Project 05
Prepare one parcel-specific zoning and site compliance checklist for a proposed residential project, using authoritative survey, plat, zoning, overlay, and approved site-plan information verified directly against the controlling authority rather than fences, tax maps, or aerial imagery.
These cues appear at the point of work. They identify property-line, easement, and zoning-determination issues before an unverified dimension or assumption reaches the site plan.
Task-specific guidance for site-walk hazards while confirming physical conditions against the survey.
A stop-work condition: the learner must not establish a controlling dimension, assume a variance, or proceed to foundation layout without official confirmation.
Practical handling of surveyors, zoning staff, and recorded documents.
Zoning definitions and measurement methods vary by jurisdiction. Verify the local definition before measuring.
Identifies determinations reserved for the licensed surveyor, zoning official, or design professional.
Recording, sourcing, and dating guidance for every dimension and requirement placed on the checklist.
This project qualifies you to identify setbacks, verify lot-coverage limits, identify easements, check height restrictions, review accessory-structure limits, and prepare a zoning compliance checklist for one defined residential parcel. The finished work product is one parcel-specific zoning and site compliance package: a marked-up site plan showing verified controlling dimensions, a completed checklist linking each requirement to its source and status, and a record of every unresolved item referred to the responsible professional or authority.
You will obtain the current survey, plat, and zoning map for the parcel; identify the zoning district and every applicable overlay; locate setback, easement, coverage, height, and accessory-structure requirements; measure the proposed project against the approved site plan; and resolve unclear or conflicting site conditions through the surveyor, zoning official, utility, or design professional rather than through field assumption.
This project depends directly on the Chapter 1 authority register and binder. It confirms the site-level constraints that must be resolved before Chapter 6's foundation-inspection preparation and before the Chapter 3 permit application packet can show an accurate site plan.
Project 02 determined whether the proposed work needs a permit and flagged zoning triggers as a category. This project resolves those zoning triggers to specific, sourced, measured requirements before the Chapter 3 application packet is assembled. An inaccurate site plan discovered during plan review forces a resubmittal cycle; an inaccurate site plan discovered after foundation layout forces a stop-work order, a survey correction, and possible removal of completed work.
The same verification discipline used here — confirming property lines from the recorded survey rather than from fences or aerial imagery, and referring unresolved conditions to the surveyor or zoning official rather than guessing — carries forward into the Chapter 6 foundation-inspection preparation and the Chapter 20 capstone.
This project covers:
This project does not authorize the learner to:
Any dimension that cannot be traced to the recorded survey, an official zoning determination, or the approved site plan must be labeled unresolved rather than estimated.
Establish these references before any dimension is measured, and apply them consistently across every checklist entry.
| Term | Definition |
|---|---|
| Legally controlling reference | The recorded survey, plat, or legal description used to establish property lines; not a fence, hedge, tax map, or aerial image |
| Setback | The minimum distance between a lot line and a structure or feature, measured using the jurisdiction's defined method and reference points |
| Lot coverage | The portion of the lot occupied by building footprint, impervious surface, or floor area, calculated using the jurisdiction's own definition |
| Easement | A recorded right held by another party to use a defined portion of the property for a stated purpose, such as utility access or drainage |
| Height limit | The maximum permitted building height, measured from the jurisdiction's defined grade point using its defined measurement method |
| Accessory structure | A detached building or structure subordinate to the primary residence, subject to its own size, location, and use limits |
| Unresolved site issue | Any dimension, boundary, or requirement that cannot yet be confirmed from the recorded survey, zoning code, or official determination |
Before locating any zoning requirement, record the parcel and proposed project directly on the zoning compliance checklist:
Property address: ______ Parcel number: ______ Legal lot: ______ Zoning district: ______
Proposed project description: ____________ Survey or plat date: ____________ Site plan revision reviewed: ____________
Date started: ____________ Preparer name: ____________
Every site-compliance task in this project follows the same sequence: confirm the legally controlling reference, identify the applicable zoning requirement from its official source, measure the proposed condition against that requirement, record the result with its source and date, and refer anything unresolved to the responsible professional or authority before it controls a design decision.
Every setback, coverage, easement, height, or accessory-structure value entered on the checklist must be traced to the adopted zoning code, the recorded survey or plat, or an official written determination. A value estimated from a fence, a landscape edge, a tax map, or an aerial image cannot be entered as a controlling dimension.
Record the requirement, its official source and section, the plan value measured against it, the status, and the responsible party for every checklist entry. An entry without a recorded source cannot be treated as verified.
Do not establish, assume, or adjust a property line, easement boundary, or elevation benchmark from a fence, landscaping, tax map, aerial image, or occupant statement. Use only the recorded survey, plat, legal description, or a licensed surveyor's field work. Stop and obtain a survey or surveyor confirmation whenever the legally controlling reference is unclear, missing, or contradicted by field conditions.
When walking the parcel to compare recorded conditions with field conditions, watch for uneven grade, overgrown vegetation, buried utility markers, animals, and traffic near the property edge. Do not enter a neighboring property to verify a shared line without permission.
Variances, conditional-use approvals, formal zoning interpretations, and property-line establishment are made by the zoning official, planning department, or a licensed surveyor, not by this checklist or its preparer. Where a requirement or boundary is ambiguous, label it unresolved and record the official source that must answer it.
CP-025 – CP-030
Site Verification / Zoning Compliance / Documentation Qualification
Scope: one parcel-specific zoning and site compliance checklist, organized by the requirement categories in the Component Schedule below, covering one defined residential parcel and one proposed project scope, with every dimension sourced from the recorded survey or plat and every requirement sourced from the adopted zoning code or an official determination.
| Section | Quantity | Source Type | Required Content | Verification / Purpose |
|---|---|---|---|---|
| Property Record | 1 | Official | Recorded survey or plat, legal description, parcel number, property record | Confirmed as the legally controlling reference |
| Zoning District | 1 | Official | Zoning district, permitted use, conditional use, accessory-use provisions | Matched to the confirmed parcel |
| Overlays and Special Districts | 1 | Official | Flood, wildfire, seismic, coastal, historic, planned-development, or other overlay conditions | Confirmed applicable or not applicable to the parcel |
| Setbacks | 1 | Official | Front, side, rear, street-side, waterfront, slope, well, septic, and other applicable setbacks | Measured from the legally controlling reference on the site plan |
| Easements and No-Build Areas | 1 | Official | Recorded utility, drainage, access, and other easements; encroachment or release status | Confirmed against the recorded survey or plat |
| Lot Coverage | 1 | Official | Existing and proposed building footprint, impervious coverage, floor-area ratio where applicable | Calculated using the jurisdiction's own definitions |
| Height | 1 | Official | Height limit, grade-measurement method, story and basement definitions affecting height | Measured using the jurisdiction's defined method |
| Accessory Structures | 1 | Official | Size, location, separation, foundation, and use limits for accessory buildings | Confirmed applicable to the proposed scope |
| Parking, Access, and Environmental | 1 | Official | Parking, driveway, sight-triangle, landscape, tree, stormwater, and fire-access conditions | Confirmed applicable to the proposed scope |
| Private Restrictions | 1 | Non-governmental | HOA, covenant, deed, or lease restrictions affecting the proposed scope | Confirmed separately from government zoning requirements |
| Unresolved Items and Referrals | 1 | Working document | Missing survey information, uncertain lot lines, conflicting dimensions, unverified easements | Converted into surveyor, zoning, utility, fire, or engineering questions |
| Check | Standard |
|---|---|
| Property-line sourcing | Every property-line dimension is traced to the recorded survey, plat, or legal description, never to a fence, tax map, or aerial image |
| Setback verification | Every applicable setback is measured from the legally controlling reference on the site plan and compared to the adopted requirement |
| Easement identification | Every recorded easement, right-of-way, and no-build area affecting the buildable area is identified and shown on the marked-up site plan |
| Coverage calculation | Lot coverage, impervious coverage, or floor-area ratio is calculated using the jurisdiction's own definitions, not an assumed formula |
| Height verification | The height limit is checked using the jurisdiction's defined grade point and measurement method |
| Accessory-structure review | Applicable accessory-structure size, location, separation, and use limits are identified and compared to the proposed scope |
| Unresolved-item handling | Every missing, uncertain, or conflicting site condition is logged, referred to the responsible party, and tracked to a recorded response |
| Checklist completeness | All eleven checklist sections from the Component Schedule are present, populated, and correctly labeled |
Inspect the finished checklist using the same checks regardless of which section is being reviewed.
Complete the Zoning Compliance Worksheet in the Inspection Checklist section below before scheduling foundation layout or excavation.
Probable cause: the preparer measured from a visible fence, hedge, or landscape edge instead of the recorded survey or plat.
Confirmation: compare the fence location with the recorded survey's property-line dimensions and monument locations.
Correction: remeasure the setback from the legally controlling reference and correct the checklist entry and marked-up site plan.
Reinspection: repeat the reference check on the corrected entry.
Probable cause: the site plan was prepared without cross-checking the recorded plat's easement notations.
Confirmation: compare the recorded plat's easement locations against the current site plan.
Correction: add the missing easement to the marked-up site plan and confirm whether it affects the buildable area or requires an encroachment agreement.
Reinspection: repeat the easement-identification check on the corrected site plan.
Probable cause: the preparer used a general or out-of-jurisdiction coverage formula instead of the adopted zoning code's own definition.
Confirmation: compare the calculation method used against the zoning code's published coverage definition.
Correction: recalculate lot coverage using the jurisdiction's own definition and correct the checklist entry.
Reinspection: repeat the coverage-calculation check with the corrected method.
Probable cause: the preparer measured height from finished grade, natural grade, or an assumed point instead of the jurisdiction's defined grade-measurement method.
Confirmation: compare the measurement method used against the zoning code's grade-definition and height-measurement rules.
Correction: remeasure the height using the correct grade reference and correct the checklist entry.
Reinspection: repeat the height-verification check with the corrected measurement.
Probable cause: a flagged item was logged but never actually submitted to the surveyor or zoning official, or a verbal answer was recorded without a name, date, or agency.
Confirmation: review the Unresolved Items and Referrals section for entries missing a recorded response, contact, or date.
Correction: submit or resubmit the question through the approved channel and record the full response before layout proceeds.
Reinspection: repeat the unresolved-item check on the completed log before authorizing foundation layout.
Probable cause: an HOA, covenant, or deed restriction was filed in the same section as government setback or coverage requirements.
Confirmation: review each entry in the zoning sections and confirm whether it originates from a government authority or a private review body.
Correction: relocate the private restriction to the Private Restrictions section and label its source accordingly.
Reinspection: repeat the sourcing check on both the zoning and private-restriction sections.
This project ends with the checklist and marked-up site plan reviewed, corrected, and archived, not left as a working draft.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| CP-025 | Identifies every applicable setback from the adopted zoning code and measures it from the legally controlling property reference | |||
| CP-026 | Calculates lot coverage, impervious coverage, or floor-area ratio using the jurisdiction's own definitions and recorded parcel dimensions | |||
| CP-027 | Identifies recorded easements, rights-of-way, and no-build areas affecting the buildable area and shows them on the marked-up site plan | |||
| CP-028 | Checks the proposed height against the height limit using the jurisdiction's defined grade point and measurement method | |||
| CP-029 | Reviews accessory-structure size, location, separation, and use limits applicable to the proposed project | |||
| CP-030 | Prepares a sourced zoning compliance checklist linking requirement, source, plan value, status, evidence, and responsible party, with unresolved items tracked to a recorded response |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Requirement | Official Source / Section | Plan Value | Status | Responsible Party | Action |
|---|---|---|---|---|---|
| Front Setback | |||||
| Side Setbacks | |||||
| Rear Setback | |||||
| Easements / No-Build Areas | |||||
| Lot Coverage | |||||
| Impervious Coverage / FAR | |||||
| Height Limit | |||||
| Accessory Structure Limits | |||||
| Parking / Access | |||||
| Environmental / Overlay Conditions | |||||
| Private Restrictions (HOA/Covenant) |
Unresolved item referred: ____________ Response and date: ____________
Marked-up site plan attached: ______ (Yes/No) Checklist archived: ______ Date: ____________ Preparer name: ____________
With all eleven checklist sections completed and recorded, review the finished checklist against the Acceptance Standards table and confirm every setback, coverage, height, and easement entry has a source and plan value, every dimension traces to the recorded survey or plat, private restrictions are recorded separately from government requirements, every unresolved item has a recorded response, and the marked-up site plan distinguishes verified dimensions from unresolved areas. Complete the Zoning Compliance Worksheet and correct any failed item before scheduling foundation layout or excavation. If an entry fails, identify whether the error occurred in sourcing, referencing, calculation, or referral before correcting and re-running the affected check.
You have completed the fifth project in the building codes, permits, and inspections sequence: building a site, setback, and zoning compliance checklist. This project required you to identify setbacks required for the proposed project from the adopted zoning code and property record (CP-025), verify lot-coverage limits using the jurisdiction's own definitions and the parcel's recorded dimensions (CP-026), identify easements, rights-of-way, and no-build areas affecting the buildable area (CP-027), check height restrictions using the jurisdiction's defined grade and measurement method (CP-028), review accessory-structure limits applicable to the proposed project (CP-029), and prepare a zoning compliance checklist linking requirement, source, plan value, status, and responsible party (CP-030).
You now have a sourced, dated zoning compliance package and a marked-up site plan distinguishing verified dimensions from unresolved areas. That verified site information carries directly into the next projects: preparing for the foundation inspection and coordinating every later trade inspection that depends on an accurate, legally supportable site plan.
Store the archived checklist, survey, and marked-up site plan where they remain available to the Chapter 3 application packet, the Chapter 6 foundation-inspection preparation, and the Chapter 20 capstone.