Project 12

Build an Energy-Code Compliance Checklist

Convert one project's approved energy documents into a field-verifiable, trade-assigned matrix covering enclosure assemblies, air sealing, fenestration, ducts, equipment, ventilation, testing, and documentation, tied to the inspection stages that must occur before concealment.

Field Cue System

These cues appear at the point of work. They identify safety, code, professional-boundary, and documentation issues before they become an unverified assumption or a concealed compliance gap.

△

Safety Cue

Task-specific guidance for site walks, attic and crawlspace access, and equipment areas during matrix verification.

✋

Critical Safety Cue

A stop-work condition: concealment, testing, or final approval must not proceed without the required document, inspection, or qualified party.

⛑

Field Safety Cue

Practical handling of trade coordination, photo documentation, and jobsite access during the pre-insulation and pre-drywall walks.

▤

Code Alert

Energy requirements, compliance paths, and testing rules vary by jurisdiction and climate zone. Verify directly rather than from memory.

▧

Professional Boundary Cue

Identifies work reserved for the design professional, energy professional, qualified tester, or building official.

▱

Documentation Cue

Recording, sourcing, and dating guidance for every value, product, and test entered into the matrix.

Job Overview

This project qualifies you to convert approved energy documents into one project-specific compliance matrix that a superintendent, trade, or inspector can use in the field. The finished work product is one energy-code compliance matrix covering enclosure assemblies, air sealing, fenestration, ducts, equipment, ventilation, testing, and documentation, with every item assigned to a responsible trade, inspection stage, verification method, and evidence requirement.

You will identify the adopted energy code and compliance path, build an assembly schedule from approved energy documents, create air-sealing and fenestration schedules, identify duct, equipment, and ventilation requirements, identify required testing, convert conflicts into clarification questions, and perform pre-insulation, pre-drywall, and pre-test reviews using the completed matrix before archiving it with test results and final documentation.

This project depends on the Project 01 reference binder for the adopted energy code and local amendments, the Project 04 code-note summary for energy notes already located on the plans, and the Project 03 application packet for the approved energy forms. It feeds directly into Project 15's interior concealment inspections, Project 16's final inspection, and the Chapter 20 capstone's energy-code matrix and testing evidence.

Skills You Will Demonstrate

  • CP-067 — Identify insulation requirements for every enclosure assembly from approved energy documents.
  • CP-068 — Verify air-sealing details and air-barrier continuity against approved plans and inspection stages.
  • CP-069 — Inspect windows and doors for approved fenestration ratings, installation, and flashing coordination.
  • CP-070 — Review duct-sealing, duct-insulation, and duct-leakage-testing requirements.
  • CP-071 — Identify ventilation, equipment, and controls requirements tied to the energy path.
  • CP-072 — Prepare a trade-assigned, inspection-staged energy-code compliance checklist supported by evidence and test results.

Where This Skill Fits

Energy-code requirements touch nearly every trade on a residential project: framing and insulation contractors, window and door installers, duct and equipment installers, and the ventilation and controls trade. Without one coordinated matrix, energy requirements are scattered across separate architectural, structural, MEP, and energy documents, and a single missed duct-sealing note or fenestration rating can fail a blower-door test, a duct-leakage test, or the final energy inspection after the assemblies are already concealed.

The matrix built in this project becomes the pre-insulation and pre-drywall readiness tool used in Project 15, and its testing evidence and product register carry directly into the Project 16 final inspection and the Project 18 closeout compliance file.

Scope and Intended Use

This project covers:

  • identifying the adopted energy code, local amendments, compliance path, and climate zone for one defined residential project
  • building an assembly schedule for walls, roofs, ceilings, floors, slabs, foundations, crawlspaces, and rim areas from approved energy documents
  • creating air-sealing and fenestration schedules tied to plan details and inspection stages
  • identifying duct, equipment, controls, and ventilation requirements from approved documents
  • identifying required testing, qualified testers, and corrective processes from approved requirements
  • converting conflicts and missing values into formal clarification questions and recording approved responses
  • performing pre-insulation, pre-drywall, and pre-test reviews using the completed matrix
  • archiving the completed matrix with products, photographs, tests, approvals, and revisions

This project does not authorize the learner to:

  • select, size, or substitute insulation values, equipment efficiencies, window ratings, or duct-sealing methods; those values come only from the approved energy documents, design professional, or manufacturer instructions
  • perform, supervise, or interpret a blower-door, duct-leakage, or other required energy test beyond the qualified tester's role and the learner's assigned documentation task
  • mix requirements from different compliance paths, such as combining prescriptive insulation values with performance-path duct-leakage targets, without design-professional approval
  • treat the completed matrix as a certificate of energy compliance, an inspection approval, or a substitute for the required final energy documentation

Reference Conventions

Establish these references before any assembly, product, or test is entered into the matrix, and apply them consistently across every matrix row.

TermDefinition
Compliance pathThe prescriptive, performance, rating, modeled, or other approved method by which the project demonstrates energy compliance
Assembly scheduleThe matrix section listing every wall, roof, ceiling, floor, slab, foundation, crawlspace, and rim assembly with its required insulation value and location
Air-barrier continuityAn unbroken air-control layer at walls, floors, roofs, ceilings, foundations, openings, penetrations, chases, fireplaces, garages, and attics as shown in approved details
Fenestration scheduleThe matrix section listing every window, door, and skylight with area, performance rating, orientation, and product documentation
Verification methodThe specific way an item will be confirmed, such as visual inspection, photograph, product label, calculation check, or test result
EvidenceThe document, photograph, label, certificate, or test report proving a matrix item was installed or performed as required

Project and Compliance Path Record

Before building any schedule, record the project, permit, and compliance-path basis directly on the matrix cover page:

Project address: ______     Permit number: ______     Authority having jurisdiction: ______

Adopted energy code and edition: ____________     Local amendments: ____________     Climate zone: ______

Compliance path (prescriptive / performance / rating / modeled / other): ______     Approved energy form reference: ____________

Date started: ____________     Preparer name: ____________

Prerequisites

Common Field Fundamentals

Every energy-code task in this book, from this chapter's assembly schedule to the Chapter 20 capstone's energy-code matrix, follows the same sequence: confirm the adopted code and compliance path, extract every required value from approved documents, assign the value to a trade and inspection stage, verify the installed condition against the value, and record the evidence. Learning that sequence here, on one project's enclosure, fenestration, duct, and equipment scope, means the interior-concealment and final-inspection projects later in this book start from a matrix you already trust.

AssembliesWall, roof, ceiling, floor, slab, foundation, crawlspace, rim insulation values
Air SealingAir-barrier continuity at plates, rims, penetrations, chases, attics
FenestrationWindow, door, skylight ratings, orientation, product documentation
Ducts and EquipmentDuct location, insulation, sealing, equipment efficiency, controls
VentilationLocal exhaust, whole-house ventilation, controls, balancing
LightingHigh-efficacy, control, and exterior-lighting requirements where applicable
TestingBlower-door, duct-leakage, ventilation, equipment-startup requirements
EvidenceProduct labels, photographs, certificates, and test reports by item

Approved Documents, Compliance Paths, and Verification Dates

Every value entered in the matrix must trace to an approved energy form, plan sheet, specification, or manufacturer instruction, with the compliance path recorded once at the matrix cover page and never mixed mid-matrix without a documented design-professional response. A matrix row without a recorded approved-document source cannot be treated as controlling.

CP-067 – CP-072

Document Review / Field Verification / Compliance Documentation Qualification

Energy-Code Compliance Matrix

Difficulty: Intermediate

Estimated Time: 6–9 hours, plus wait time for responses and test scheduling

Estimated Cost: $0–$60, plus separate testing fees paid to the qualified tester

Finished Work: One trade-assigned, inspection-staged energy-code compliance matrix with recorded evidence and test results

A. Finished-Project Specification

Scope: one project-specific energy-code compliance matrix, organized into the eight schedule sections listed in the Component Schedule below, covering one defined residential project's approved energy documents, with every item assigned to a responsible trade, inspection stage, verification method, and evidence requirement.

B. Matrix Section Schedule (Component Schedule)

SectionQuantitySource TypeRequired ContentVerification / Purpose
Cover and Compliance Path1Approved documentAdopted code, edition, local amendments, climate zone, compliance path, authorityConfirmed against Project 01 binder and approved energy form
Assembly Schedule1Approved documentWall, roof, ceiling, floor, slab, foundation, crawlspace, and rim insulation type, location, value, depth, density, installation grade, continuityTraced to approved energy form or plan detail
Air-Sealing Checklist1Approved documentAir-barrier materials and continuity at walls, floors, roofs, ceilings, foundations, openings, penetrations, chases, fireplaces, garages, atticsTied to plan details and inspection stages
Fenestration Schedule1Approved documentWindow, door, skylight area, performance rating, orientation, product documentationProduct labels and certificates retained before removal
Duct and Equipment Schedule1Approved documentDuct location, insulation, sealing, support, return pathways, access, leakage-testing requirement; equipment efficiency, controls, thermostats, zoning, heat-recovery, commissioningTraced to approved MEP and energy documents
Ventilation and Lighting Schedule1Approved documentLocal exhaust, whole-house ventilation, controls, balancing, verification; high-efficacy lighting, controls, exterior-lighting requirements where applicableTraced to approved energy and MEP documents
Testing Schedule1Approved documentBlower-door, duct-leakage, ventilation, balancing, equipment-startup, or other required testing with qualified tester, timing, equipment, target, form, corrective processTraced to approved requirements; performed only by qualified tester
Product and Evidence Register1Working documentInsulation, window, door, HVAC, water-heating, ventilation, lighting, and controls product documents; installation photographs by locationPopulated during pre-insulation and pre-drywall walks

C. Resource Takeoff

  • Approved-document set: current approved energy forms, calculations, reports, plans, specifications, equipment schedules, and revisions for the defined project.
  • Matrix hardware: one energy-matrix template with the eight sections listed in the Component Schedule, or an equivalent digital tracking sheet with matching sections.
  • Evidence documents: product labels, certificates, and installation photographs saved by assembly, fenestration item, duct run, equipment unit, and ventilation component.
  • Clarification allowance: at least one completed clarification exchange with the design professional or authority for a conflict or missing value identified while building the matrix, with the response recorded.

D. Acceptance Standards

CheckStandard
Compliance-path consistencyThe matrix uses one recorded compliance path throughout, with any path mixing traced to a documented design-professional response
Value sourcingEvery assembly, air-sealing, fenestration, duct, equipment, and ventilation entry traces to an approved energy document, plan sheet, or manufacturer instruction
Trade and stage assignmentEvery matrix item is assigned to a responsible trade, inspection stage, verification method, and evidence requirement
Section completenessAll eight matrix sections listed in the Component Schedule are present, populated, and correctly labeled
Pre-insulation and pre-drywall walkBoth readiness walks are completed using the matrix, with findings recorded in the verification-method and evidence columns
Testing evidenceEvery required test has a recorded qualified tester, date, result, and corrective action where applicable
Revision controlThe archived matrix version carries a revision date, change log, and assigned reviewer

E. Preparation — Confirm Code, Path, and Approved Documents

  1. Identify the adopted energy code, local amendments, compliance path, climate zone, project type, and authority. Confirm this against the Project 01 reference binder before entering any value into the matrix.
  2. Obtain approved energy forms, calculations, reports, plans, specifications, equipment schedules, and revisions. Record the current revision date for each document on the matrix cover page.
  3. Confirm whether compliance uses prescriptive, performance, rating, modeled, or other approved path. Record the confirmed path and its source document.
  4. Do not mix requirements from different compliance paths without design-professional approval. Flag any apparent mixing as a clarification question rather than resolving it independently.

F. Build the Assembly, Air-Sealing, and Fenestration Schedules

  1. Create an assembly schedule for walls, roofs, ceilings, floors, slabs, foundations, crawlspaces, and rim areas. List every distinct assembly by location using the approved energy form's own assembly identifiers.
  2. Record required insulation type, location, value, depth, density, installation grade, and continuity from approved documents. Enter one complete row per assembly; do not leave any column blank without marking it unresolved.
  3. Identify thermal bridges, narrow cavities, headers, corners, eaves, knee walls, attic access, and difficult transitions requiring field attention. Note each condition against the affected assembly row.
  4. Identify air-barrier materials and continuity at walls, floors, roofs, ceilings, foundations, openings, penetrations, chases, fireplaces, garages, and attics. Reference the controlling detail sheet for each location.
  5. Create an air-sealing checklist tied to plan details and inspection stages. Assign each air-sealing item to the inspection stage at which it must remain visible.
  6. Identify vapor-control and moisture-management requirements without adding an unapproved layer. Record only the layer shown in the approved assembly; flag any apparent omission as a clarification question.
  7. Create a fenestration schedule with window, door, skylight, area, performance rating, orientation, and product documentation. List every opening using the approved window and door schedule's own tag numbers.
  8. Verify product labels, certificates, ratings, and approved substitutions are retained before installation labels are removed. Photograph each label before it is covered or discarded.
  9. Identify window and door installation, flashing, insulation, and air-sealing checkpoints. Cross-reference the Project 08 envelope-inspection checklist for the shared flashing details.

G. Build the Duct, Equipment, and Ventilation Schedules

  1. Identify duct location, insulation, sealing, support, return pathways, access, and leakage testing requirements. Record each duct run and its required sealing method from the approved energy form.
  2. Identify piping insulation, equipment efficiency, controls, thermostats, zoning, heat-recovery, and commissioning requirements. Record equipment identifiers matching the approved equipment schedule.
  3. Identify local exhaust, whole-house ventilation, makeup air, controls, balancing, and verification requirements. Record each ventilation component and its required verification method.
  4. Identify lighting, high-efficacy, control, exterior-lighting, and other electrical energy requirements where applicable. Record only where the approved documents include a lighting energy requirement.
  5. Identify blower-door, duct-leakage, ventilation, balancing, equipment-startup, or other required testing. Record the required test type, target, and timing from approved requirements.
  6. Identify qualified tester, timing, equipment, target, form, and corrective process from approved requirements. Confirm the tester's qualification before scheduling.
  7. Identify inspections that must occur before insulation, drywall, exterior finish, equipment enclosure, or final approval. Assign each matrix item to its controlling concealment stage.

H. Assign Responsibility, Resolve Conflicts, and Verify in the Field

  1. Create installation photo requirements for concealed air, thermal, duct, and flashing details. List the specific location and angle required for each photograph.
  2. Create a product-document register for insulation, windows, doors, HVAC, water heating, ventilation, lighting, and controls. File each product's label, certificate, or rating alongside its matrix row.
  3. Compare architectural, structural, MEP, and energy documents for conflicts. Note every discrepancy found between the assembly schedule and the architectural or structural drawings.
  4. Convert conflicts and missing values into formal clarification questions. Use the clarification-question log rather than resolving the conflict independently.
  5. Record approved responses and revise the matrix. Update the affected row and note the response date and source.
  6. Assign every item to responsible trade, inspection stage, verification method, and evidence. Complete these four columns for every row before the matrix is used in the field.
  7. Perform a pre-insulation walk using the matrix. Verify framing cavities, air-sealing items, and rough utilities against the matrix before insulation begins.
  8. Perform an insulation and air-sealing readiness review before concealment. Confirm every assembly and air-sealing row is installed as specified and photographed.
  9. Perform a pretest review before blower-door or duct testing. Confirm the building is ready for the test conditions specified by the qualified tester.
  10. Record test results, corrective actions, retests, and final acceptance. Enter results directly into the Testing Schedule with the tester's name and date.
  11. Verify final certificates, labels, forms, manuals, and owner information are installed or delivered as required. Confirm this against the approved energy form's closeout requirements.
  12. Archive the completed energy matrix, products, photographs, tests, approvals, and revisions. Record the archive date, version number, and a summary of what was verified.

Common Matrix Inspection

Inspect the finished matrix using the same checks regardless of which section is being reviewed.

Complete the Matrix Verification Worksheet in the Inspection Checklist section below before beginning Project 13.

Image Placeholder
Recommended image: a completed assembly-schedule row showing location, insulation type, value, and approved-document reference.
Image Placeholder
Recommended image: a fenestration schedule with window and door tags matched to product labels before installation-label removal.
Image Placeholder
Recommended image: a pre-insulation walk in progress, with the matrix in hand and a concealed air-sealing detail photographed.
Image Placeholder
Recommended image: a testing-schedule row showing qualified tester, date, target, and recorded result.

Failure Points and Troubleshooting

Cleanup

This project ends with the first controlled matrix version archived and ready for reuse in later inspection projects, not left as a working draft.

Field Terms

Compliance Path
The prescriptive, performance, rating, modeled, or other approved method by which a project demonstrates energy compliance.
Assembly Schedule
The matrix section listing every enclosure assembly with its required insulation value and location.
Air-Barrier Continuity
An unbroken air-control layer at every wall, floor, roof, ceiling, foundation, opening, penetration, chase, fireplace, garage, and attic shown in approved details.
Fenestration Schedule
The matrix section listing every window, door, and skylight with area, performance rating, orientation, and product documentation.
Verification Method
The specific way a matrix item will be confirmed, such as visual inspection, photograph, product label, or test result.
Evidence
The document, photograph, label, certificate, or test report proving a matrix item was installed or performed as required.
Qualified Tester
The individual or agency identified by the approved requirements as authorized to perform blower-door, duct-leakage, or other required energy tests.
Clarification-Question Log
The document recording conflicts and missing values converted into formal questions, with approved responses.
Pre-Insulation Walk
The matrix-driven field review confirming assembly and air-sealing items before insulation conceals them.
Revision Control
Tracking the matrix's version number, archive date, and change log so outdated values are not mistaken for current ones.

Skill Check

  1. Why must every insulation value in the assembly schedule trace to this project's approved energy form rather than a similar project's matrix?
  2. What is the risk of mixing prescriptive and performance-path requirements without a documented design-professional response?
  3. What four items must every matrix row include before it can be used in the field?
  4. Why must product labels be photographed before installation labels are removed?
  5. What must occur before insulation, drywall, or exterior finish conceals a matrix item?
  6. Who is authorized to perform a required blower-door or duct-leakage test, and why can the learner not perform it independently?
  7. What is the purpose of the pre-insulation and pre-drywall walks, and what does a failed walk indicate?
  8. What are three possible causes of a value mismatch between the matrix and the approved documents, and how does the learner confirm which one occurred?
  9. What must the learner do before archiving the first controlled matrix version?
  10. Why does this chapter require conflicts and missing values to be converted into formal clarification questions rather than resolved independently?

Competency Rubric

CompetencyIndependent Pass StandardNot DemonstratedWith AssistanceIndependently
CP-067Identifies insulation requirements for every enclosure assembly and traces each value to its approved-document source
CP-068Verifies air-sealing details and air-barrier continuity against approved plans and assigns each item to its inspection stage
CP-069Inspects windows and doors for approved fenestration ratings, installation, and flashing coordination, with product evidence retained
CP-070Reviews duct-sealing, duct-insulation, and duct-leakage-testing requirements against approved MEP and energy documents
CP-071Identifies ventilation, equipment, and controls requirements tied to the confirmed compliance path
CP-072Prepares, field-verifies, tests, corrects, and archives a trade-assigned, inspection-staged energy-code compliance checklist

Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.

Inspection Checklist — Matrix Verification Worksheet

SectionSource TypeApproved-Document ReferenceTrade AssignedVerification MethodEvidence / Correction
Cover and Compliance Path
Assembly Schedule
Air-Sealing Checklist
Fenestration Schedule
Duct and Equipment Schedule
Ventilation and Lighting Schedule
Testing Schedule
Product and Evidence Register

Clarification item contacted: ____________     Response and date: ____________

Pre-insulation walk result: ______ (Pass/Fail)     Matrix version archived: ______     Date: ____________     Reviewer name: ____________

Performance Check

With all eight matrix sections assembled and recorded, review the finished matrix against the Acceptance Standards table and confirm every value has an approved-document source, every row is assigned to a trade, inspection stage, verification method, and evidence requirement, the pre-insulation and pre-drywall walks are recorded, every required test carries a qualified tester and result, and the archived version carries a revision date and change log. Complete the Matrix Verification Worksheet and correct any failed item before beginning Project 13. If an entry fails, identify whether the error occurred in sourcing, assignment, field verification, testing, or archiving before correcting and re-running the affected check.

Project Closeout

You have completed the twelfth project in the building codes, permits, and inspections sequence: building an energy-code compliance checklist. This project required you to identify insulation requirements for every enclosure assembly from approved energy documents (CP-067), verify air-sealing details and air-barrier continuity against approved plans and inspection stages (CP-068), inspect windows and doors for approved fenestration ratings, installation, and flashing coordination (CP-069), review duct-sealing and duct-leakage-testing requirements (CP-070), identify ventilation, equipment, and controls requirements tied to the energy path (CP-071), and prepare a trade-assigned, inspection-staged energy-code compliance checklist supported by evidence and test results (CP-072).

You now have a verified, source-traced energy-code matrix and a repeatable field-verification method you can apply to any future residential project's enclosure, fenestration, duct, equipment, and ventilation scope. That system carries directly into the next project: building the fire, smoke, carbon monoxide, and egress checklist that governs life-safety compliance for the same project.

Store the archived matrix version where it remains available to Project 15's interior concealment inspections, Project 16's final inspection, and the Chapter 20 capstone. You will recheck and reuse this exact matrix throughout the rest of this book.