumb, square, and operational. It sits immediately after Project 05 and before Project 07, which prepares the exterior-door sill pan on a separate opening.
The rough-opening flashing prepared in Project 04 and the window set and fastened in Project 05 both depend on this project to become a complete, water-shedding assembly. The jamb and head flashing installed here integrate with the WRB courses from Project 02 and 03, and the interior air seal completed here is the last opportunity to control air leakage at this opening before rainscreen furring in Project 10 and siding in Project 12 or 13 conceal the wall.
The shingle-lap sequence used here — sill, then jambs, then head, each layer overlapping the one below it — is the same drainage logic applied at every other opening and penetration in this book, including the door flashing in Project 09 and the penetration flashing in Project 16.
This project covers:
This project does not authorize the learner to:
Any condition that does not match the approved plans, or that suggests the window has shifted, racked, or lost operation since Project 05, must stop work at that opening until the condition is corrected and reinspected.
Establish these references before any flashing or sealing begins, and do not change them once installation starts.
| Term | Definition |
|---|---|
| Shingle-lap order | The bottom-to-top sequence in which each water-control layer overlaps the layer below it: sill, then jambs, then head |
| Flange | The nailing fin around the perimeter of the window unit, already fastened to the rough opening in Project 05 |
| Head flap | The WRB material left temporarily unfastened above the opening in Project 02, integrated over the head flashing in this project |
| Reverse lap | Any condition where an upper layer tucks behind a lower layer instead of overlapping it, directing water inward instead of outward |
| Interior perimeter gap | The shimmed space between the window frame and the rough-opening framing, air-sealed from the interior in this project |
| Sill-pan outlet | The designed exterior drainage opening at the base of the sill pan that must remain unobstructed throughout this project |
Before beginning any flashing or air-seal work, record the controlling data directly on the window flashing and air-seal record:
Window/opening ID: ______ Flashing tape product and width: ______ Head-flashing component: ______ Air-seal product: ______
Date started: ____________ Builder name: ____________
Every water-control detail in this book follows the same shingle-lap logic: the lowest layer is installed first, and each layer above it overlaps the one below rather than tucking behind it. This project applies that logic at the window flange and head, continuing the sequence established at the sill pan in Project 04 and carried forward at the door in Project 09 and at penetrations in Project 16.
This project asks you to do two things that can seem contradictory: seal the wall against air leakage while keeping it open to drainage. The distinction is location. Air sealing happens at the interior perimeter gap, behind the drainage plane. Drainage happens at the exterior sill-pan outlet and any designed weep. Never let an exterior tape, primer, or sealant bridge the sill-pan outlet, and never let the interior air seal extend into a location where it would block water that has already entered the wall from draining back out.
Recheck sill level, jamb plumb, head level, and frame square against the Project 05 installation record before installing any tape or flashing. Do not assume the window remains in the same condition it was left in; confirm it directly. Covering a flange over a window that has shifted conceals the problem instead of correcting it.
Do not tape or seal across the exterior sill drainage opening unless the approved system specifically requires it. Bridging this opening with tape, primer, or sealant traps water inside the sill pan with no path to the exterior, turning a designed drainage feature into a reservoir that will eventually leak into the wall or interior finishes.
Clear debris from the perimeter gap before installing backer rod or foam, and confirm shims remain in their approved locations. Do not reach into the gap with unprotected hands where shim edges or fastener points are exposed.
Use only the flashing tape, primer, head-flashing component, and interior air-seal product identified as compatible by the window and WRB manufacturers. Confirm temperature and substrate limits for tape adhesion and primer cure before beginning work in cold or damp conditions.
Required air-sealing methods, materials, and inspection sign-offs at window rough openings vary by adopted energy code and jurisdiction. Verify the current requirement with the authority having jurisdiction before treating the interior air seal as complete.
BE-031 – BE-036
Flashing / Sealing / Air-Barrier Integration Qualification
Scope: one completed window flashing and air-seal assembly, covering the jamb flashing, head flashing, WRB head-flap integration, and interior perimeter air seal for the Project 05 window installation.
| Document | Source | Confirmation Required |
|---|---|---|
| Window installation record | Project 05 record | Confirmed level, plumb, square, fastened, and operational |
| Flashing tape and head-flashing instructions | Window and WRB manufacturers | Tape width, overlap distance, primer requirement, and head-flashing detail confirmed |
| Interior air-seal instructions | Foam or sealant manufacturer | Product, application method, and cure or expansion limits confirmed |
| Rough-opening flashing record | Project 04 record | Confirmed undamaged and passed inspection |
| Change documentation | Design professional / general contractor | All approved field changes incorporated |
| Check | Standard |
|---|---|
| Window condition | Level, plumb, square, securely fastened, and operational before and after flashing |
| Jamb flashing | Installed bottom to top, full adhesive contact, required overlap onto sill flashing, no wrinkles or fishmouths |
| Head flashing | Extends beyond both jambs by the approved distance; WRB head flap integrated over it in shingle-lap order |
| Sill drainage | Sill-pan outlet remains open and unobstructed by tape, primer, or sealant |
| Interior air seal | Backer rod and foam or sealant fill the perimeter gap without bowing the frame; shims remain in approved locations |
| Operation | Sash or panel operates freely after flashing and after air-seal cure |
Inspect the completed window flashing and air-seal assembly using the same checks regardless of which opening it covers.
Complete the Window Flashing and Air-Seal Record in the Inspection Checklist section below before beginning Project 07.
Probable cause: the tape was applied too quickly without working out air pockets, or it was applied outside the manufacturer's temperature range.
Confirmation: inspect the affected section for trapped air or incomplete adhesive contact.
Correction: remove and replace the affected section using the approved patch or reinstallation method; do not smooth a wrinkle over trapped air.
Reinspection: repeat the adhesion and contact check across the full jamb or head section after correction.
Probable cause: the head-flashing component was cut short, or the required extension distance was measured incorrectly.
Confirmation: measure the installed extension on each side against the approved detail.
Correction: remove and replace the head-flashing component with one cut to the correct length.
Reinspection: repeat the extension measurement on both sides after replacement.
Probable cause: the sill-pan outlet was not clearly marked before nearby tape or sealant work began.
Confirmation: inspect the sill-pan outlet for tape, primer, or sealant residue blocking the opening.
Correction: remove the obstructing material without damaging the sill pan and confirm the outlet drains freely.
Reinspection: repeat the drainage check by confirming water introduced at the sill pan exits through the outlet.
Probable cause: excessive foam expansion pressure at the perimeter gap, or foam applied faster than the manufacturer's fill rate.
Confirmation: operate the sash or panel and compare resistance against the pre-foam operation check.
Correction: remove the affected foam section and reapply using controlled passes with adequate expansion room, per manufacturer instructions.
Reinspection: recheck frame dimensions and operation after the replacement foam has cured.
Probable cause: the shim was disturbed during flange-flashing work or during handling between Project 05 and this project.
Confirmation: inspect each approved shim location and compare against the Project 05 installation record.
Correction: reinstall or replace the shim at the approved location before proceeding with the air seal.
Reinspection: recheck frame level, plumb, and square after the shim is corrected.
This project ends with a flashed, drained, air-sealed, and operational window installation, not with rainscreen, siding, or trim installed.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| BE-031 | Applies self-adhered flashing tape to the window flange in the correct shingle-lap sequence | |||
| BE-032 | Integrates rigid or flexible head flashing above the window so water from above sheds outward over the assembly | |||
| BE-033 | Seals the side flanges with compatible flashing tape while maintaining full contact and avoiding wrinkles or fishmouths | |||
| BE-034 | Maintains the window's designed weep paths and sill-pan drainage outlet throughout flashing and sealing | |||
| BE-035 | Air-seals the interior perimeter gap using backer rod and low-expansion foam or an approved sealant without bowing the frame | |||
| BE-036 | Inspects the completed window water-control and air-seal assembly and correctly identifies and corrects failed laps, blocked drainage, or bowed frames |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Check | Plan Value / Requirement | Field Value | Within Tolerance (Y/N) | Correction (if any) |
|---|---|---|---|---|
| Window condition before flashing | Level, plumb, square, fastened, operational | |||
| Jamb flashing overlap onto sill | Matches approved detail | |||
| Jamb flashing contact/wrinkles | Full contact, no wrinkles or fishmouths | |||
| Head flashing extension beyond jambs | Matches approved distance | |||
| WRB head-flap integration | Shingle-lap order over head flashing | |||
| Sill-pan outlet condition | Open and unobstructed | |||
| Interior perimeter gap / shims | Clear of debris, shims in approved locations | |||
| Air-seal application | No bowing, controlled fill, drainage separation maintained | |||
| Window operation after air seal | Free sash or panel movement |
Open discrepancies attached: ____________ Responsible authority for each: ____________
Window flashing and air-seal decision: ______ (Proceed/Conditional-Proceed/Stop-Work) Date: ____________ Builder name: ____________
With review, pre-flashing verification, jamb flashing, head flashing, interior air sealing, and inspection complete, review the assembly against the Acceptance Standards table and confirm the window remains level, plumb, square, and operational, jamb and head flashing are installed in correct shingle-lap order with full contact and the required overlaps, the sill-pan outlet remains open and unobstructed, and the interior air seal fills the perimeter gap without bowing the frame or blocking exterior drainage. Complete and sign the window flashing and air-seal record before rainscreen furring is installed in Project 10. If a discrepancy remains open, identify the responsible authority and required correction before proceeding.
You have completed the sixth project in the building-envelope sequence: flashing and sealing an installed window. This project required you to apply flashing tape in correct shingle-lap sequence (BE-031), integrate head flashing so water sheds outward (BE-032), seal the side flanges without wrinkles or fishmouths (BE-033), maintain the window's designed weep paths and sill-pan drainage (BE-034), air-seal the interior perimeter gap without bowing the frame (BE-035), and inspect the completed assembly for failed laps, blocked drainage, or bowed frames (BE-036).
You now have a fully integrated window installation that sheds exterior water, preserves sill drainage, limits air leakage, and remains operational. That completed assembly carries directly into the next project: preparing a drained sill-pan system in an exterior-door rough opening.
Protect the completed flashing, drainage paths, and air seal established in this project. Project 07 begins door sill-pan preparation on a separate opening, and the full exterior inspection in Project 19 will verify this window assembly remains intact.