Scope Cue
Task-specific guidance for ordinary channel-selection and message-drafting issues.
Project 17
Create and operate one project communication plan that routes decisions, notices, schedule information, trade coordination, supplier status, emergencies, and records through defined channels and authority levels, using the approved scope, job file, schedule, RFI, change, safety, quality, and closeout systems built in Projects 01 through 16 as the controlling project information.
These cues appear at the point of work. They identify channel, authority, confidentiality, and record-keeping issues before they become missed notices, unauthorized direction, or lost decisions.
Task-specific guidance for ordinary channel-selection and message-drafting issues.
An unauthorized instruction, missed contractual notice, or confidentiality breach is possible.
Practical stakeholder and field coordination: contacts, access, and communication.
Contractual notice, permit, or authority communication requirements vary. Verify before assuming.
Follow the executed agreement's specific notice address, method, and timeframe.
Recordkeeping, register, and traceability guidance for communication records.
This project qualifies you to create and operate a project communication plan — the controlling system that determines which channel carries which kind of information, who has authority to speak for the project, how decisions and notices are documented, and how communication records are preserved. The finished work product is one issued communication plan supported by an owner-decision log, trade and supplier notification templates, a communication register, and a completed audit of a sample of records.
You will identify every stakeholder and their information needs, define channels for emergencies, formal notices, owner decisions, field coordination, schedule updates, RFIs, changes, billing, safety, quality, and closeout, define response-time and escalation rules, build an owner-decision log and schedule-notice procedure, create trade and supplier notification templates, establish a field-conversation confirmation process, protect confidential information, build a communication register, and audit a sample of communications for completeness before archiving the plan.
This project depends on the scope baseline from Project 01, the job file from Project 02, the schedule and lookahead from Projects 05 and 06, the trade-handoff system from Project 08, the coordination-meeting record from Project 09, the RFI system from Project 10, the change-control system from Project 11, the safety plan from Project 12, the quality plan from Project 13, and the inspection-approval record from Project 16. It supplies the controlled communication record that Project 18 closeout, Project 19 owner handoff, and the Chapter 20 capstone all depend on.
Every prior project in this book generates communication that this plan must route and preserve: schedule updates from Project 05, lookahead publication from Project 06, procurement notices from Project 07, trade handoffs from Project 08, meeting minutes from Project 09, RFI distribution from Project 10, change notices from Project 11, safety and quality communication from Projects 12 and 13, and inspection results from Project 16. This project does not create new project content; it creates the controlled channels, authority rules, and records that carry the content already produced.
The discipline built here — one controlling channel per subject, written confirmation of verbal direction, and a preserved register — is the same discipline the Project 18 closeout package and the Project 19 owner handoff depend on to prove that decisions, notices, and approvals actually occurred.
This project covers:
This project does not authorize the learner to:
Any conflict between an informal communication and the contractually required notice method must be identified and resolved in writing before the informal communication is treated as controlling.
Establish these references before the plan is drafted, and do not change them mid-project without a recorded revision.
| Term | Definition |
|---|---|
| Controlling channel | The one defined communication method that governs a given subject when duplicate or conflicting messages exist |
| Formal notice | A communication delivered by the method and to the address the executed agreement requires for contractual effect |
| Owner-decision log | The controlled record of decisions requested from the owner, the options presented, and the response received |
| Field-conversation confirmation | A written record confirming the content of an important telephone or verbal direction |
| Communication register | The master log of project communications by date, sender, recipient, subject, type, required action, and file location |
| Escalation path | The defined sequence of contacts and timeframes used when a response-time expectation is not met |
| Distribution list | A defined set of recipients for a given subject or project phase, used to route communications consistently |
Before distributing the issued communication plan, record the plan identification directly on the plan-approval record:
Project name: ______ Project address: ______ Plan revision: ______ Date issued: ______
Issued by (name and role): ____________ Project manager: ____________ Distribution confirmed to stakeholder list: ______ (Y/N)
Every communication plan in this book, from this chapter's residential channel structure to the Chapter 20 capstone project record, follows the same sequence: identify, channel, authorize, template, confirm, protect, register, audit. Learning that sequence here, on one residential project, means the closeout and handoff documents in Projects 18 and 19 start from records you already trust.
Every communication plan must state, for each subject, which channel is controlling when duplicate or conflicting messages exist. Write the controlling-channel rule immediately next to the channel it governs so a reader cannot mistake a convenient message for the one that carries contractual or scheduling effect. A subject left without a stated controlling channel becomes a disputed notice once a deadline or delay is contested.
Every communication register entry must carry a date, sender, recipient, subject, type, required action, due date, and file location. Do not log a communication without its file location. Recording only the subject line, without the file reference, allows a critical notice or decision to become unlocatable later in the project.
Do not allow an owner request made directly to a trade or supplier to be treated as authorization to change scope, price, or schedule. Every such request must be routed through the authorized channel and decision maker identified in Step 6, confirmed in writing, and evaluated through the change-control process from Project 11 before work proceeds.
Confirm the current name, role, organization, and preferred contact method for every stakeholder before a distribution list is used. A notification routed to an outdated contact, or missing a required recipient, delays action and creates confusion about who received what information.
Where the executed agreement specifies a particular method, address, or timeframe for a formal notice, follow that method exactly. Do not substitute an informal communication channel, such as a group message, for the notice method the contract requires, even when it would be faster.
PM-097 – PM-102
Communication Control / Coordination Qualification
Deliverable: one issued residential project communication plan, containing defined channels for every listed subject, controlling-channel rules, response-time and escalation paths, defined direction authority, an owner-decision log, a schedule-notice procedure, trade and supplier notification templates, a field-conversation confirmation process, confidentiality restrictions, a communication register, and a completed audit of a sample of records.
| Section | Content | Source | Purpose |
|---|---|---|---|
| Stakeholder information needs | What each stakeholder needs, provides, approves, or receives | Project 01 stakeholder list | Establishes who must be reached for each subject |
| Channel definitions | Emergencies, formal notices, owner decisions, field coordination, schedule updates, RFIs, changes, billing, safety, quality, closeout | Executed agreement, company policy | Routes each subject to one controlling channel |
| Authority rules | Who may issue direction to subcontractors, suppliers, designers, field staff | Executed agreement, project directory | Prevents unauthorized direction and scope change |
| Owner-decision log | Decision requested, options, cost and time effect, due date, decision maker, response, distribution | Change log, RFI log, procurement log | Documents owner decisions rather than leaving them verbal |
| Schedule-notice procedure | Baseline issue, updates, lookaheads, delays, recovery, milestone changes | Project 05 schedule, Project 06 lookahead | Distinguishes forecast information from approved time extension or formal notice |
| Trade and supplier templates | Mobilization, readiness, delivery, inspection, delay, correction, protection, demobilization, release, shipping, damage, shortage, replacement, return | Project 07 procurement plan, Project 08 handoff plan | Standardizes recurring notifications |
| Confirmation process | Field-conversation confirmation; distinguishing observation, recommendation, request, instruction, decision, approval | Company policy | Prevents an unconfirmed verbal direction from controlling the project |
| Confidentiality rules | Restricted payroll, medical, personnel, pricing, claims, security, access-code, financial records | Company confidentiality policy | Protects sensitive information from improper distribution |
| Communication register | Date, sender, recipient, subject, type, required action, due date, file location | Project 02 job file | Preserves a retrievable master log of project communications |
| Audit record | Sample audit of owner, trade, supplier, and formal communications for completeness | Communication register | Verifies the plan is being followed rather than assumed |
| Check | Standard |
|---|---|
| Channels | Every listed subject has one stated controlling channel and a defined escalation path |
| Authority | Direction authority is named for subcontractors, suppliers, designers, and field staff; unauthorized owner-to-trade direction is prevented |
| Owner decisions | Every decision request is logged with options, cost and time effect, due date, decision maker, response, and distribution |
| Schedule notices | Forecast information is distinguished from approved time extension or contractual notice in every schedule communication |
| Confirmation | Important verbal or telephone direction is confirmed in writing before it is treated as controlling |
| Confidentiality | Payroll, medical, personnel, security, and financial records are restricted according to the confidentiality rule |
| Register and audit | The communication register is current and a sample audit finds no channel misuse, missing confirmation, or distribution gap left uncorrected |
Inspect every communication plan using the same checks regardless of project size or complexity.
Complete the Communication Plan Inspection Checklist in the Inspection Checklist section below before beginning Project 18.
Probable cause: the authority rule from Step 6 was not communicated to the trade, or the owner's request was treated as equivalent to written authorization.
Confirmation: check whether a written change record exists for the work and whether it was routed through the person identified in Step 6.
Correction: stop work pending written authorization where safely possible, document the request, and route it through the change-control process from Project 11.
Reinspection: confirm the authority rule has been reissued to the trade and acknowledged.
Probable cause: the delay was communicated through an informal channel instead of the schedule-notice procedure from Step 10, or the message was not distinguished as a forecast versus a formal notice.
Confirmation: check the communication register for a schedule-notice entry matching the date and subject, and confirm which channel it was sent through.
Correction: reissue the notice through the controlling channel identified in Step 4, and confirm receipt from the required recipient.
Reinspection: repeat the schedule-notice check against the procedure for the remainder of the project.
Probable cause: the controlling-channel rule from Step 4 was not defined for that subject, or it was defined but not followed.
Confirmation: check the channel definitions for the subject and confirm which channel is stated as controlling.
Correction: issue one controlling clarification through the correct channel, and notify all parties who received the conflicting instructions.
Reinspection: repeat the channel check for the disputed subject and confirm no further conflicting messages were sent.
Probable cause: the confidentiality rule from Step 18 was not applied to the specific document or message, or the distribution list from Step 17 included a recipient without access rights.
Confirmation: check the distributed communication against the confidentiality categories and the distribution list used.
Correction: restrict further distribution, notify management according to company policy, and correct the distribution list.
Reinspection: repeat the confidentiality check on a new sample of communications involving the same subject.
Probable cause: the field-conversation confirmation process from Step 15 was not applied to the conversation.
Confirmation: check whether a written confirmation was sent following the conversation and whether it was acknowledged.
Correction: document the conversation as accurately as possible from available records, and require written confirmation for all future direction from that party.
Reinspection: confirm the confirmation process is being applied consistently going forward.
Probable cause: the communication was not entered in the register at Step 24, or it was filed without the required file-location reference.
Confirmation: check the communication register for the entry and confirm whether the file-location field is complete.
Correction: locate the original communication, enter it in the register with a complete file location, and correct the filing procedure with the person responsible.
Reinspection: repeat the register-completeness check on a new sample of recent communications.
Probable cause: the escalation path from Step 5 was not applied, or overdue responses were not being monitored as required in Step 31.
Confirmation: check the communication register for the original request date and confirm whether the response-time expectation was exceeded without escalation.
Correction: escalate the item immediately according to the defined path and document the escalation.
Reinspection: confirm overdue-response monitoring is being performed at the required frequency going forward.
This project ends with the issued communication plan operating and filed, not left as an unused document.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| PM-097 | Defines a controlling communication channel, response-time expectation, and escalation path for every required subject | |||
| PM-098 | Logs owner decisions with options, cost and time effect, due date, decision maker, response, and distribution | |||
| PM-099 | Communicates schedule changes through the defined schedule-notice procedure and distinguishes forecast from formal notice | |||
| PM-100 | Coordinates supplier updates using the defined notification templates for release, shipping, delivery, damage, shortage, replacement, and return | |||
| PM-101 | Manages trade notifications using the defined templates and confirms important verbal direction in writing | |||
| PM-102 | Preserves communication records in a current register and produces a completed sample audit with corrected findings |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Standard | Meets Standard (Y/N) | Correction (if any) |
|---|---|---|---|
| Channels | One controlling channel and escalation path defined per subject | ||
| Authority | Direction authority named for trades, suppliers, designers, and field staff | ||
| Owner decisions | Options, cost and time effect, due date, decision maker, response, and distribution logged | ||
| Schedule notices | Forecast information distinguished from approved time extension or formal notice | ||
| Trade and supplier templates | Complete template set issued for recurring subjects | ||
| Verbal confirmation | Important verbal direction confirmed in writing | ||
| Confidentiality | Payroll, medical, personnel, security, and financial records restricted | ||
| Register | Current with date, sender, recipient, subject, type, required action, due date, file location | ||
| Audit | Sample audit completed with corrections closed | ||
| Archive | Plan, register, decisions, and notices archived and accessible |
Owner-decision log status: ____________ Open items carried forward: ____________
Communication plan declared issued: ______ (Pass/Fail) Date: ____________ Project manager name: ____________
With the communication plan issued and operating, review it against the Acceptance Standards table and confirm every subject has one stated controlling channel and escalation path, direction authority is named for trades, suppliers, designers, and field staff, every owner-decision log entry is complete, schedule notices distinguish forecast from formal notice, trade and supplier templates are complete and in use, important verbal direction is confirmed in writing, confidential information is restricted according to the confidentiality rule, and the communication register is current with a completed sample audit. Complete the Communication Plan Inspection Checklist and correct any failed item before beginning Project 18. If an item fails, identify whether the error occurred in channel definition, authority assignment, decision logging, schedule notice, template use, verbal confirmation, confidentiality restriction, or register maintenance before revising.
You have completed the seventeenth project in the construction project management sequence: controlling project communication with owners, trades, and suppliers. This project required you to create communication channels (PM-097), document owner decisions (PM-098), communicate schedule changes (PM-099), coordinate supplier updates (PM-100), manage trade notifications (PM-101), and preserve communication records (PM-102).
You now have an issued communication plan, an owner-decision log, trade and supplier notification templates, a communication register, and a completed audit record. That controlled communication system carries directly into the next project: assembling the closeout package that depends on the warranties, approvals, and records this plan has been routing and preserving throughout the project.
File your issued communication plan, owner-decision log, and communication register where Project 18 can incorporate them into the closeout package. Every remaining record in this book relies on the channel discipline and preserved communications built here.