Project 12
Establish a controlled tile layout on an accepted backer-board substrate, mix and spread mortar within its working time, set a full ceramic or porcelain tile field with verified coverage, and inspect joint width, plane, and lippage before grouting.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become failed installations, hazardous exposure, or rejected inspections.
Task-specific safety guidance for ordinary work hazards.
Serious injury, hazardous-material exposure, or major property damage is possible.
Practical work-area safety: lighting, footing, ventilation, and housekeeping.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for mortar mixing, open time, coverage, and joint width.
Reference-point, tolerance, and verification guidance.
This project qualifies you to lay out and set a controlled field of ceramic or porcelain floor tile on an accepted backer-board substrate. The finished work product is one completed tile field: a verified dry layout with perpendicular control lines, a documented movement-joint plan, a mixed and applied thinset mortar bed with verified coverage, a set tile field with maintained joint width and controlled lippage, and accurately cut perimeter, doorway, pipe, and obstacle tiles.
You will establish reference lines from a dry layout; plan movement and perimeter joints; mix mortar to the specified ratio; spread and comb mortar within its open time; set tile while collapsing mortar ridges; maintain joint width and pattern with spacers or leveling devices; verify mortar coverage by lifting representative tiles; and inspect the completed field for layout accuracy, coverage, lippage, and clean joints before grouting begins in Chapter 13.
This project depends on the tile-backer substrate accepted in Chapter 11. The grouting, cleaning, and sealing work that finishes this floor is covered in Chapter 13 and must not begin until the mortar set in this project has cured for the required period.
This project follows directly from the tile-backer substrate installed and inspected in Chapter 11. It establishes every condition that Chapter 13 grouting depends on: joint width and depth, tile plane, preserved movement joints, and mortar coverage beneath every tile. A poorly planned layout, an underfilled mortar bed, or an uncontrolled lippage condition set in this project cannot be corrected by grouting and is the leading cause of cracked tile, hollow-sounding tile, and rejected tile-floor inspections.
The documentation habit established here — recording mortar batch, coverage checks, and cure conditions — is reused in Chapter 13's grouting record and in the Chapter 19 final quality inspection.
This project covers:
This project does not authorize the learner to:
Any layout, coverage, plane, or movement-joint condition that fails verification in this chapter must be corrected before grouting begins.
Establish these references before mortar is mixed, and do not change the defined control lines mid-project.
| Term | Definition |
|---|---|
| Control line | A chalk or marked reference line, established perpendicular to a second control line, used to align every course of tile in the field |
| Dry-laid reference row | A row of tile placed without mortar to verify layout, joint width, and cut sizes before setting begins |
| Open time | The period after mortar is spread during which it remains workable enough to properly bond tile, as specified by the mortar manufacturer |
| Mortar coverage | The percentage of a tile's back surface, and the corresponding substrate area, in full contact with mortar after the tile is set and pressed into place |
| Lippage | A vertical difference in height between the edges of two adjoining tiles, measured at the joint |
| Movement joint | A joint at the perimeter, at changes in plane, or within a large field that must remain flexible and free of rigid mortar or grout to accommodate structural and thermal movement |
Before mixing mortar, record the confirmed layout and mortar product directly on the Tile-Setting Record:
Inspection area (room / rooms): ______ Tile size and pattern: ______ Specified joint width: ______
Mortar product and lot number: ______ Trowel size: ______ Date started: ____________ Builder name: ____________
Every step in this project depends on the layout and reference lines established before mortar is mixed. A tile field set without a verified dry layout, an accurate control line, or a planned movement-joint layout cannot be corrected without removing hardened mortar and tile.
Every control line established in this chapter is derived from a dry-laid reference row checked against room dimensions, doorway alignment, and cut sizes at every wall. Do not chalk a control line directly from a wall measurement without first confirming it against a dry layout. Where the mortar manufacturer specifies a water ratio, mixing time, slake period, remix procedure, open time, or trowel size, follow that requirement exactly and record it on the Tile-Setting Record.
Dry-lay reference rows in both directions and adjust the layout to avoid tile cuts narrower than the manufacturer-approved minimum before mixing any mortar. A layout adjusted after mortar has been spread wastes material and risks tile being set into mortar that has exceeded its open time.
Cut tile only with a wet saw or method that controls silica dust. Do not dry-cut tile with an abrasive blade in a manner that generates airborne silica dust. Use eye protection and keep the cutting area separated from the mortar-mixing and setting zones as established in Chapter 2.
Use knee pads and change position regularly during extended tile-setting work. Keep the mixing and cutting areas clear of trip hazards, hoses, and standing water that could cause a slip while carrying mortar or tile.
Mix mortar using the exact water ratio, mixing time, slake period, and remix procedure specified by the mortar manufacturer. Do not add water after the permitted mixing sequence. Spread only the area that can be covered with tile within the mortar's specified open time.
FL-067 – FL-072
Tile Layout / Mortar Mixing and Spreading / Tile Setting and Coverage Verification
Quantity: one defined tile field covering the inspection area, set on established control lines, with movement joints preserved, verified mortar coverage beneath every tile, maintained joint width and lippage tolerance, and accurately cut perimeter, doorway, pipe, and obstacle pieces.
| Item | Target Condition | Verification Method |
|---|---|---|
| Dry layout | Reference rows placed in both directions with no unacceptable narrow cuts or poor doorway alignment | Visual check against control lines and doorway centerline |
| Control lines | Two perpendicular control lines established and verified square | Chalk line and measured diagonal check |
| Movement joints | Perimeter and field movement joints identified and marked before mortar is spread | Written record on plan and visual marking |
| Mortar mix | Mixed to the specified water ratio, mixing time, slake, and remix procedure | Timed mixing and visual consistency check |
| Mortar coverage | Full mortar contact on tile back and substrate at every lifted representative tile | Physical lift-and-check of representative tile |
| Joint width and lippage | Joint width consistent with the specified pattern; lippage within the manufacturer or industry tolerance | Spacer or leveling-device check and straightedge across adjoining tiles |
| Perimeter and obstacle cuts | Every cut tile fits with the required clearance and maintains movement space | Direct measurement at each cut location |
| Check | Standard |
|---|---|
| Layout accuracy | Control lines square and verified against a dry layout with no unacceptable narrow cuts at any wall or doorway |
| Mortar coverage | Every lifted representative tile shows full mortar contact on both tile back and substrate with no skinned or hollow areas |
| Joint width and pattern | Joint width and pattern consistent across the field within the tolerance specified by the tile assembly specification |
| Lippage | Adjoining tile edges within the manufacturer or industry lippage tolerance at every checked joint |
| Movement joints | Every designated movement joint free of mortar intrusion and marked for flexible treatment in Chapter 13 |
| Perimeter and obstacle cuts | Every cut tile accurately sized with required clearance maintained |
| Cleanliness | Mortar removed from tile faces and joints before hardening |
| Documentation | Tile-Setting Record complete with layout, mortar batch, coverage checks, and cure entries |
Inspect every completed tile field using the same checks regardless of tile size, pattern, or room shape.
Complete the Tile-Setting Record in the Inspection Checklist section below before beginning Project 13.
Probable cause: the mortar skinned over before the tile was set, the trowel notch size did not match the tile and substrate requirement, or the tile was not moved perpendicular to the ridges to collapse them.
Confirmation: lift additional tiles from the same spread section and compare coverage against the required percentage.
Correction: remove the affected tile, re-comb or re-spread fresh mortar within its open time, back-butter the tile if required, and reset it on the reference lines.
Reinspection: lift the corrected tile again to confirm full coverage before proceeding to the next section.
Probable cause: an uncorrected minor substrate deviation, an inconsistent mortar bed thickness, or a leveling device not fully engaged before the mortar set.
Confirmation: re-check the joint with a straightedge across both directions and compare against the specified tolerance.
Correction: while the mortar remains workable, lift and reset the high tile with corrected mortar thickness; if the mortar has hardened, remove the tile per the Chapter 18 repair procedure.
Reinspection: recheck the corrected joint and the adjoining joints for consistent plane.
Probable cause: the control lines were established directly from a wall measurement without a confirmed dry layout, or the layout was not adjusted before mortar was spread.
Confirmation: re-measure the affected cut against the minimum width specified in the tile assembly specification.
Correction: where mortar has not yet been spread in the affected area, shift the control lines and re-lay the dry reference row; where tile has already been set, document the condition and correct before grouting.
Reinspection: re-verify the dry layout across the full width of the affected wall before resuming mortar spreading.
Probable cause: the movement-joint location was not marked before mortar was spread, or mortar was not trimmed away from the joint before it hardened.
Confirmation: inspect the full length of every marked movement joint for mortar contamination.
Correction: remove intruded mortar from the joint while it remains workable using a margin trowel or scoring tool; where the mortar has hardened, remove it mechanically without damaging adjoining tile.
Reinspection: confirm the joint is fully clear and ready for the flexible sealant installed in Chapter 13.
Probable cause: too large an area was spread relative to the mortar's open time, or ambient temperature and humidity shortened the working time.
Confirmation: check the mortar surface for skinning by lightly touching an unset area with a gloved finger.
Correction: remove the skinned mortar, discard it, and re-spread a smaller section sized to the crew's actual setting pace.
Reinspection: verify coverage on the first tile set into the re-spread section before continuing.
Probable cause: mortar was not cleaned from the tile surface before it began to set.
Confirmation: inspect the tile face under raking light for residue and haze.
Correction: remove hardened residue using the method approved for the tile finish without scratching the surface; consult the tile manufacturer's cleaning instructions before using any abrasive method.
Reinspection: re-inspect the cleaned area under the same lighting condition.
This project ends with the tile field fully set, cleaned, and protected through the specified cure period, not yet grouted.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| FL-067 | Establishes tile layout using dry-laid reference rows and verified perpendicular control lines, with layout adjusted to avoid unacceptable narrow cuts | |||
| FL-068 | Mixes thinset mortar using the specified water ratio, mixing time, slake, and remix procedure without adding water after the permitted sequence | |||
| FL-069 | Spreads and combs mortar with the specified trowel, limiting coverage to the area that can be set within open time | |||
| FL-070 | Sets tile on the established reference lines, collapses mortar ridges, and verifies coverage by lifting representative tiles | |||
| FL-071 | Maintains joint width, pattern, and lippage tolerance across the tile field, correcting deviations before mortar sets | |||
| FL-072 | Inspects tile alignment, coverage, lippage, cuts, and movement details, and completes the Tile-Setting Record before Chapter 13 |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Target Condition | Result | Pass/Fail | Correction (if any) |
|---|---|---|---|---|
| Layout and control lines | Square, verified against dry layout, no unacceptable narrow cuts | |||
| Movement-joint plan | Every joint marked before mortar spread and kept free of mortar intrusion | |||
| Mortar mix and batch record | Mixed to specified ratio, time, slake, and remix procedure; batch and lot recorded | |||
| Mortar coverage | Full coverage confirmed on every lifted representative tile | |||
| Joint width and lippage | Consistent joint width and lippage within tolerance across the field | |||
| Perimeter and obstacle cuts | Accurately measured and cut with required clearance | |||
| Cleanliness and cure protection | Tile faces and joints clean; field protected through specified cure period |
Deficiency list and assigned corrections: ____________________________________________
Tile-setting readiness for grouting: ______ (Approved/Conditional/Rejected) Date: ____________ Builder name: ____________
With the layout established from a confirmed dry-laid reference row, mortar mixed and spread within its open time, tile set with verified coverage, joint width and lippage maintained within tolerance, and perimeter and obstacle tiles accurately cut, compare the finished tile field against the Acceptance Standards table and confirm control lines are square, every lifted representative tile shows full mortar coverage, every checked joint is within the lippage tolerance, every movement joint is free of mortar intrusion, and the Tile-Setting Record is complete. Correct any failed item and repeat the affected check before beginning Project 13. If an item fails, identify whether the error occurred in layout, mortar mixing, mortar spreading, tile setting, or coverage verification before correcting it and re-running the affected check.
You have completed the twelfth project in the residential flooring sequence: laying out and setting floor tile. This project required you to establish a verified layout, mix and spread mortar within its working time, set tile with maintained joint width and controlled lippage, verify mortar coverage, and cut and set perimeter and obstacle tiles (FL-067 through FL-072).
You now have a completed tile field, set on verified control lines with documented mortar coverage, that Chapter 13 depends on directly. That work carries into the next project: grouting, cleaning, and where required sealing this same tile floor once the specified mortar cure period has elapsed.
Retain your Tile-Setting Record, including mortar batch information, coverage checks, and cure conditions. You will reference this exact record before Chapter 13 grouting begins.