Safety Cue
Task-specific safety guidance for ordinary work hazards.
Project 08
Complete and verify the equipment-grounding and metal-box bonding path for one de-energized branch-circuit assembly, using listed grounding screws, clips, and connectors, so that every device and metal enclosure installed later in this book shares one continuous, isolated, and tested grounding path back to the source.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become shock, arc flash, or an unproven grounding path.
Task-specific safety guidance for ordinary work hazards.
Serious injury, shock, electrocution, or arc flash is possible.
Practical work-area safety: lighting, footing, access, and housekeeping.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for grounding screws, clips, and connectors.
Reference-point, verification, and continuity-test guidance.
This project qualifies you to complete and verify the equipment-grounding and metal-box bonding path for one de-energized branch-circuit assembly. The finished work product is one metal box, correctly bonded with a listed grounding screw or clip, containing a joined equipment-grounding splice, a box-bonding pigtail, and a device-grounding pigtail where required, with continuity verified from the device yoke and metal box back to the branch equipment-grounding path by a de-energized continuity test.
You will identify each equipment-grounding conductor and distinguish it from the grounded neutral conductor; install a listed grounding screw, clip, or bonding device in the metal box; join incoming and outgoing equipment-grounding conductors; add box-bonding and device-grounding pigtails; terminate them at the correct points; keep the neutral conductor isolated from the box and grounding path; and verify continuity with an approved meter before reassembling the box.
This project builds directly on the box installation of Chapters 3 and 4, the connectors of Chapter 5, the cable of Chapter 6, and the splicing and pigtailing of Chapter 7. It is a prerequisite for every device installed later in this book — the duplex receptacle of Chapter 9, the GFCI receptacle of Chapter 10, the switches and fixtures of Chapters 11 through 15, and the Chapter 20 capstone all depend on a metal box that has already been correctly bonded and grounded using this exact procedure.
The grounding and bonding work performed here is what makes a metal box, a device, and every later fixture in this book safe to touch under a fault condition. A box with cable connectors seated and conductors spliced, as completed in Chapters 5 through 7, is not yet a safe assembly until its metal parts are bonded and its equipment-grounding path is proven continuous. Every receptacle, switch, fixture, fan, and exterior device installed in Chapters 9 through 15 terminates its grounding conductor at the pigtail and grounding screw installed in this chapter.
The de-energized continuity test taught here is the same verification method used again in the Chapter 17 diagnostic project, where an open or high-resistance grounding path is one of the conditions a learner must be able to recognize and correct.
This project covers:
This project does not authorize the learner to:
Any grounding path that fails the continuity test in this chapter must be corrected before the box is reassembled or the assigned device is installed.
Establish these references before any conductor is joined or terminated, and do not change the defined grounding scheme mid-project.
| Term | Definition |
|---|---|
| Equipment-grounding conductor | The bare or green-insulated conductor that provides a fault-current path back to the source; not the same conductor as the grounded neutral |
| Box-bonding pigtail | The short conductor connecting the metal box's grounding screw or clip to the joined equipment-grounding conductors |
| Device-grounding pigtail | The short conductor connecting the device's green grounding terminal to the joined equipment-grounding conductors, separate from the box-bonding pigtail where required |
| Bonding point | The location where the box, device, and equipment-grounding conductors are joined to a common, continuous path |
| Bootleg ground | An improper jumper connecting the neutral terminal to the grounding terminal or metal box in place of a real equipment-grounding path; never used in this project |
| Continuity test | A de-energized resistance measurement confirming an unbroken conductive path from the device yoke and metal box to the branch equipment-grounding path |
Before joining any grounding conductor, record the assembly identity and design basis directly on the Grounding and Bonding Verification Worksheet:
Work boundary (box / device location): ______ Box type: ______ Grounding method (screw / clip / bonding device): ______
Wiring method and conductor material: ______ Device-grounding pigtail required: ______ (Yes/No) Date started: ____________ Builder name: ____________
Every metal box in this book depends on the same grounding logic: identify the equipment-grounding conductor, bond the box to it with a listed device, pigtail the device to it separately where required, and prove the path continuous before covering or energizing anything.
Identify each conductor from the approved circuit documentation before touching any terminal. The equipment-grounding conductor is bare or green-insulated and carries fault current back to the source; it is never the same conductor as the grounded neutral, and the two must remain isolated from each other downstream of the service bonding point. Confusing the two, or bonding them together at a device box, creates a bootleg ground and a false-safe condition.
Do not connect the neutral conductor to the grounding terminal, the metal box, or the equipment-grounding conductor at any point downstream of the service bonding point. A bootleg ground can allow a plug-in tester to show a false "correctly wired" result while leaving the box and device frame energized under a fault condition. This is a stop-work condition if discovered on existing wiring; correct it before continuing.
Use only a listed green grounding screw, grounding clip, or bonding device manufactured for equipment grounding. Never substitute a sheet-metal screw, a device mounting screw, or any unlisted fastener as the grounding connection. Follow the connector manufacturer's instructions for conductor range, stripping length, and installation method.
A grounding conductor that is connected but not tested has not been verified. Perform the de-energized continuity test using an approved meter and isolated test conditions, confirming continuity from the device yoke and metal box all the way to the branch equipment-grounding path. Investigate and correct any open, high-resistance, or uncertain reading before energization.
Confirm the circuit is de-energized using the live-dead-live procedure before removing any cover or touching any conductor. Re-verify de-energization if work is interrupted and resumed, or if there is any doubt about which circuit is present at the box.
EL-043 – EL-048
Grounding / Bonding / Continuity Verification Qualification
Quantity: one metal box assembly, bonded with a listed grounding screw, clip, or bonding device; equipment-grounding conductors joined with an approved connector; box-bonding pigtail and device-grounding pigtail installed as required by the design; continuity verified from the device yoke and metal box to the branch equipment-grounding path; and documented on one completed Grounding and Bonding Verification Worksheet.
| Component | Quantity | Material | Finished Size | Preparation |
|---|---|---|---|---|
| Grounding screw or clip | 1 per metal box | Listed green grounding screw or grounding clip per manufacturer instructions | As supplied by manufacturer | Installed in the box's designated grounding hole or slot; not substituted with a sheet-metal or device-mounting screw |
| Box-bonding pigtail | 1 per metal box | Conductor material and gauge matching the branch equipment-grounding conductor | Length sufficient to reach the grounding screw with the required free length in the box | Stripped to the connector-controlled length; one end at the grounding screw, one end at the grounding splice |
| Device-grounding pigtail | 1 per device, where required | Conductor material and gauge matching the branch equipment-grounding conductor | Length sufficient to reach the device green terminal with the required free length | Stripped to the connector-controlled length; one end at the device green terminal, one end at the grounding splice |
| Grounding splice connector | 1 per grounding splice point | Listed wire connector rated for the conductor count, material, and gauge present | As supplied by manufacturer | Installed per manufacturer's twist, lever, push-in, or crimp method; not reused if single-use |
| Check | Standard |
|---|---|
| Conductor identification | Equipment-grounding conductors correctly identified and kept isolated from grounded neutral conductors throughout the assembly |
| Box bonding | Listed grounding screw, clip, or bonding device installed in the metal box; no sheet-metal, device-mounting, or unlisted fastener used |
| Splice condition | Incoming and outgoing equipment-grounding conductors joined with a listed connector, correctly seated with no exposed copper beyond the connector |
| Pigtail termination | Box pigtail terminated at the grounding screw or device; device pigtail terminated at the green terminal with no more conductors under the terminal than listed |
| Neutral isolation | No neutral-to-ground jumper or bootleg ground present anywhere in the assembly |
| Continuity | De-energized continuity test confirms an unbroken path from the device yoke and metal box to the branch equipment-grounding path |
| Documentation | Grounding and Bonding Verification Worksheet complete with components, continuity results, and any corrections recorded |
Inspect every completed grounding assembly using the same checks regardless of which box, device, or circuit the project involves.
Complete the Grounding and Bonding Verification Worksheet in the Inspection Checklist section below before beginning Project 09.
Probable cause: a loose or missing grounding screw, an unjoined equipment-grounding conductor, a broken pigtail, or a connector that failed to seat.
Confirmation: re-verify the circuit is de-energized, then inspect the grounding screw, splice, and each pigtail termination one at a time.
Correction: reseat or replace the grounding screw, re-splice the equipment-grounding conductors with a new listed connector, and reterminate any loose pigtail.
Reinspection: repeat the de-energized continuity test from the device yoke and metal box to the branch equipment-grounding path.
Probable cause: corrosion or paint at the bonding point, a loosely tightened grounding screw, or a connector rated for a different conductor range than what is installed.
Confirmation: inspect the bonding surface for paint, corrosion, or debris, and check connector listing against the actual conductor count and size.
Correction: clean the designated bonding location, retighten the grounding screw to a firm, fully seated condition, or replace the connector with one listed for the present conductors.
Reinspection: repeat the continuity test and confirm a low-resistance result.
Probable cause: a prior installation connected the neutral terminal to the grounding terminal or metal box instead of running a real equipment-grounding conductor.
Confirmation: trace the neutral and grounding conductors separately back toward the source and confirm whether they are joined at any point downstream of the service bonding point.
Correction: remove the improper jumper immediately and install a correct equipment-grounding conductor, splice, and pigtail per this chapter's procedure; treat the discovery as a stop-work condition until corrected.
Reinspection: repeat the de-energized continuity test and confirm the neutral and grounding paths remain isolated from each other.
Probable cause: the device-grounding pigtail was omitted, or the device was wired as the only path between the box bonding and the branch grounding conductor.
Confirmation: inspect whether the box-bonding pigtail is independently connected to the grounding splice or depends on the device being present.
Correction: install a separate box-bonding pigtail terminated at the grounding screw, independent of the device-grounding pigtail, per the approved design.
Reinspection: repeat the continuity test with the device disconnected from the box to confirm the box remains bonded independently.
Probable cause: a damaged or wrong-size grounding screw, a stripped hole, or debris in the designated bonding location.
Confirmation: inspect the screw, clip, and bonding hole for damage, incorrect size, or obstruction.
Correction: replace the grounding screw or clip with the correct listed part for the box, and clear any obstruction from the bonding location before reinstalling.
Reinspection: confirm the grounding screw or clip seats fully and repeat the continuity test.
This project ends with the grounding and bonding path complete, tested, and either covered or ready for the assigned device installation.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| EL-043 | Identifies each equipment-grounding conductor in a branch-circuit assembly and distinguishes it from the grounded neutral conductor | |||
| EL-044 | Installs a listed grounding screw, grounding clip, or approved bonding device in a metal box without substituting an unlisted fastener | |||
| EL-045 | Bonds a metal box by joining incoming and outgoing equipment-grounding conductors with an approved connector and pigtail | |||
| EL-046 | Attaches device-grounding pigtails at the green grounding terminal without exceeding the terminal's listed conductor limit | |||
| EL-047 | Verifies grounding continuity from the device yoke and metal box to the branch equipment-grounding path using a de-energized continuity test | |||
| EL-048 | Inspects the completed grounding path for isolation from the neutral conductor, correct termination, and continuity, correcting any deficiency found |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Target Condition | Result | Pass/Fail | Correction (if any) |
|---|---|---|---|---|
| Conductor identification | Equipment-grounding conductors identified and isolated from grounded neutral conductors | |||
| Box bonding | Listed grounding screw, clip, or bonding device installed; no unlisted fastener used | |||
| Splice condition | Incoming, outgoing, and pigtail grounding conductors joined with a listed connector, no exposed copper beyond it | |||
| Pigtail termination | Box pigtail at grounding screw or device; device pigtail at green terminal within listed conductor limit | |||
| Neutral isolation | No neutral-to-ground jumper or bootleg ground present | |||
| Continuity test | Unbroken path confirmed from device yoke and metal box to branch equipment-grounding path |
Unresolved grounding conditions and correction plan: ____________________________________________
Grounding path declared complete: ______ (Pass/Fail) Date: ____________ Builder name: ____________
With the equipment-grounding conductors identified, the metal box bonded with a listed grounding screw or clip, the box-bonding and device-grounding pigtails terminated, neutral conductors kept isolated, and continuity verified, review the finished grounding assembly against the Acceptance Standards table and confirm every equipment-grounding conductor is correctly identified and isolated from the neutral, the box is bonded with a listed device rather than an unlisted fastener, every splice and pigtail termination is correctly seated with no exposed copper beyond the connector, no neutral-to-ground jumper or bootleg ground exists anywhere in the assembly, and the de-energized continuity test confirms an unbroken path from the device yoke and metal box to the branch equipment-grounding path. Complete the Grounding and Bonding Verification Worksheet and correct any failed item before beginning Project 09. If an item fails, identify whether the error occurred in conductor identification, box bonding, splicing, termination, or neutral isolation before correcting it and re-running the affected continuity check.
You have completed the eighth project in the residential electrical sequence: bonding metal boxes and grounding a branch circuit. This project required you to identify equipment-grounding conductors and distinguish them from grounded neutral conductors, install listed grounding screws and clips, bond and pigtail the metal box and device, keep neutral conductors correctly isolated, and verify the completed grounding path with a de-energized continuity test (EL-043 through EL-048).
You now have a metal box with a proven, continuous, correctly isolated equipment-grounding path, ready to receive the duplex receptacle, GFCI receptacle, switches, and fixtures installed in the projects that follow. That system carries directly into the next project: installing and testing a duplex receptacle on this de-energized, grounded, inspected branch circuit.
Keep the circuit de-energized and locked out, and retain your Grounding and Bonding Verification Worksheet alongside your Chapter 1 Electrical Safety-Readiness Worksheet. You will reference both records before every remaining device and fixture project in this book.