Chapter 17
Build one small masonry step or two-step practice assembly on an approved base while preserving required geometry, support, drainage, and slip resistance.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework, an unsafe step, or a failed inspection.
Task-specific safety guidance for ordinary step-construction hazards.
Serious injury, a fall hazard, or a noncompliant step is possible.
Practical work-area safety: access, footing, lighting, and housekeeping.
Local requirements vary. Verify rise, run, width, and permit rules.
Follow product-specific instructions for units, mortar, and setting materials.
Rise, run, nosing, width, and elevation-reference guidance.
This chapter qualifies you to build one small masonry step or two-step practice assembly on an approved base while holding the exact rise, run, tread depth, nosing, width, and drainage the approved plans specify. The finished work product is one stable, code-consistent step assembly with uniform risers and treads, secure bearing, controlled drainage, safe nosing, and a documented cure record.
You will use the approved total rise, riser count, tread depth, nosing, width, landing, foundation, drainage, material, and code requirements supplied for the project. Nothing in this chapter authorizes you to invent a rise, run, or tread dimension not supplied by the approved plans, adopted code, or a qualified professional; this chapter builds exactly what those documents specify.
This chapter depends on Chapter 1 readiness planning, Chapter 2 work-area setup, Chapter 3 mortar mixing, and Chapter 4 layout skills, and it uses the Chapter 10 cutting procedure for any riser or tread unit that requires cutting. It feeds directly into the Chapter 20 capstone, which may hand off a completed nonstructural garden-wall or veneer section but does not repeat step construction; the geometry and stability judgment practiced here also applies wherever a masonry step condition is encountered in later work.
A masonry step is one of the few masonry assemblies where a small dimensional error becomes an immediate trip hazard rather than a cosmetic defect. The layout discipline from Chapter 4, the base preparation from Chapters 1 and 2, and the mortar and unit-setting skills from Chapters 3, 5, and 8 all converge here, but the acceptance standard is stricter: every riser and every tread in the assembly must match the approved geometry within the stated tolerance, not just within an aesthetic sense of "close enough."
The stop-work judgment you use here — refusing to build a step that cannot achieve the required geometry on the existing base — is the same judgment used in Chapter 16 for garden-wall foundations and in the Chapter 20 capstone for the final handoff inspection.
This chapter covers:
This chapter does not authorize the learner to:
Any base, elevation, or code condition that cannot be resolved within this chapter's scope must be documented and referred to the responsible design or inspection authority before construction begins.
Establish these references before any layout mark, excavation, or unit is placed, and use them consistently across the project record.
| Term | Definition |
|---|---|
| Total rise | The vertical distance from the base or lower finished grade to the upper finished threshold or landing elevation, as stated in the approved drawings |
| Riser height | The vertical face dimension of one step, measured finished-tread-surface to finished-tread-surface, as specified in the approved drawings |
| Tread depth (run) | The horizontal walking-surface dimension of one step, measured from the leading edge (nosing) to the leading edge of the next riser, as specified in the approved drawings |
| Nosing | The projection of the tread's leading edge beyond the riser face below it, held to the dimension specified in the approved drawings |
| Story pole | The reference pole marked with each riser, tread, and finished elevation for this specific step assembly, built from actual unit height and specified joint thickness |
| Stop-work condition | A base, elevation, or code condition that prevents the specified geometry from being achieved and must be referred to a qualified professional before work proceeds |
Before beginning layout, record the selected project and its controlling documents directly on the project record:
Project name: ______ Total rise: ______ Number of risers: ______ Riser height: ______ Tread depth: ______ Nosing: ______ Width: ______
Landing required: ______ (Y/N) Approved drawings on hand: ______ (Y/N) Permit required: ______ (Y/N/Unknown) Responsible design/inspection authority: ____________
Date started: ____________ Mason name: ____________
Every masonry step assembly, from a single stone step to a full stair run, depends on the same governing relationship: total rise divided among a fixed number of equal risers, and a tread depth held constant across every step. A rise that grows or shrinks from step to step, or a nosing that varies across the width of the tread, produces a hazard that cannot be corrected after the mortar cures. Confirm the geometry on paper and on the story pole before any unit is set.
Confirm the approved total rise, number of risers, tread depth, nosing, width, and landing dimensions against the existing base and adjacent threshold elevations before any excavation begins. If the measured field condition does not allow the specified geometry to be achieved — for example, an existing threshold elevation that produces a top riser taller or shorter than every other riser — stop and refer the discrepancy to the responsible design authority. Do not adjust the specified rise or run in the field to make the existing condition work.
Build the story pole from the actual riser and tread unit height plus the specified joint thickness before excavation begins. Mark every riser, tread, and finished elevation on the pole. Check every course against the story pole as it is built; do not rely on a running tape measurement from the base, which allows small joint variations to accumulate into an out-of-tolerance final riser.
Do not begin construction if the required rise, run, nosing, width, or landing dimension cannot be achieved on the existing base or threshold elevation. Do not improvise a nonuniform riser or tread to compensate for a field discrepancy. Stop, document the discrepancy, and refer it to the responsible design or inspection authority before proceeding.
Barricade the work area during excavation, base preparation, and unit setting to prevent foot traffic across an incomplete or uncured assembly. Keep the barricade in place after construction until the assembly is safe for traffic per the acceptance standards in this chapter; do not remove it based on visual appearance alone.
Maximum riser height, minimum tread depth, riser-to-tread uniformity tolerance, minimum width, nosing dimensions, and landing requirements vary by jurisdiction and by whether the step assembly serves as a required means of egress. Verify the requirements that apply to this specific project locally rather than assuming the requirements of a prior project apply.
RM-097 – RM-102
Layout / Base Preparation / Masonry Construction
Deliverable: one small masonry step or two-step assembly built on an approved base, with total rise, riser count, tread depth, nosing, width, and landing exactly matching the approved drawings; full riser and tread bearing; approved reinforcement, infill, or concrete support where specified; controlled drainage slope on treads and landing; tooled and cleaned joints; and a documented cure and inspection record.
| Component | Quantity | Material | Finished Size | Preparation |
|---|---|---|---|---|
| Base / footing support | Per approved detail | Compacted aggregate or concrete, per approved detail | Per approved base or footing detail | Excavated, compacted, formed, and cured or verified level per approved detail |
| Riser units | Per approved riser count | Brick, block, or stone per approved specification | Riser height per story pole | Dry-laid, cleaned, and cut per Chapter 10 where required |
| Tread units | Per approved tread count | Brick, block, or stone per approved specification | Tread depth and nosing per approved dimensions | Dry-laid, cleaned, and cut per Chapter 10 where required |
| Infill / reinforcement / grout | Per approved detail | Per approved specification | Per approved detail | Installed and inspected only where specified; not substituted or omitted |
| Mortar or setting bed | Per approved mix and takeoff | Per Chapter 3 specification | Bed and joint thickness per story pole | Batched, mixed, and tested per Chapter 3 |
Base every quantity of riser units, tread units, aggregate or concrete, reinforcement, infill, mortar, and joint material on the approved drawings and component schedule for this specific project. Include a waste allowance for cutting under Chapter 10. Do not estimate quantities without a source document.
| Check | Standard |
|---|---|
| Riser height uniformity | Every riser matches the specified height within the tolerance stated in the approved drawings or adopted code; if none is stated, treat any measurable variation between risers as a deficiency and refer it rather than estimating a tolerance |
| Tread depth uniformity | Every tread matches the specified depth within the same tolerance standard applied to riser height |
| Nosing | Consistent projection matching the approved dimension on every tread; no tread nosing may be omitted or reduced to correct a riser-height error |
| Level and straightness | Each riser and tread level along its length and straight across its face, checked with the 4-foot level and straightedge |
| Bearing | Full bearing on the approved base, footing, or supporting course beneath every riser and tread; no unit bears on unverified or unsupported material |
| Drainage slope | Treads and landing slope per the approved drainage detail without creating an unsafe cross slope; standing water is not present after the drainage test in Step 21 |
| Joints | Full, tooled joints matching the specified profile; no voids visible at riser-to-tread or tread-to-riser transitions |
| Stop-work conditions | Required geometry cannot be achieved on the existing base or threshold elevation; construction stops on that item and is referred to the responsible design authority before proceeding |
Inspect every step assembly using the same checks regardless of unit material or riser count.
Complete the Step Assembly Inspection Checklist below before removing the barricade.
Probable cause: courses were built by running tape measurement from the base rather than checking each course against the story pole, allowing small joint-thickness variations to accumulate.
Confirmation: measure every riser individually against the story pole rather than against the base; compare each measurement to the specified riser height and the stated tolerance.
Correction: if any riser exceeds the tolerance, the affected course must be removed and rebuilt to the story-pole elevation; do not attempt to compensate by adjusting an adjacent riser.
Reinspection: recheck every riser in the assembly against the story pole after the correction, not only the corrected riser.
Probable cause: the tread unit was set without checking nosing projection at both ends and the center, allowing the unit to twist or shift before the mortar set.
Confirmation: measure nosing projection at both ends and the center of every tread and compare to the specified dimension.
Correction: reset the affected tread unit in fresh mortar with the nosing checked and held at all three points before the bed sets.
Reinspection: recheck nosing at all three points on the corrected tread and on adjacent treads for consistency.
Probable cause: the tread or landing was set level or with reversed slope instead of the specified drainage slope.
Confirmation: check the tread or landing slope with the level against the approved drainage detail; confirm the standing water location and depth.
Correction: remove and reset the affected tread or landing unit with the correct slope; do not attempt to correct drainage with a sealer or surface coating.
Reinspection: repeat the drainage test on the corrected surface and on adjacent treads.
Probable cause: infill, reinforcement, or concrete support specified in the approved detail was omitted or not allowed to cure before the next course was loaded.
Confirmation: inspect beneath the affected unit for voids, uncured infill, or missing reinforcement; compare against the approved detail.
Correction: remove the affected unit, install the missing infill, reinforcement, or support exactly as specified, allow the required cure, and reset the unit with full bearing.
Reinspection: confirm full bearing on the corrected unit and reinspect adjacent units for the same deficiency.
Probable cause: the existing base or threshold elevation was not verified against the approved total rise before excavation began.
Confirmation: remeasure the existing lower grade and upper threshold elevation and compare the difference to the approved total rise and riser count.
Correction: stop work on the affected item and refer the discrepancy to the responsible design authority; do not adjust the specified rise, run, or riser count in the field.
Reinspection: confirm the referral is resolved and a revised or reconfirmed geometry is issued before construction resumes.
This chapter ends with a barricaded, curing, documented step assembly, not an assembly opened to traffic on visual impression alone.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| RM-097 | Lays out step footprint, riser lines, and finished elevations matching the approved total rise, riser count, tread depth, nosing, width, and landing dimensions before excavation begins | |||
| RM-098 | Excavates, compacts, and installs the approved aggregate or concrete base or footing to the level and drainage condition specified | |||
| RM-099 | Constructs each riser course level, straight, and to the elevation marked on the story pole, with full bearing on the course below | |||
| RM-100 | Sets tread units with full bearing, consistent nosing at both ends and the center, and the specified drainage slope | |||
| RM-101 | Holds uniform finished rise and tread depth across every step in the assembly within the stated tolerance | |||
| RM-102 | Inspects and documents stability, geometry, nosing, slip resistance, drainage, edges, and transitions before the barricade is removed |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Finding | Deficient / Stop-Work | Correction or Referral | Reinspected (Date) |
|---|---|---|---|---|
| Layout and geometry | ||||
| Base preparation | ||||
| Riser construction | ||||
| Tread construction and nosing | ||||
| Drainage slope | ||||
| Joints and finish | ||||
| Cure protection | ||||
| Final stability and traffic readiness |
Professional referrals made: ____________ Hold points before traffic: ____________
Final result: ______ (Passed / Corrected and Reinspected / Rejected) Date: ____________ Mason name: ____________
With construction and cure complete, review the Step Assembly Record against the Acceptance Standards table and confirm every riser, tread, drainage, joint, and bearing item has been measured and recorded. Confirm every Deficient item has a documented correction and reinspection record, and every Stop-Work item has a documented professional referral. Remove the barricade and return the assembly to traffic only after every deficiency has been reinspected and cleared, the required cure period has elapsed, and the final result is recorded as Passed.
You have completed the seventeenth chapter in the residential masonry sequence: building a small brick or stone step assembly. This chapter required you to lay out step dimensions (RM-097), prepare the base (RM-098), set risers (RM-099), set treads (RM-100), maintain safe rise and run (RM-101), and inspect step stability (RM-102).
You now have a stable, cured, code-consistent step assembly with documented geometry, bearing, drainage, and inspection results. That documentation carries forward into the remaining chapters of this book: the chimney inspection judgment in Chapter 18 applies the same stop-work discipline to a different assembly, and the Chapter 20 capstone draws on the same layout, base-preparation, and inspection sequence practiced here.
File your completed Step Assembly Record, photographs, and referral records with the approved drawings for this project. You will reference this same layout and inspection discipline throughout the rest of this book.