Project 16
Receive, place, consolidate, strike off, and bring a residential slab to the correct elevation and initial surface condition so the finishing work in the next project can begin immediately, during the same continuous placement operation.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework, a cold joint, or a failed inspection.
Task-specific safety guidance for ordinary work hazards.
Serious injury, structural risk, or major damage is possible.
Practical work-area safety: pump lines, moving equipment, and placement traffic.
Local requirements vary. Verify permit, inspection, and testing requirements.
Follow the concrete supplier's mixture data and equipment manufacturer instructions.
Elevation, thickness, slope, and screed-reference guidance.
This project qualifies you to receive, place, consolidate, and screed a residential concrete slab to the correct elevation and surface condition. The finished work product of this project alone is a continuously placed, consolidated, and screeded wet slab, at the required thickness and elevation, turned over to the finishing operation at the correct concrete condition. This project does not end with a finished, jointed, or cured slab surface; that work belongs to the next project, which begins the moment this project's screeded slab reaches the correct condition.
You will stage every tool, worker, and material needed for both placement and finishing before concrete discharge begins, receive and verify the delivered concrete, place and consolidate it without displacing reinforcement, embeds, or the vapor barrier beneath it, strike the surface off to the required elevation and profile, and turn the completed placement area over to the finishing crew without allowing the slab to miss its finishing window.
This project depends entirely on the slab forms, control lines, compacted base, vapor barrier, and reinforcement completed and inspected in the two projects before it. No placement may begin until those inspections are complete and the finishing resources required by the next project are staged and ready.
The slab forms and control lines from Project 14 and the compacted base, vapor barrier, and reinforcement from Project 15 exist to be placed against and around by this project. Every elevation, slope, and thickness verified in this project is measured against the same benchmark, screed reference, and control line established in those two projects.
This project and the next one are a single continuous slab placement divided into two competency groups for instruction and assessment. Finishing must begin at the correct concrete condition during the same operation described here; it may not be postponed merely because it is described in a separate project. The crew that begins this project must be staffed, staged, and equipped to carry the work straight through floating, edging, jointing, and initial curing without a gap.
This project covers:
This project does not authorize the learner to:
Any form movement, equipment failure, segregation, delayed delivery, surface crusting, displaced embed, or elevation loss identified during placement must be stopped and corrected before placement continues.
Establish these references before concrete discharge begins, and do not change them mid-placement.
| Term | Definition |
|---|---|
| Screed reference | The screed rail, wet-screed pin, laser-controlled elevation, or other approved interior control established in Project 14 that governs the finished slab elevation |
| Placement route | The approved path by which concrete travels from the delivery vehicle or pump to its final location in the slab |
| Workable front | The leading edge of freshly placed, unconsolidated concrete that the placing crew keeps continuously moving forward during placement |
| Turnover | The point at which a completed placement area reaches the correct surface condition and is handed to the finishing crew for floating, edging, jointing, and finishing |
| Construction joint | A planned stopping location in the slab placement, established in advance, used only if placement is interrupted |
Before concrete discharge begins, record the selected references and plan directly on the Slab-Placement Record:
Site name/address: ______ Screed reference: ______ Placement route: ______ Planned construction-joint location (if interrupted): ______
Date: ____________ Placing crew lead: ____________ Finishing crew lead: ____________
Every concrete placement in this book, from footings to stem walls to this slab, follows the same discipline: confirm the mixture at delivery, keep a continuous workable front, consolidate around every embedded item without displacing it, and monitor forms, reinforcement, and elevation throughout placement rather than only at the end. Applying that discipline here, at the largest single placement in the book, is what keeps the slab within its required thickness and elevation across its full area.
This project's placement and screeding steps and the next project's floating, edging, jointing, and finishing steps are one continuous operation performed on the same wet concrete. Do not treat the end of this project's numbered sequence as a stopping point. The crew, tools, and curing materials required for finishing must already be staged before discharge begins, and the finishing crew must take over each completed area at the correct surface condition without delay.
Strike off every area of the slab from the screed rail, wet-screed pin, laser reference, or other control established in Project 14. Do not estimate slab thickness by eye or adjust the screed reference mid-placement to compensate for an unrelated elevation problem; identify and correct the actual cause instead.
Treat a pressurized concrete pump line as capable of sudden, forceful discharge or blockage release. Keep all workers clear of the discharge end during line priming, blockage clearing, and cleanout. Stop the pump and follow the manufacturer's blockage-clearing procedure before any worker approaches the line to clear an obstruction.
Confirm a clear, designated path for ready-mix trucks, pump trucks, and buggies before placement begins. Keep workers not directly involved in placement out of the delivery and buggy travel path, and wear the required high-visibility vest whenever this equipment is operating.
Required field sampling, slump testing, air-content testing, and cylinder-making frequency vary by jurisdiction, project specification, and concrete supplier agreement. Verify the required testing frequency and personnel qualifications with the approved testing agency before delivery, and do not substitute an informal check for a required documented test.
FN-091 – FN-096
Slab Placement and Screeding Qualification
Deliverable: a slab area placed to the approved mixture, volume, and joint plan; consolidated at every edge, corner, thickened area, embed, blockout, and penetration; struck off at the screed reference to the required elevation, thickness, and profile; and turned over to the finishing crew at the correct surface condition, with a completed Slab-Placement Record.
| Item | Reference Used | Standard | Purpose |
|---|---|---|---|
| Delivered mixture | Approved concrete specification and supplier documentation | Match the specified mixture before discharge; resolve any mismatch before accepting the load | Confirm the correct concrete is placed |
| Placement rate and route | Approved placement plan | Maintain a continuous workable front along the planned route | Prevent cold joints and segregation |
| Consolidation | Reinforcement plan and embed schedule | Full consolidation at edges, corners, thickened areas, embeds, and penetrations without displacement | Eliminate voids and honeycombing |
| Slab elevation and thickness | Screed reference from Project 14 | Match the approved slab plan within the plan's stated tolerance | Confirm correct slab thickness and finished-floor elevation |
| Surface condition at turnover | Approved finish specification | Correct condition for immediate floating per the next project | Preserve the finishing window |
| Check | Standard |
|---|---|
| Delivered mixture | Matches the approved specification on the delivery ticket; any mismatch is resolved before discharge begins |
| Field testing | Required sampling and testing conducted by approved personnel before or during placement |
| Placement continuity | A continuous workable front is maintained; any unplanned stoppage is treated per the interruption procedure in Step 20 |
| Reinforcement and embed position | No reinforcement, dowel, sleeve, or embedded item is displaced beyond the tolerance stated in the approved plan |
| Vapor barrier | No vapor-barrier damage caused by placement equipment or excessive free fall |
| Slab elevation and thickness | Struck-off surface matches the screed reference and approved slab plan within stated tolerance |
| Turnover condition | Each completed area is handed to the finishing crew at the surface condition required by the approved finish specification |
Inspect every placement area using the same checks regardless of location within the slab.
Complete the Slab-Placement Record in the Inspection Checklist section below as each area is turned over to finishing.
Probable cause: a supplier batching or dispatch error, or a load intended for a different project delivered to this site.
Confirmation: compare the delivery ticket to the approved mixture specification before any discharge occurs.
Correction: reject the load and do not place any portion of it; contact the supplier for a corrected delivery.
Reinspection: verify the replacement delivery ticket against the approved specification before discharge begins.
Probable cause: concrete was deposited with excessive free fall directly onto reinforcement, or a worker or equipment contacted an embedded item during placement.
Confirmation: compare the current position of the item to its approved location and elevation using the reinforcement or embed schedule.
Correction: reposition the item while the concrete remains workable, using the approved support method; do not bury a displaced item without correction.
Reinspection: repeat the reinforcement and embed check for the affected area before continuing placement past it.
Probable cause: an inaccurate screed reference, a miscalculated placement volume, or inconsistent screed technique.
Confirmation: re-check the screed rail, pin, or laser reference elevation and re-measure the affected area with the grade rod.
Correction: fill low areas with fresh concrete from the same placement and rescreed; remove excess material from high areas before it sets.
Reinspection: repeat the elevation and thickness check for the corrected area.
Probable cause: a delivery delay, equipment failure, or crew shortage interrupted the continuous workable front.
Confirmation: assess the elapsed time and surface condition of the stalled edge against the concrete's working time.
Correction: if the surface remains workable, resume placement and consolidate thoroughly at the rejoined edge; if the surface has begun to set, stop at the nearest planned construction-joint location and install the approved joint detail.
Reinspection: inspect the rejoined or jointed edge for consolidation and bond before continuing.
Probable cause: equipment contact, a dropped tool, or excessive free fall from height damaged the vapor barrier before or during concrete deposit.
Confirmation: inspect the affected area for a visible tear, puncture, or displaced seam before concrete covers it.
Correction: stop placement at the affected location and repair the vapor barrier using the approved patch method before continuing.
Reinspection: repeat the vapor-barrier check for the repaired area before placement resumes over it.
Probable cause: finishing tools, curing materials, or the finishing crew were not staged before discharge began.
Confirmation: compare the actual readiness of finishing resources to the staging requirements confirmed in Step 4.
Correction: stop and complete staging immediately; do not allow the surface to sit past its finishing window while resources are gathered.
Reinspection: confirm the finishing crew has taken over the completed area at the correct surface condition before recording turnover.
This project does not end with tool cleanup and demobilization; it ends with turnover to the finishing crew described in the next project. Complete only the cleanup tasks that do not interfere with immediate finishing.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| FN-091 | Plans the slab-pour sequence, including delivery interval, placement route, screed method, and crew assignments, before concrete discharge begins | |||
| FN-092 | Places concrete close to its final position without damaging the vapor barrier or displacing reinforcement or embedded items | |||
| FN-093 | Screeds the surface to the required elevation and profile using the established screed reference | |||
| FN-094 | Maintains slab elevation, thickness, and slope throughout placement, checking while correction remains possible | |||
| FN-095 | Consolidates edges, corners, thickened areas, and embedded items without displacing them | |||
| FN-096 | Continuously inspects the wet-slab placement and corrects deficiencies, including delayed delivery and interrupted placement, before continuing |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Plan Value | Field Value | Time | Pass (Y/N) | Correction (if any) |
|---|---|---|---|---|---|
| Delivery — mixture verification | |||||
| Slump test | |||||
| Air-content test | |||||
| Cylinder samples taken | |||||
| Placement start time | |||||
| Interruptions (location/reason) | |||||
| Elevation check — Area 1 | |||||
| Elevation check — Area 2 | |||||
| Reinforcement/embed check | |||||
| Vapor-barrier check | |||||
| Turnover to finishing crew (time) | |||||
| Weather conditions |
Total volume placed: ____________ Deficiencies corrected during placement: ____________
Placement declared complete and turned over: ______ (Pass/Fail) Date: ____________ Placing crew lead: ____________ Received by (finishing crew lead): ____________
With the slab placed, consolidated, and screeded, review the Slab-Placement Record against the Acceptance Standards table and confirm the delivered mixture matched the approved specification, required field testing was completed by approved personnel, a continuous workable front was maintained or any interruption followed the approved construction-joint plan, no reinforcement or embedded item was displaced beyond tolerance, the vapor barrier was not damaged, the struck-off surface matches the screed reference and approved slab plan within tolerance, and each completed area was turned over to the finishing crew at the correct surface condition. If an item fails, identify whether the error occurred in delivery verification, placement technique, consolidation, elevation control, or turnover timing before recording the correction and continuing directly into the next project's finishing work.
You have completed the placement and screeding half of the continuous slab operation: planning the slab-pour sequence (FN-091), placing concrete without displacing reinforcement or embedded items (FN-092), screeding the surface to the required elevation and profile (FN-093), maintaining slab elevation, thickness, and slope (FN-094), consolidating edges, corners, thickened areas, and embeds (FN-095), and continuously inspecting and correcting the wet-slab placement (FN-096).
You now have a continuously placed, consolidated, and screeded wet slab at the required elevation, turned over to the finishing crew at the correct surface condition. That turnover carries directly into the next project: floating, edging, jointing, texturing, curing, and inspecting the same slab while it remains workable.
Do not allow this slab to sit unattended after screeding. The next project's finishing operations must begin immediately, on the same concrete, before it loses the workability this project was built to preserve.