Draw Schedule

Real Estate Investing Glossary – Malone Global University

Definition

A draw schedule is the planned timing and line-item structure for when construction funds (typically from a construction loan) are released to pay for completed work. Draw schedules tie disbursements to verified progress—often based on a cost breakdown, inspections, lien waivers, and lender conditions—so the lender and owner can control budget and construction risk.

How Draw Schedules Work

  1. Budget is broken into categories (often called a Schedule of Values or cost code budget).
  2. Contractor submits a draw request showing percent complete by line item.
  3. Third-party inspector (or lender construction consultant) verifies progress on site.
  4. Lender funds the draw (net of retainage and any holdbacks) once conditions are satisfied.
  5. Borrower pays contractors/subs and provides lien waivers for the next draw.

Common Draw Schedule Formats

1) Cost-to-Complete (Progress-Based) Draws

Most common: funding is based on verified % completion of each budget line item.

2) Milestone-Based Draws

Funding is released when specific milestones are achieved (e.g., foundation complete, dry-in, TCO/CO, substantial completion). Milestone draws are common in certain build-to-suit or smaller projects but still often require inspection support.

3) Time-Phased Draw Forecast

A monthly cash flow curve (spend forecast) that complements the line-item draw process. This helps model interest carry and working capital needs even though draws still depend on actual progress.

What Lenders Typically Require

Key Concepts Inside a Draw Schedule

Retainage (Holdback)

Retainage is the portion of each draw held back (often 5–10%) to encourage completion and protect against defective work or lien issues. Retainage is typically released at substantial completion or final completion, subject to punch-list closeout.

Contingency

Most budgets include owner contingency and/or contractor contingency. Lenders often control when contingency can be used and may require approvals for draws against it.

Hard Costs vs. Soft Costs

Stored Materials

Some lenders allow draws for stored materials (e.g., long-lead equipment) if properly documented, insured, and stored securely. Requirements may include bills of sale, paid invoices, and a warehouse agreement.

Why Draw Schedules Matter

Example (Simplified)

A project has a $20M hard-cost budget. The GC requests a draw showing the project is 15% complete. The lender verifies work and applies 10% retainage.

Common Pitfalls

Related Terms