Project 01

Define the Scope of a Residential Construction Project

Define and gain approval for one residential project scope statement that establishes objectives, deliverables, inclusions, exclusions, stakeholders, responsibilities, assumptions, constraints, acceptance conditions, and change boundaries, using the owner's request, executed agreement, drawings, and approved project documents as the controlling information.

Field Cue System

These cues appear at the point of work. They identify scope, authority, documentation, and decision issues before they become disputes, unpriced work, or unauthorized changes.

△

Scope Cue

Task-specific guidance for ordinary scope-definition and boundary issues.

✋

Critical Scope Cue

A contract dispute, unpriced work, or unauthorized scope expansion is possible.

⛑

Field Coordination Cue

Practical stakeholder and field coordination: contacts, access, and communication.

▤

Authority Alert

Permit, code, lender, HOA, or authority conditions vary. Verify before assuming.

▧

Contract Instruction Cue

Follow the executed agreement's specific terms for authority, notice, and approval.

▱

Documentation Cue

Recordkeeping, version-control, and traceability guidance for scope documents.

Job Overview

This project qualifies you to define and gain approval for a residential project scope statement — the controlling document that establishes what the project includes, what it excludes, who has authority over what decisions, and how change will be handled. The finished work product is one approved, version-controlled scope statement supported by a stakeholder list, a responsibility matrix, documented assumptions and constraints, and a resolved scope-gap list.

You will collect and review the owner request and executed project documents, define measurable objectives and the completed physical outcome, identify mandatory authority conditions, list every deliverable required for owner acceptance, define inclusions and explicit exclusions, identify stakeholders and their decision authority, document assumptions and constraints, compare the draft scope against the estimate and permit plan, resolve gaps and ambiguities, and obtain written approval of the baseline.

This is the first project in the book. It establishes the single controlling scope baseline that every later project in this book depends on: the job file in Project 02, the work breakdown structure in Project 03, the schedule in Project 04 and Project 05, procurement in Project 06, trade coordination in Project 07, and every planning document through the Chapter 20 capstone all trace back to the scope statement produced here.

Skills You Will Demonstrate

  • PM-001 — Identify project objectives.
  • PM-002 — Define included work.
  • PM-003 — Define excluded work.
  • PM-004 — Identify stakeholders.
  • PM-005 — Document assumptions.
  • PM-006 — Create a project scope statement.

Where This Skill Fits

Every later document in this book depends on the scope baseline produced here. The job file in Project 02 is organized around the sections and references this scope statement establishes. The work breakdown structure in Project 03 converts this scope statement's deliverables into schedulable, cost-coded work packages. The change-control system in Project 11 exists specifically to prevent informal expansion of the baseline you approve in this project.

The discipline of separating included work, excluded work, allowances, alternates, and future phases — taught in this chapter — is the same discipline used later to separate original contract scope from approved and pending changes throughout the rest of the book.

Scope and Intended Use

This project covers:

  • collecting and reviewing the owner request, executed agreement, estimate, drawings, specifications, addenda, permits, and prior correspondence
  • defining measurable business and owner objectives and the completed physical outcome
  • identifying mandatory permit, code, design, lender, insurer, utility, HOA, and authority conditions
  • listing every primary deliverable required for owner acceptance, including temporary work, demolition, and closeout deliverables
  • defining included design, procurement, and installation responsibilities, and identifying owner-furnished and third-party work
  • writing explicit exclusions and distinguishing them from deferred work, alternates, allowances, and future phases
  • identifying stakeholders, their authority, and a responsibility matrix
  • documenting existing-condition information, assumptions, and constraints
  • comparing the draft scope against the estimate and permit plan, resolving gaps, and obtaining approval of the baseline

This project does not authorize the learner to:

  • interpret contract law, render a legal opinion, or resolve a contract dispute; the scope statement is a project-management coordination document, not a legal instrument
  • make design, engineering, or code-compliance decisions; those remain with the licensed design professional, engineer, or authority having jurisdiction
  • approve cost, schedule, design, or scope changes without the authority identified in Step 16 of the procedure below
  • treat a verbal owner conversation, text message, or field sketch as sufficient authorization to expand the approved scope baseline once it is frozen

Any conflict between the owner request, the executed agreement, the drawings, and prior correspondence must be identified and resolved in writing before the scope baseline is approved.

Reference Conventions

Establish these references before drafting begins, and do not change them mid-document without a recorded revision.

TermDefinition
Scope baselineThe one current, approved version of the scope statement all other project documents are built from
Included workWork the contractor is responsible to perform, furnish, or coordinate under the approved scope
Excluded workWork stated in plain language as outside the contractor's responsibility under the approved scope
Deferred workWork recognized as needed but scheduled for a later phase, not included in this scope baseline
AllowanceA budgeted amount for a category of work or material where the final selection is not yet made
AlternateAn optional scope item priced separately from the base scope, accepted or declined by the authorized approver
Decision authorityThe specific named person or role authorized to approve scope, cost, schedule, design, or acceptance decisions

Scope Baseline Record

Before distributing the approved scope statement, record the baseline identification directly on the scope-approval record:

Project name: ______     Project address: ______     Baseline number: ______     Revision: ______

Date approved: ____________     Approved by (name and role): ____________     Project manager: ____________

Prerequisites

Common Field Fundamentals

Every scope statement in this book, from this chapter's residential scope baseline to the Chapter 20 capstone project charter, follows the same sequence: collect, define, bound, assign, document, reconcile, approve. Learning that sequence here, on one residential project, means every later planning document starts from a method you already trust.

ObjectivesMeasurable business and owner objectives, defined before any deliverable list
DeliverablesEvery item required for the owner to accept the completed work
Inclusions / ExclusionsPlain-language boundaries, distinguished from deferred work, allowances, and alternates
StakeholdersNamed parties, their interest, authority, and required communication
Responsibility matrixOne primary responsible party assigned to each category of work
Assumptions / constraintsRecorded as managed conditions, not buried in notes
ReconciliationScope checked against the estimate and the permit-and-inspection plan
Baseline approvalWritten approval, baseline number, date, and distribution to the project team

Included Work, Excluded Work, and Deferred Work

Every scope statement must state what the contractor will perform, furnish, or coordinate, and separately, what the contractor will not. Write exclusions immediately after the related inclusion so a reader cannot mistake a deferred item, an allowance, or an alternate for a firm inclusion or a firm exclusion. An item left ambiguous between included and excluded becomes an unpriced scope dispute once construction begins.

PM-001 – PM-006

Scope Definition / Planning Qualification

Residential Project Scope Statement

Difficulty: Beginner

Estimated Time: 4–6 hours plus review cycles

Estimated Cost: No direct material cost

Finished Work: One approved, version-controlled scope statement with stakeholder list, responsibility matrix, and resolved scope-gap list

A. Finished-Project Specification

Deliverable: one approved residential project scope statement, containing measurable objectives, the completed physical outcome, mandatory authority conditions, a complete deliverable list, defined inclusions and exclusions, a stakeholder list, a responsibility matrix, documented assumptions and constraints, and a defined change-approval process, reconciled against the estimate and permit plan and approved by the authorized party.

B. Scope Statement Document Schedule

SectionContentSourcePurpose
Project identificationAddress, property boundaries, project type, delivery method, intended useOwner request, agreement, permit applicationEstablishes the project the scope statement governs
ObjectivesBusiness and owner objectives stated in measurable termsOwner request, agreementDefines what success means for the project
Completed physical outcomeOutcome by area, system, room, structure, and tradeDrawings, specificationsDefines the physical result the owner will accept
Authority conditionsMandatory permit, code, design, lender, insurer, utility, HOA conditionsPermits, agreement, authority requirementsIdentifies conditions that must be satisfied regardless of contractor preference
DeliverablesEvery item required for owner acceptance, including temporary work and closeout itemsAgreement, drawings, specificationsDefines the complete list the owner will check against at handoff
Inclusions / exclusionsIncluded design, procurement, installation responsibilities; explicit exclusions; deferred work; allowances; alternatesAgreement, estimate, owner selectionsBounds the contractor's responsibility in plain language
StakeholdersName or role, organization, interest, authority, contact methodAgreement, project directoryIdentifies who must be consulted, informed, or asked to approve
Responsibility matrixOwner, contractor, subcontractors, suppliers, designer, inspectors, utilities, other partiesAgreement, permit planPrevents two parties from each assuming the other owns a task
Assumptions / constraintsDimensions, access, hours, utilities, occupancy, weather, soil, structure, budget, schedule, neighborhoodField observation, agreement, owner inputRecords conditions the scope statement depends on rather than burying them in notes
Quality and acceptanceQuality and performance requirements; milestone and completion conditions without unsupported datesDrawings, specifications, samples, manufacturer instructionsDefines how the owner and contractor will recognize the work as complete
Change processProcess for RFIs, substitutions, hidden conditions, owner requests, delays, change ordersAgreement, company policyDefines how the baseline may be modified after approval

C. Information and Document Takeoff

  • Source records: owner request, executed agreement or proposal, approved estimate, drawings, specifications, addenda, permits, and prior correspondence, sufficient to draft every section of the document schedule above without inventing missing information.
  • Comparison records: the Book 24 estimate and the Book 25 permit-and-inspection plan, used in Steps 26–27 to identify priced items, unpriced items, gaps, duplications, regulated work, and permit-holder responsibilities.
  • Approval record: written confirmation of the person or role authorized to approve scope, cost, schedule, design, and final acceptance, obtained before drafting begins.
  • Revision control: a baseline numbering and archive convention sufficient to distinguish the current approved scope statement from every superseded draft.

D. Acceptance Standards

CheckStandard
ObjectivesStated in measurable terms; not merely a general aspiration
DeliverablesEvery item required for owner acceptance is listed individually, not implied
ExclusionsStated in language understandable without trade assumptions; distinguished from deferred work, allowances, and alternates
Stakeholders and authorityEvery stakeholder identified with role, organization, and contact method; decision authority explicitly named for scope, cost, schedule, design, and acceptance
Assumptions and constraintsRecorded as a managed log, not embedded only in narrative text
ReconciliationScope compared against the estimate and permit plan; gaps and duplications identified and resolved before approval
ApprovalWritten approval obtained from the authorized party; baseline number and date assigned before distribution

E. Preparation — Collect Documents and Identify Project Basics

  1. Collect the owner request, executed agreement or proposal, approved estimate, drawings, specifications, addenda, permits, clarifications, selections, and prior correspondence. Assemble every available document before drafting begins.
  2. Identify the project address, property boundaries, occupied conditions, project type, delivery method, and intended use. Record these facts from the agreement and permit application.
  3. Define the business and owner objectives in measurable terms. State the objective in terms that can later be checked as met or not met.
  4. Define the completed physical outcome by area, system, room, structure, and trade. Draw the outcome directly from the approved drawings and specifications.
  5. Identify mandatory permit, code, design, lender, insurer, utility, HOA, and authority conditions. Record each condition and the document or authority that establishes it.
  6. List every primary deliverable required for the owner to accept the work. Include each deliverable individually rather than as a general category.

F. Objectives, Deliverables, and Authority Conditions

  1. List temporary work, protection, access, utilities, storage, sanitation, security, and cleanup needed to deliver the project. Record these as deliverables even though they are not part of the permanent finished work.
  2. Identify demolition, salvage, disposal, testing, inspection, commissioning, training, warranty, and closeout deliverables. Record each as an individual item on the deliverable list.
  3. Define included design, engineering, surveying, selections, submittals, mockups, samples, and shop-drawing responsibilities. State which party is responsible for each.
  4. Define included procurement, delivery, unloading, staging, installation, startup, and warranty responsibilities. State which party is responsible for each.
  5. Identify owner-furnished, contractor-installed and owner-furnished, owner-installed items. List each item and its furnishing and installation responsibility separately.
  6. Identify work by utility, municipality, separate contractor, landlord, tenant, HOA, designer, or other third party. Record the party and the work they are responsible for.
  7. Define explicit exclusions in language that can be understood without trade assumptions. State each exclusion as a specific item, not a general category.
  8. Distinguish excluded work from deferred work, alternates, allowances, and future phases. Label each item with its correct category rather than leaving it ambiguous.
  9. Identify stakeholders by name or role, organization, interest, authority, contact method, and required communication. Build the stakeholder list from the agreement and project directory.
  10. Identify the person authorized to approve scope, cost, schedule, design, and final acceptance. Confirm this authority in writing before proceeding.
  11. Create a responsibility matrix for owner, contractor, subcontractors, suppliers, designer, inspectors, utilities, and other parties. Assign one primary responsible party to each category of work.

G. Exclusions, Assumptions, and Constraints

  1. Document existing-condition information and conditions that remain concealed or unverified. State clearly which existing conditions have not been confirmed by direct observation.
  2. Document assumptions concerning dimensions, access, working hours, utilities, occupancy, weather, soil, structure, and existing systems. Record each assumption individually in the assumptions log.
  3. Document constraints concerning permits, budget, financing, schedule, neighborhood, storage, noise, dust, parking, and seasonal work. Record each constraint individually in the constraints log.
  4. Define quality and performance requirements using approved documents, samples, manufacturer instructions, and acceptance criteria. Cite the controlling document for each requirement rather than describing it generally.
  5. Define milestone and completion conditions without assigning unsupported dates. State the condition that defines each milestone; leave date assignment to the Project 04 schedule.
  6. Define how owner selections and allowance decisions will be made and by what deadlines. Record the decision process and the consequence of a missed deadline.
  7. Define the process for RFIs, substitutions, hidden conditions, owner requests, delays, and change orders. Reference the change-control process established for the project.
  8. Define which work may not begin until approval, permit, inspection, selection, or payment condition is satisfied. List each hold condition and the work it affects.

H. Draft, Reconcile, and Approve the Scope Statement

  1. Compare the scope against the Book 24 estimate and identify priced items, unpriced items, gaps, and duplicated items. Record every discrepancy found.
  2. Compare the scope against the Book 25 permit plan and identify regulated work and permit-holder responsibilities. Confirm each regulated item is assigned to the correct responsible party.
  3. Create a scope-gap and ambiguity list. Record every unresolved item discovered during Steps 26–27 in the scope-gap log.
  4. Resolve gaps through written clarification, approved assumption, allowance, alternate, exclusion, or contract revision. Do not leave a gap-log item unresolved when the draft is submitted for review.
  5. Prepare the draft scope statement in logical project sequence. Follow the document schedule in Section B.
  6. Review the draft with the owner, project manager, estimator, field lead, designer, and key trades as applicable. Distribute the draft far enough in advance for informed review.
  7. Record comments and revise the statement without deleting unresolved risk. Preserve a record of every comment received and how it was addressed.
  8. Obtain approval from the authorized parties. Confirm the approval is from the person or role identified in Step 16.
  9. Assign the scope baseline number and date. Record both directly on the scope-approval record.
  10. Distribute the approved scope and archive the superseded drafts. Move superseded drafts to the archive location so they cannot be mistaken for the current baseline.
  11. Create a change-control rule preventing informal expansion of the approved baseline. State the rule in the scope statement itself and confirm it matches the process defined in Step 24.

Common Scope-Statement Inspection

Inspect every scope statement using the same checks regardless of project size or complexity.

Complete the Scope Statement Inspection Checklist in the Inspection Checklist section below before beginning Project 02.

Image Placeholder
Recommended image: a completed scope statement cover page showing project identification, baseline number, revision, and approval block.
Image Placeholder
Recommended image: a responsibility matrix table showing owner, contractor, subcontractor, and designer columns with assigned tasks.
Image Placeholder
Recommended image: a stakeholder list showing name, role, organization, authority, and contact method columns.
Image Placeholder
Recommended image: a scope-gap and ambiguity log with columns for item, description, resolution, and date closed.
Image Placeholder
Recommended image: a side-by-side comparison of the scope statement deliverable list against the estimate line items, with gaps highlighted.
Image Placeholder
Recommended image: a document register entry showing an active baseline version and a superseded draft moved to archive status.

Failure Points and Troubleshooting

Cleanup

This project ends with the approved scope statement filed and distributed, not left as an open draft.

Field Terms

Scope Baseline
The one current, approved version of the scope statement all other project documents are built from.
Included Work
Work the contractor is responsible to perform, furnish, or coordinate under the approved scope.
Excluded Work
Work stated in plain language as outside the contractor's responsibility under the approved scope.
Deferred Work
Work recognized as needed but scheduled for a later phase, not included in this scope baseline.
Allowance
A budgeted amount for a category of work or material where the final selection is not yet made.
Alternate
An optional scope item priced separately from the base scope, accepted or declined by the authorized approver.
Decision Authority
The specific named person or role authorized to approve scope, cost, schedule, design, or acceptance decisions.
Responsibility Matrix
A control assigning one primary responsible party to each task, used whenever multiple parties could reasonably assume the other owns it.
Scope-Gap List
A log of ambiguities or discrepancies discovered when comparing the scope statement against the estimate and permit plan.
Change-Control Rule
The written rule preventing informal expansion of the approved scope baseline without required authorization.

Skill Check

  1. Why must the scope statement be built from the executed agreement and approved project documents rather than an unconfirmed verbal understanding?
  2. What is the difference between excluded work and deferred work, and why must a scope statement distinguish them?
  3. What happens to a scope statement's baseline status if a superseded draft is not moved to the archive location?
  4. Why must exactly one primary responsible party be assigned to each task in the responsibility matrix?
  5. What two documents must the draft scope statement be reconciled against before it is approved, and what is each comparison intended to reveal?
  6. Who is authorized to approve the scope baseline, and why must this be confirmed before drafting begins rather than after the draft is complete?
  7. Why must assumptions and constraints be recorded in a managed log rather than only described in narrative text?
  8. What are three possible causes of a disputed exclusion during construction, and how does the learner confirm which one occurred?
  9. What must the learner do before an approved scope baseline can be expanded, according to the change-control rule?
  10. Why does this chapter require the scope statement to be distributed to every identified stakeholder rather than only the owner?

Competency Rubric

CompetencyIndependent Pass StandardNot DemonstratedWith AssistanceIndependently
PM-001Defines business and owner objectives in measurable terms drawn from the owner request and executed agreement
PM-002Lists every included deliverable, design, procurement, and installation responsibility required for owner acceptance
PM-003Writes explicit exclusions in plain language and correctly distinguishes them from deferred work, allowances, and alternates
PM-004Identifies every stakeholder with role, organization, authority, and contact method, and names the decision authority for scope, cost, schedule, design, and acceptance
PM-005Documents assumptions and constraints individually in a managed log rather than embedding them only in narrative text
PM-006Produces an approved, version-controlled scope statement reconciled against the estimate and permit plan with a resolved scope-gap list

Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.

Inspection Checklist — Scope Statement Inspection Checklist

ItemStandardMeets Standard (Y/N)Correction (if any)
ObjectivesStated in measurable terms
Physical outcomeDefined by area, system, room, structure, and trade
Authority conditionsPermit, code, design, lender, insurer, utility, HOA conditions identified
DeliverablesEvery item required for owner acceptance listed individually
Inclusions / exclusionsPlain-language exclusions, distinguished from deferred work, allowances, and alternates
StakeholdersNamed with role, organization, authority, contact method
Responsibility matrixOne primary responsible party per category of work
Assumptions / constraintsRecorded individually in a managed log
ReconciliationCompared against estimate and permit plan; gaps resolved
ApprovalWritten approval by authorized party; baseline number and date assigned

Scope-gap log status: ____________     Open items carried forward: ____________

Scope baseline declared approved: ______ (Pass/Fail)     Date: ____________     Project manager name: ____________

Performance Check

With the scope statement drafted and reconciled, review it against the Acceptance Standards table and confirm every objective is measurable, every deliverable required for owner acceptance is listed individually, every exclusion is written in plain language and correctly distinguished from deferred work, allowances, and alternates, every stakeholder is identified with contact information and decision authority, assumptions and constraints are recorded in a managed log, the scope has been reconciled against the estimate and permit plan with every gap resolved, and written approval has been obtained from the authorized party with a baseline number and date assigned. Complete the Scope Statement Inspection Checklist and correct any failed item before beginning Project 02. If an item fails, identify whether the error occurred in document collection, objective definition, deliverable listing, exclusion language, stakeholder identification, responsibility assignment, assumption documentation, or reconciliation before revising.

Project Closeout

You have completed the first project in the construction project management sequence: defining and approving the scope of a residential construction project. This project required you to identify project objectives (PM-001), define included work (PM-002), define excluded work (PM-003), identify stakeholders (PM-004), document assumptions (PM-005), and create a project scope statement (PM-006).

You now have an approved, version-controlled scope baseline, a stakeholder list, a responsibility matrix, and a resolved scope-gap list. That baseline carries directly into the next project: setting up the controlled project management job file that will organize every document, log, and record this scope statement has identified as required.

File your approved scope statement, responsibility matrix, and reconciliation records where Project 02 can incorporate them into the project job file. Every later planning document in this book is built from this exact scope baseline.