Project 05
Inspect the accessible duct system serving selected rooms and produce an evidence-based airflow-deficiency report, using the system map from Project 01 and the shutdown procedure from Project 02, without redesigning, resizing, or altering the HVAC system.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become an electrical, combustion, or air-quality hazard.
Task-specific safety guidance for ordinary work hazards.
Serious injury, shock, combustion, or exposure hazard is possible.
Practical work-area safety: lighting, footing, access, and housekeeping.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for equipment, controls, and labels.
Reference-point, verification, and documentation guidance.
This project qualifies you to inspect the accessible duct system serving selected rooms and produce a written, evidence-based airflow-deficiency report. The finished work product is one completed Duct and Airflow Deficiency Report: a documented inspection of accessible supply and return duct runs identifying disconnections, crushing, leakage, undersized-return symptoms, and other restrictions, together with recommended corrections and a clear separation between work this book authorizes and work requiring professional design or licensed service.
You will trace the supply path from equipment plenum to each selected register and the return path from selected return grilles to the equipment; identify disconnected joints, crushed flex duct, sagging, and damaged boots; inspect return paths for undersized-return symptoms; compare room airflow using approved observation or instrumentation; and prepare a deficiency report using location, symptom, confirmation evidence, recommended correction, and priority.
This project depends on the system map completed in Project 01 and uses the shutdown procedure established in Project 02 before any physical inspection begins. The deficiency report produced here directly controls the work performed in Projects 6 through 11: duct sealing, insulation, register-boot work, return-path construction, flexible-duct installation, and airflow balancing. This project does not authorize resizing ducts, redesigning the system, or performing any correction beyond the noninvasive observations described here.
This project sits between the basic-service work of Projects 3 and 4 and the duct-system correction work of Projects 6 through 11. The system map from Project 01 identifies what exists; the readiness procedure from Project 02 shuts equipment down safely; this project determines what is wrong with the accessible duct system and where; and Projects 6 through 11 correct only the deficiencies this report identifies as within their scope.
The evidence-based reporting habit established here — location, symptom, confirmation evidence, recommended correction, and priority — is the same structure used again in the comfort-diagnostic work of Project 19.
This project covers:
This project does not authorize the learner to:
Any deficiency identified in this chapter that requires design calculations, equipment service, duct replacement, or licensed evaluation must be recorded and escalated; it is not corrected as part of this project.
Establish these references before beginning the duct inspection, and do not change the defined scope mid-project.
| Term | Definition |
|---|---|
| Selected rooms | The exact rooms and their supply and return paths that this project's inspection and deficiency report apply to |
| Accessible duct | Any duct section, joint, boot, or fitting that can be inspected without opening a finished surface, entering a restricted space, or disturbing hazardous material |
| Disconnected joint | Any duct connection separated far enough to allow visible air leakage or physical gap at the joint |
| Crushed duct | Any duct section, most often flexible duct, whose cross-section is significantly reduced by collapse, sharp bending, or external pressure |
| Undersized-return symptom | An observable condition — such as door-closure pressure effects, a restricted transfer path, or heavy filter loading — consistent with insufficient return-air capacity, without a design calculation confirming undersizing |
| Confirmation evidence | The specific observation, measurement, or comparison that supports a recorded deficiency, as distinct from an assumption |
| Priority | The recorded urgency of a deficiency based on its effect on safety, comfort, or equipment condition, used to sequence correction in later chapters |
Before beginning the walk-through, record the defined scope directly on the Duct and Airflow Deficiency Report worksheet:
Selected rooms / zone: ______ Complaint or reason for inspection: ______ System map reference (Project 01): ______
Filter condition at time of inspection: ______ Date started: ____________ Builder name: ____________
Duct inspection is a diagnostic skill built on the identification work of Project 01. A duct traced incorrectly, or a symptom recorded without confirming evidence, produces a deficiency report that sends later chapters to the wrong location or the wrong correction. This project trains the habit of tracing every path completely, recording exactly what confirms each finding, and separating what the book authorizes you to correct from what requires professional design or service.
This project diagnoses accessible duct and airflow conditions only. It does not authorize adding ducts, enlarging returns, resizing branches, or changing equipment capacity. A finding that appears to require any of these actions must be recorded as requiring design calculations or licensed evaluation, not corrected or assumed resolved by a larger duct or return opening chosen in the field.
Record a deficiency only after you have traced the duct to the point of the observed condition and identified the specific evidence — a visible gap, a measured collapse, a door-closure pressure effect, or a comparable observation. Do not record a symptom based on a room's reputation for being "always cold" without confirming it during this inspection.
Shut down equipment using the Project 02 procedure before beginning physical inspection of duct runs, boots, and connections. Restore equipment and perform only noninvasive observations with all safety panels installed when comparing room airflow. Do not touch energized components, and do not remove a restricted electrical, combustion, or refrigerant-component cover at any point in this project.
Inspect attic, crawlspace, and mechanical-closet access for structural support, adequate lighting, insulation hazards, pests, and confined-space conditions before entering. Stop work and do not continue inspecting an area where suspected asbestos-containing duct wrap, transite, vermiculite, lead dust, animal waste, sewage contamination, heavy mold growth, or fire damage is observed.
Do not treat a garage, mechanical room, contaminated space, or other restricted location as an acceptable return-air source when recording undersized-return symptoms or proposing a correction. Any return-air change identified as necessary is recorded for the approved-design procedure in Project 09, not decided or implemented here.
HV-025 – HV-030
Diagnostic / Inspection / Deficiency-Reporting Qualification
Quantity: one defined set of selected rooms, traced supply and return paths, identified duct deficiencies with confirming evidence, identified return-path concerns, completed airflow comparison, and completed Duct and Airflow Deficiency Report separating book-scope corrections from professional-referral items.
| Item | Target Condition | Verification Method |
|---|---|---|
| Selected rooms and scope | Defined and does not change mid-project | Written record on worksheet |
| Supply-path trace | Every selected supply path traced from equipment plenum to register | Visual trace and written record |
| Return-path trace | Every selected return path traced from grille to equipment | Visual trace and written record |
| Duct condition | Disconnections, crushing, sagging, and boot damage identified with location and evidence | Visual confirmation and photograph |
| Return-path condition | Undersized-return symptoms identified with confirming evidence | Observation under defined door and operating conditions |
| Room airflow comparison | Compared using the approved observation or instrument method | Recorded comparison under stable operating condition |
| Deficiency report | Every finding recorded with location, symptom, evidence, recommended correction, and priority | Completed written report |
| Check | Standard |
|---|---|
| Duct tracing | Every selected supply and return path traced from equipment to register or grille, or to the point access ends |
| Deficiency identification | Every disconnection, crushed section, sag, and damaged boot recorded with location and confirming evidence |
| Return-path evaluation | Every undersized-return symptom recorded with confirming observation under a defined condition |
| Airflow comparison | Room airflow compared using the approved observation or instrument method under a stable operating condition |
| Scope separation | Every finding classified as within book scope for Projects 6 through 11 or as requiring professional design or service |
| Documentation | Duct and Airflow Deficiency Report complete with location, symptom, evidence, recommended correction, and priority for every finding |
| Procedure | Preparation, safe access confirmation, shutdown, supply tracing, return tracing, deficiency identification, airflow comparison, and reporting completed independently and in sequence |
Inspect every completed deficiency report using the same checks regardless of which residence or training system the project involves.
Complete the Duct and Airflow Deficiency Report in the Inspection Checklist section below before beginning Project 06.
Probable cause: a restriction beyond accessible inspection, a loaded filter, closed or partially closed dampers, or an equipment-capacity condition rather than a duct defect.
Confirmation: re-check filter condition, damper positions, and the complete traced path for any missed section.
Correction: record the finding as requiring further evaluation rather than assigning it to a specific duct correction; do not guess at an unconfirmed cause.
Reinspection: confirm the report reflects the unresolved status and recommends the correct next step.
Probable cause: the duct passes into an inaccessible cavity, concealed chase, or restricted area beyond the point access ends.
Confirmation: check for the duct's reappearance at another accessible point, such as a register, grille, or exterior termination.
Correction: record the trace as ending at the specific point access was lost; do not assume the condition of the unseen section.
Reinspection: confirm the worksheet identifies the exact point where tracing stopped and why.
Probable cause: an undersized or blocked return-air transfer path relative to the room's supply airflow.
Confirmation: observe the symptom with the door closed under the defined test condition and compare with the door open.
Correction: record the finding as an undersized-return symptom with the confirming observation; do not cut a new return opening as part of this project.
Reinspection: confirm the finding is assigned to the approved-design procedure in Project 09 rather than corrected here.
Probable cause: a prior modification, an undocumented repair, or an incomplete original trace.
Confirmation: re-check the field condition against the system map at the specific point of disagreement.
Correction: record the discrepancy on the deficiency report; do not alter the original system map to match the new observation without updating both records.
Reinspection: confirm every identified discrepancy appears in the report with its location and description.
Probable cause: suspected asbestos-containing material, heavy mold growth, sewage contamination, fire damage, or an unsafe access condition.
Confirmation: do not approach, disturb, or further investigate the condition; confirm only what is visible from a safe distance.
Correction: stop work in the affected area, record the condition and its location, and escalate to a qualified professional; do not continue inspecting that area until the condition is addressed.
Reinspection: resume inspecting the affected area only after the condition has been corrected or a qualified professional has authorized continued access.
This project ends with the deficiency report completed and the work area left undisturbed, not altered further until the assigned correction chapter begins.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| HV-025 | Traces duct runs from equipment plenum to selected registers and from selected return grilles to equipment | |||
| HV-026 | Identifies crushed ducts, including collapsed flex liners, sharp bends, and structurally damaged sections | |||
| HV-027 | Identifies disconnected ducts, including open seams, separated joints, and detached boots | |||
| HV-028 | Identifies undersized-return symptoms with confirming observation under defined conditions | |||
| HV-029 | Locates airflow restrictions using approved comparison or measurement methods without altering the system | |||
| HV-030 | Documents duct deficiencies in a structured, evidence-based report with recommended correction and priority |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Target Condition | Result | Pass/Fail | Correction (if any) |
|---|---|---|---|---|
| Scope definition | Selected rooms and zone defined in writing before inspection began | |||
| Supply-path trace | Traced from equipment plenum to each selected register or to the limit of access | |||
| Return-path trace | Traced from each selected return grille to equipment or to the limit of access | |||
| Duct deficiencies | Disconnections, crushing, sagging, and damaged boots recorded with location and evidence | |||
| Return-path symptoms | Undersized-return symptoms recorded with confirming observation | |||
| Airflow comparison | Completed using the same method and operating condition across selected rooms | |||
| Scope classification | Every finding classified as book-scope or professional-referral |
Unresolved conditions and escalation notes: ____________________________________________
Deficiency report declared ready: ______ (Pass/Fail) Date: ____________ Builder name: ____________
With the supply and return paths traced, duct deficiencies identified with confirming evidence, undersized-return symptoms recorded, airflow comparison completed, and every finding classified, review the finished report against the Acceptance Standards table and confirm every selected path is traced to its termination or to the limit of access, every deficiency has recorded location and evidence, every undersized-return symptom is supported by a confirming observation, the airflow comparison used a consistent method and operating condition, and every finding is correctly classified as book-scope or professional-referral with no unsupported recommendation to add ducts, enlarge returns, or change equipment. Complete the Duct and Airflow Deficiency Report and correct any failed item before beginning Project 06. If an item fails, identify whether the error occurred in path tracing, deficiency identification, return-path evaluation, airflow comparison, or scope classification before correcting it and re-running the affected check.
You have completed the fifth project in the residential HVAC sequence: inspecting ductwork and diagnosing airflow problems. This project required you to trace supply and return duct paths, identify crushed and disconnected ducts, identify undersized-return symptoms, locate airflow restrictions using approved methods, and document every finding in a structured, evidence-based deficiency report (HV-025 through HV-030).
You now have a verified deficiency report you can reference for every duct-correction project that follows. That record carries directly into the next project: sealing the accessible leakage points this inspection identified using mastic and HVAC-rated tape.
Retain your Duct and Airflow Deficiency Report. You will reference this exact report before beginning Project 06 and throughout Projects 6 through 11.