Project 20 — Capstone
Integrate every prior competency in this book into one rough-in, inspection, finish, and closeout sequence for a small bathroom serving one lavatory and one toilet, using an approved plan, a rough-in inspection before wall closure, and a finish inspection before handoff.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become water damage, injury, or failed inspections.
Task-specific safety guidance for ordinary work hazards.
Serious injury, scalding, electrical shock, or major property damage is possible.
Practical work-area safety: lighting, footing, ventilation, and housekeeping.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for valves, tools, and equipment.
Reference-point, clearance, and verification guidance.
This capstone project qualifies you to rough-in, inspect, finish, test, and document a small bathroom plumbing system serving one lavatory and one toilet. The finished work product is one inspected, functional small-bathroom plumbing system: tested water-supply piping, an approved DWV and venting arrangement, accessible shutoffs, correctly installed fixtures, a complete rough-in inspection record, a complete finish inspection record, and a formal closeout package.
You will obtain and confirm the approved bathroom plan; mark fixture and piping references; install the toilet and lavatory drain, trap, and vent rough-in; install the hot and cold supply branches; cap and test the rough-in; pass a rough-in inspection before wall closure; protect the system during finish work; set the closet flange and fixture stops at finished-floor height; install the toilet, faucet, pop-up drain, and P-trap using the exact procedures from Chapters 9, 10, and 11; restore water and test the completed system; pass a finish inspection; and complete the documentation and handoff required to close out the project.
This is the last project in the book. It does not introduce a new joining method, fixture type, or test procedure. It integrates the shutoff and work-area discipline of Chapter 1, the system-mapping habit of Chapter 2, the pipe-preparation standard of Chapter 3, the supply-piping methods of Chapters 4 through 7, the DWV assembly standard of Chapter 8, the trap-installation procedure of Chapter 9, the faucet and pop-up procedure of Chapter 10, and the toilet-setting procedure of Chapter 11 into one continuous, inspected installation.
Every project in this book has been building toward this integration. Chapter 1 supplied the isolation and work-area discipline used at every stage of this project. Chapter 2 supplied the system-mapping habit used to confirm the approved plan against field conditions. Chapters 3 through 7 supplied the pipe-preparation and supply-piping methods used for the hot and cold branches. Chapter 8 supplied the PVC DWV assembly standard used for the drain, trap arm, and vent. Chapter 9 supplied the P-trap installation procedure. Chapter 10 supplied the faucet and pop-up drain procedure. Chapter 11 supplied the toilet-setting procedure. This capstone does not replace any of those procedures — it sequences them into one inspected system.
The rough-in inspection and finish inspection completed in this project are the same two-stage inspection discipline used on any real bathroom plumbing installation: concealed work is verified before it is covered, and completed work is verified before it is handed off.
This project covers:
This project does not authorize the learner to:
This capstone must be installed inside a permitted small bathroom installation, a code-compliant training structure, or a professionally supervised plumbing practice wall designed for the specified fixtures, and only where the approved plans provide the required framing, fixture clearances, water supply, DWV route, venting, and inspection access.
Establish these references before rough-in begins, and do not change the defined project boundary mid-project.
| Term | Definition |
|---|---|
| Approved bathroom plan | The plumbing plan, fixture schedule, and DWV/vent design that controls pipe size, fitting type, slope, venting, and fixture clearances for this project |
| Rough-in stage | All work completed before the required rough-in inspection: DWV assembly, supply branches, shutoffs, and capped openings |
| Finish stage | All work completed after the rough-in inspection passes and wall finishing is complete: flange setting, fixture stops, and fixture installation |
| Rough-in inspection | The required inspection of concealed piping, supports, and test results completed before wall closure |
| Finish inspection | The required inspection of completed fixture operation, drainage, and absence of leakage completed before project closeout |
| Learner-assigned work | The rough-in and finish tasks defined in Step 3 of the Work Order as within the learner's authorized scope |
Before any framing hole is drilled or any pipe is cut, record the approved plan reference and the learner/professional work split directly on the Rough-In and Finish Inspection Record:
Approved plan reference: ______ Fixture schedule reference: ______ Permit number (if applicable): ______
Learner-assigned work: ______ Professional-reserved work: ______ Date started: ____________ Builder name: ____________
This capstone follows the same four-part sequence introduced in Chapter 1 — identify, isolate, drain, protect — at every stage, and adds a second discipline required only at this scale: rough-in before finish, and inspection before concealment or handoff.
This project requires two separate inspections at two separate stages. The rough-in inspection verifies concealed piping, supports, and test results before any wall material is installed over the work. The finish inspection verifies completed fixture operation, drainage performance, and absence of leakage before the project is closed out. Do not combine, skip, or reorder these two inspections.
Confirm every pipe size, fitting type, slope, vent arrangement, and fixture clearance against the approved bathroom plan and fixture schedule before cutting any framing member or pipe. Do not infer a dimension or arrangement that the plan does not state.
Do not conceal supply, drain, vent, or fixture connections until the rough-in pressure test, DWV test, and required rough-in inspection have passed. Concealing untested work risks undetected leakage, structural water damage, and failed finish inspection.
Coordinate framing holes, backing, and protection plates with the approved framing plan. Do not cut, notch, or drill a structural member beyond what the framing plan authorizes. Verify electrical circuits and other utilities in the work area before drilling.
Local jurisdictions vary in scheduling and documentation requirements for rough-in and finish plumbing inspections. Confirm the required inspection sequence, notice period, and documentation with the authority having jurisdiction before wall closure and before fixture handoff.
PL-115 – PL-120
Capstone Integration / Rough-In / Finish / Inspection / Closeout Qualification
Quantity: one rough-in and finish installation serving one lavatory and one toilet, built to the approved bathroom plan and fixture schedule, tested at rough-in and finish stage, inspected at rough-in and finish stage, and documented with a complete closeout package.
| Milestone | Target Condition | Verification Method |
|---|---|---|
| Plan confirmation | Approved bathroom plan, fixture schedule, and permit conditions confirmed before rough-in begins | Written record on capstone worksheet |
| DWV rough-in | Toilet drain, lavatory drain, trap arm, and vent installed per the approved fitting pattern, slope, and vent relationship | Visual inspection and dry-fit record per Chapter 8 procedure |
| Supply rough-in | Hot and cold branches installed using the approved method and supported per plan | Visual inspection per Chapters 4–7 procedure |
| Rough-in test | Supply pressure test and DWV test both pass at the specified pressure and duration | Gauge reading and observed leak check |
| Rough-in inspection | Required inspection completed and approved before wall closure | Signed inspection approval |
| Finish installation | Closet flange, fixture stops, toilet, faucet, pop-up drain, and P-trap installed per Chapters 9–11 | Visual inspection and operational test |
| Finish test | Static and operating leak tests pass on every disturbed connection | Direct observation during fill-and-release testing |
| Finish inspection and closeout | Required finish inspection passed; documentation complete | Signed inspection approval and completed closeout record |
| Check | Standard |
|---|---|
| Plan compliance | Every pipe size, fitting type, slope, vent arrangement, and fixture clearance matches the approved plan and fixture schedule |
| Rough-in test | Supply pressure test and DWV test both pass at the specified pressure and duration with no observed leakage |
| Rough-in inspection | Required inspection completed and approved before any wall material is installed over the work |
| Finish installation | Toilet, faucet, pop-up drain, and P-trap installed and pass the acceptance standards defined in Chapters 9, 10, and 11 |
| Finish test | No leakage observed at any disturbed connection under static and operating conditions during repeated testing |
| Finish inspection | Required finish inspection completed and approved before closeout |
| Documentation | Rough-In and Finish Inspection Record set complete with plan reference, test results, both inspection approvals, and punch-list correction record |
Inspect the completed capstone project using the same two-stage discipline regardless of which supply-joining method or DWV routing the approved plan specifies.
Complete the Rough-In and Finish Inspection Record in the Inspection Checklist section below before declaring the capstone project closed out.
Probable cause: an incomplete crimp, clamp, solder joint, push-fit engagement, or compression connection made during supply rough-in.
Confirmation: depressurize, inspect each connection using the method specified in the applicable supply chapter, and isolate the failed joint.
Correction: remake or replace the failed connection using the exact correction method specified in Chapters 4 through 7 for that joining system.
Reinspection: repressurize and repeat the full rough-in pressure test before proceeding to the DWV test.
Probable cause: an incompletely cemented PVC joint, incorrect slope, or a fitting rotated out of the approved direction.
Confirmation: inspect the joint, slope, and fitting orientation against the approved plan using the Chapter 8 inspection method.
Correction: cut out and rebuild the failed joint following the Chapter 8 procedure; do not coat a leaking joint externally with cement or sealant.
Reinspection: repeat the DWV test after the joint has cured for the manufacturer-controlled time.
Probable cause: a support spacing, fitting pattern, slope, or clearance that does not match the approved plan or adopted code.
Confirmation: compare the identified deficiency against the approved plan and the inspector's written finding.
Correction: correct the deficiency using the controlled repair method for the affected system before requesting reinspection.
Reinspection: obtain a new rough-in inspection approval before any wall material is installed.
Probable cause: the toilet, faucet, pop-up drain, or P-trap was not installed to the acceptance standard defined in its controlling chapter.
Confirmation: re-run the exact test specified in the Chapter 9, 10, or 11 acceptance standards for the affected fixture.
Correction: apply the correction procedure from the controlling chapter for that fixture; do not invent a substitute correction.
Reinspection: repeat the fixture-specific test and the overall finish leak test before requesting the finish inspection.
Probable cause: a fixture connection, drainage condition, or documentation item that does not meet the finish acceptance standards.
Confirmation: compare the identified deficiency against the Acceptance Standards table and the inspector's written finding.
Correction: correct the deficiency, complete the punch list entry, and retest the affected connection.
Reinspection: obtain a new finish inspection approval before closeout.
Probable cause: a required photograph, test record, or inspection approval was not compiled during rough-in or finish stage.
Confirmation: review the Rough-In and Finish Inspection Record set against the Material Takeoff and Acceptance Standards requirements.
Correction: locate or reconstruct the missing record; if concealed piping cannot be verified, escalate to the authority having jurisdiction before closeout.
Reinspection: confirm the completed record set before handing off the project.
This project ends with a functional, inspected bathroom plumbing system handed off with complete documentation.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| PL-115 | Integrates the water-supply layout with the approved bathroom plan and fixture schedule, confirmed by rough-in inspection approval | |||
| PL-116 | Integrates the DWV layout, including drain, trap, vent, and cleanout arrangement, with the approved plan, confirmed by rough-in inspection approval | |||
| PL-117 | Installs and verifies fixture shutoffs serving the lavatory and toilet, confirmed by operation through full range and accessible location | |||
| PL-118 | Installs the sink drain, toilet connection, and faucet using the exact procedures established in Chapters 9, 10, and 11, confirmed against each chapter's acceptance standards | |||
| PL-119 | Completes rough-in and finish leak testing and passes the required rough-in and finish inspections, confirmed by signed inspection approvals | |||
| PL-120 | Completes plumbing closeout documentation for the finished bathroom system, confirmed by a complete Rough-In and Finish Inspection Record set |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Target Condition | Result | Pass/Fail | Correction (if any) |
|---|---|---|---|---|
| Plan compliance | Pipe size, fitting type, slope, vent arrangement, and fixture clearances match the approved plan | |||
| Rough-in supply test | Passes at specified pressure and duration with no observed leakage | |||
| Rough-in DWV test | Passes at specified test method with no observed leakage | |||
| Rough-in inspection | Completed and approved before wall closure | |||
| Finish installation | Toilet, faucet, pop-up drain, and P-trap meet Chapters 9–11 acceptance standards | |||
| Finish leak test | No leakage at any disturbed connection under static and operating conditions | |||
| Finish inspection | Completed and approved before closeout | |||
| Documentation | Complete plan reference, test records, photographs, inspection approvals, and punch-list correction record |
Unresolved deficiencies and correction plan: ____________________________________________
Bathroom system declared ready for handoff: ______ (Pass/Fail) Date: ____________ Builder name: ____________
With rough-in complete, both required tests passed, the rough-in inspection approved, finish fixtures installed and tested, and the finish inspection approved, review the finished closeout record against the Acceptance Standards table and confirm every pipe size, fitting type, slope, vent arrangement, and fixture clearance matches the approved plan, the rough-in supply and DWV tests passed with no observed leakage, the rough-in inspection was approved before wall closure, the toilet, faucet, pop-up drain, and P-trap each meet their controlling chapter's acceptance standards, no leakage was observed at any disturbed connection during finish testing, and the finish inspection was approved before closeout. Complete the Rough-In and Finish Inspection Record and correct any failed item before declaring the capstone project complete. If an item fails, identify whether the error occurred in plan compliance, rough-in assembly, rough-in testing, finish installation, finish testing, or documentation before correcting it and re-running the affected check.
You have completed the capstone project of the residential plumbing sequence: rough-in and finish of a small bathroom plumbing system serving one lavatory and one toilet. This project required you to integrate water supply, DWV layout, fixture shutoffs, sink drain, toilet connection, faucet installation, leak testing, inspection, and plumbing closeout (PL-115 through PL-120) using the isolation, mapping, preparation, joining, DWV, trap, faucet, and toilet-setting competencies established across all nineteen prior projects.
You now have a documented, inspected, functional bathroom plumbing system and a complete closeout record demonstrating every competency in Book 7, PL-001 through PL-120.
Retain the complete Rough-In and Finish Inspection Record set, the approved bathroom plan, and all test and inspection documentation as the permanent record of this capstone project.