Install Floor Girders and Beams

Prepare, cut, and set the approved floor girders or beams on their specified bearing points, posts, pockets, or connectors, and verify that the completed beam system carries a continuous, inspected load path from the foundation upward.

Field Cue System

These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework, disputes, or hazards.

△

Safety Cue

Task-specific safety guidance for ordinary work hazards.

✋

Critical Safety Cue

Serious injury or major structural consequence is possible.

⛑

Field Safety Cue

Practical work-area safety: footing, debris, standing water, and access.

▤

Code Alert

Local requirements vary. Verify permit, inspection, and jurisdictional rules.

▧

Manufacturer Cue

Follow product-specific instructions for engineered beams and connectors.

▱

Measurement Cue

Clearance, layout, spacing, and reference-point guidance.

Job Overview

This project qualifies you to prepare and install the approved floor girders or beams that carry the floor-joist system down through posts, pockets, or piers to the foundation. The finished work product is a set of beams identified, cut, seated, connected, and verified against the approved beam schedule, with a completed beam-installation record.

You will review the beam plan and connector schedule, confirm that bearing surfaces have passed inspection, inspect and reject unsuitable beam stock, cut solid-sawn members only where the plan permits field cutting, lift and seat each beam section on its specified bearing points, install the specified post caps, straps, and connectors, and verify elevation, level, line, splice position, and load path before the beam system is loaded.

This project follows the reference lines and readiness record established in Project 01 and sits immediately before the floor joists in Project 03. Every joist placed in Project 03 bears directly on the beams installed here, so an error in beam elevation, bearing, or connection carries forward into the entire floor system.

Skills You Will Demonstrate

  • FR-007 — Identify beam locations, orientation, and bearing points from the approved beam plan and schedule.
  • FR-008 — Cut beam members to the approved length and end condition using the method permitted for the specified material.
  • FR-009 — Set beams on their specified bearing points, posts, pockets, or piers using the approved lifting and temporary-restraint method.
  • FR-010 — Support and verify bearing points, including post caps, bearing plates, and shims specified by the design.
  • FR-011 — Fasten beam connections using the approved connector and fastener schedule.
  • FR-012 — Inspect beam alignment, elevation, level, line, splice position, and connector seating and correct authorized deficiencies.

Where This Skill Fits

The beam system installed in this project is the load path every floor joist in Project 03 depends on, and it is the first structural member-sizing decision in this book that must come directly from the approved beam schedule rather than field judgment. The bearing, splice, and connector discipline taught here — full seating at every support, splices only over approved bearing, and listed fasteners for listed connectors — repeats at every later beam, header, and ridge installation in this book.

The temporary-restraint and controlled-lift procedures introduced here are the same procedures expanded in Chapter 11 for wall raising and in Chapter 15 for truss setting.

Scope and Intended Use

This project covers:

  • reviewing the approved beam plan, beam schedule, bearing details, post locations, connector schedule, and elevations
  • inspecting, rejecting, or quarantining beam material that does not meet the approved specification
  • marking, cutting, and preparing solid-sawn beam members only where the approved plan permits field cutting
  • lifting, placing, and seating beams on their specified bearing points using the approved worker count, rigging, and access controls
  • installing post caps, straps, bolts, structural screws, hangers, and other connectors according to the approved schedule
  • verifying bearing, elevation, alignment, splice position, and connector seating and documenting the completed installation

This project does not authorize the learner to:

  • select beam size, species, grade, ply count, or span rating without the approved beam schedule, prescriptive table, or a qualified designer's direction
  • field-cut, drill, notch, or otherwise alter an engineered beam member except as explicitly permitted by the manufacturer
  • splice a beam at any location other than a specified support
  • substitute a generic fastener for a connector's listed fastener, or release lifting equipment or temporary restraint before the beam is fully seated and secured

Any beam material that arrives damaged, delaminated, incorrectly identified, or excessively warped must be quarantined and referred, not installed with a field-improvised correction.

Reference Conventions

Establish these references before any beam is marked, cut, or lifted.

TermDefinition
Bearing pointA foundation ledge, pocket, pier, post cap, or other support surface where a beam section is required to seat, as identified on the approved beam plan
Reference endThe beam end identified on the approved plan or schedule from which cut-line measurements are taken
Full bearingContact between the beam and its support surface across the minimum bearing length stated on the approved plan or connector documentation, with no gap
SpliceA joint between two beam sections, permitted only directly over a bearing point identified on the approved plan and only in the orientation specified there
Temporary restraintBracing, shoring, or strapping installed immediately after a beam is seated and before lifting equipment is released, to prevent displacement or rotation
Load pathThe continuous connection from beam to post, pier, or foundation that transfers floor loads downward without an unsupported gap

Beam Installation Record — Header Entries

Before cutting any beam material, record the controlling documents and beam schedule reference directly on the beam-installation record:

Beam plan set and revision date: ______     Beam schedule reference: ______     Connector schedule reference: ______

Date started: ____________     Builder name: ____________

Prerequisites

Common Field Fundamentals

Every beam installed in this project is placed, seated, and connected using the same sequence: verify bearing readiness, inspect and stage material, measure before cutting, lift and seat under controlled restraint, connect to the approved schedule, and verify the completed load path. Applying that sequence consistently, section by section, is what keeps a multi-section beam run level and in line.

Material verificationGrade, treatment, moisture, and delivery documentation confirmed before staging
Bearing preparationPockets, post caps, hangers, plates, and shims installed per the design
Controlled liftApproved worker count, rigging, and immediate temporary restraint
Connection and verificationConnectors installed to schedule; bearing, level, and line checked

Bearing, Splices, and the Load Path

A beam section that is level and correctly cut but seated with less than the specified minimum bearing length at one end does not meet this project's acceptance standard, even though it may appear stable. Splices are permitted only directly over an approved bearing point; a splice located between supports is a different structural condition than the approved design and must not be created in the field to use shorter stock or avoid a difficult lift.

FR-007 – FR-012

Structural Installation Qualification

Floor Girder and Beam Installation

Difficulty: Intermediate

Estimated Time: 4–7 hours

Estimated Cost: Per approved beam and connector schedule

Finished Work: Installed floor girders or beams, seated, connected, and verified against the approved schedule

A. Finished-Project Specification

Scope: one completed installation of every floor girder or beam section shown on the approved beam plan for the current structure, including all specified bearing supports, splices, and connectors, with a completed beam-installation record.

B. Required Documentation Schedule

DocumentSourceConfirmation Required
Beam plan and scheduleDesign professional / plan setCurrent revision on site; beam size, species/grade or product designation, and span match the schedule
Bearing and connector scheduleDesign professional / manufacturerPost caps, hangers, straps, bolts, and structural screws match the specified type, size, and quantity
Bearing inspection approvalsAuthority having jurisdictionFoundation, sill-plate, post, pier, and pocket inspections required for beam bearing are confirmed complete
Manufacturer instructions for engineered membersManufacturerField-cutting, hole, notch, and end-sealing restrictions confirmed before handling
Lift planProject supervisorWorker count, rigging method, and access controls confirmed for each beam section

C. Component Schedule

ComponentQuantityMaterialFinished SizePreparation
Beam sectionsPer approved beam schedulePer approved beam schedule (solid-sawn, engineered, or as specified)Bearing-to-bearing length per field measurement, Step 7Cut only where the plan permits field cutting; seal cut ends per manufacturer instructions where required
Post caps / bearing platesPer approved connector schedulePer approved connector scheduleAs suppliedInstalled at each post or pier bearing point per Step 11
Hangers, straps, bolts, structural screwsPer approved connector schedulePer approved connector scheduleAs suppliedInstalled per the fastening pattern in Step 18
ShimsAs required by field bearing conditionsPer approved detail or manufacturer instructionsAs required to achieve full, level bearingInstalled only at bearing points identified in Step 11

D. Acceptance Standards

CheckStandard
Bearing lengthFull contact across the minimum bearing length stated on the approved plan or connector documentation at every support, with no gap
ElevationBeam top matches the plan elevation within the tolerance stated on the approved plan; if none is stated, obtain the tolerance from the design professional
LevelBeam is level along its length and across all bearing points as measured with a 4-foot level or longer straightedge
Splice locationEvery splice occurs directly over an approved bearing point and in the orientation specified on the plan
Connector installationEvery post cap, hanger, strap, bolt, and structural screw matches the approved connector schedule for type, size, quantity, and installation direction, with listed fasteners only
Documentation completenessBeam identification, dimensions, elevations, connections, field cuts, and inspection results are recorded on the beam-installation record

E. Document Review and Material Verification (Steps 1–5)

  1. Review the approved beam plan, beam schedule, bearing details, post locations, connector schedule, elevations, and temporary-support requirements. Confirm the revision date against the project's document-control log before using it.
  2. Verify that the foundation, sill plates, pockets, piers, posts, and bearing surfaces have passed the required inspection. Confirm the inspection date, inspector, and approval reference for each bearing point against Project 01's framing-readiness record.
  3. Confirm beam material, grade, treatment, engineered-product designation, moisture condition, and delivery documentation. Compare delivered material against the approved beam schedule before staging.
  4. Reject or quarantine damaged, split, delaminated, excessively warped, contaminated, or incorrectly identified members. Tag and separate rejected material and record the condition and quantity on the beam-installation record.
  5. Establish a controlled staging and lifting area that keeps beams dry, supported, and clear of traffic. Confirm the staging area matches the access and worker-count requirements of the lift plan.

F. Marking and Cutting (Steps 6–10)

  1. Mark each beam by plan location and required orientation. Label the reference end identified on the approved schedule before measuring.
  2. Measure bearing-to-bearing dimensions and compare them with the plan before cutting. Log any difference between the field measurement and the plan dimension before proceeding.
  3. Mark cut lines from a defined reference end and face. Use the framing square to strike the cut line square to the reference face.
  4. Cut only solid-sawn members when the approved plan permits field cutting; use manufacturer-controlled procedures for engineered members. Confirm the plan's field-cutting permission before cutting any member.
  5. Seal treated or engineered-member cut ends when required by the product instructions. Apply the specified sealant to the full cut-end surface.

G. Bearing Preparation and Lift (Steps 11–15)

  1. Prepare beam pockets, post caps, hangers, bearing plates, shims, or other supports specified by the design. Install each bearing component at its plan-specified location before the beam is lifted.
  2. Confirm that temporary supports and lifting equipment are stable and rated for the operation. Verify the rated capacity against the beam section's weight before lifting.
  3. Lift and place the first beam using the approved worker count, rigging method, and access controls. Follow the lift plan's assigned worker positions.
  4. Seat the beam fully on each bearing point without damaging anchors, connectors, masonry, or treated surfaces. Confirm full contact at every bearing point before releasing the lift.
  5. Install temporary restraint before releasing lifting equipment. Confirm the restraint is secured at both ends before any worker releases the rigging.

H. Remaining Sections and Connections (Steps 16–20)

  1. Set remaining beam sections in the approved sequence. Follow the sequence shown on the beam plan; do not reorder sections without a documented reason.
  2. Complete approved splices only over specified supports and in the required orientation. Verify the splice location against the bearing point identified on the plan before fastening.
  3. Install post caps, straps, bolts, structural screws, hangers, or other connectors according to the approved schedule. Use only the listed fastener for each listed connector.
  4. Verify minimum bearing, member elevation, straightness, level, line, splice position, and connector seating. Check each item against the Acceptance Standards table in Section D.
  5. Check beam-to-sill, beam-to-post, and beam-to-foundation load paths. Confirm no bearing point has an unsupported gap between the beam and the structure below.

I. Correction and Documentation (Steps 21–23)

  1. Correct authorized alignment or seating deficiencies without reducing bearing or altering the member. Use shims or approved bearing adjustments; do not trim a beam to correct a bearing discrepancy without design direction.
  2. Record beam identification, dimensions, elevations, connections, field cuts, and inspection results. Complete every entry on the beam-installation record before proceeding to Project 03.
  3. Protect the installed beam system from displacement and unapproved loading until floor joists are installed. Mark the beam system as not-for-loading until the Project 03 floor-joist inspection confirms it is ready.

Common Verification Inspection

Inspect the completed beam system using the same checks regardless of which section it covers.

Complete the Beam-Installation Record in the Inspection Checklist section below before beginning Project 03.

Image Placeholder
Recommended image: a beam section marked with its plan location and orientation before lifting.
Image Placeholder
Recommended image: a beam being lifted and placed by the approved worker count with rigging in use.
Image Placeholder
Recommended image: a beam seated fully on a post cap with temporary restraint installed before the lift is released.
Image Placeholder
Recommended image: a level being checked along a beam's length and across a bearing point.
Image Placeholder
Recommended image: a completed splice located directly over a bearing point with the approved connector installed.
Image Placeholder
Recommended image: a completed beam-installation record with dimensions, elevations, and inspection results entered.

Failure Points and Troubleshooting

Cleanup

This project ends with an installed, connected, and documented beam system, protected from loading until the floor joists in Project 03 are ready.

Field Terms

Bearing Point
A support surface where a beam section is required to seat, as identified on the approved beam plan.
Full Bearing
Contact between the beam and its support across the minimum bearing length with no gap.
Reference End
The beam end from which cut-line measurements are taken, as identified on the plan or schedule.
Splice
A joint between two beam sections, permitted only directly over an approved bearing point.
Temporary Restraint
Bracing or strapping installed immediately after a beam is seated and before lifting equipment is released.
Load Path
The continuous connection from beam to post, pier, or foundation that transfers floor loads downward.
Post Cap
A connector installed at the top of a post to seat and secure a beam bearing on that post.
Beam Schedule
The approved document specifying beam size, material, span, and bearing requirements for each beam location.
Connector Schedule
The approved document specifying connector type, fastener, and installation pattern for each beam connection.
Beam-Installation Record
The signed document confirming beam identification, dimensions, elevations, connections, and inspection results.

Skill Check

  1. Why must bearing-to-bearing dimensions be measured in the field before a beam is cut, even when a plan dimension already exists?
  2. What is the minimum requirement for a bearing point to be considered "fully seated," and why can a beam be level but still fail this standard?
  3. Where is a beam splice permitted, and why must it not be located between supports?
  4. What must the learner do before cutting, drilling, or notching an engineered beam member?
  5. What must happen before lifting equipment or workers release a newly seated beam?
  6. What is the difference between a connector schedule discrepancy corrected in the field and one requiring design direction?
  7. What conditions require the learner to quarantine beam material rather than install it?
  8. Why is the beam-to-sill, beam-to-post, and beam-to-foundation load path checked as a separate item from bearing length alone?
  9. What must be true of the beam-installation record before floor joists are installed in Project 03?
  10. Why must the installed beam system be protected from loading even after connectors are complete?

Competency Rubric

CompetencyIndependent Pass StandardNot DemonstratedWith AssistanceIndependently
FR-007Correctly identifies beam locations, orientation, and bearing points from the approved beam plan and schedule
FR-008Cuts beam members to the approved length and end condition using the method permitted for the specified material
FR-009Sets beams on their specified bearing points using the approved lifting and temporary-restraint method without damage or displacement
FR-010Supports and verifies bearing points, including post caps, bearing plates, and shims, matching the approved design
FR-011Fastens beam connections completely and correctly using the approved connector and fastener schedule
FR-012Inspects beam alignment, elevation, level, line, splice position, and connector seating and correctly resolves or refers every deficiency

Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.

Inspection Checklist — Beam-Installation Record

CheckPlan Value / RequirementField ValueWithin Tolerance (Y/N)Correction (if any)
Bearing inspection confirmationComplete before beam loading
Beam material verificationMatches approved beam schedule
Beam length (each section)
Bearing length (each support)Minimum per plan/connector documentation
Elevation (each bearing point)
Level (full length)
Splice location(s)Over approved bearing only
Connector installationMatches connector schedule
Load path continuityNo unsupported gap

Open discrepancies attached: ____________     Responsible authority for each: ____________

Beam installation approved for loading: ______ (Pass/Fail)     Date: ____________     Builder name: ____________

Performance Check

With document review, material verification, cutting, bearing preparation, lifting, connection, and correction complete, review the finished beam system against the Acceptance Standards table and confirm bearing length, elevation, level, splice position, and connector installation all match the approved schedule, and that the beam-to-sill, beam-to-post, and beam-to-foundation load path is continuous with no unsupported gap. Complete and sign the beam-installation record before floor joists are installed in Project 03. If a discrepancy remains open, identify the responsible authority and required decision before proceeding.

Project Closeout

You have completed the second project in the residential framing sequence: installing floor girders and beams. This project required you to identify beam locations and bearing points from the approved plan (FR-007), cut beam members to the approved length and end condition (FR-008), set beams on their specified bearing points using controlled lifting and temporary restraint (FR-009), support and verify bearing points including post caps and shims (FR-010), fasten beam connections to the approved schedule (FR-011), and inspect beam alignment, elevation, level, splice position, and connector seating (FR-012).

You now have an installed, connected, and documented beam system carrying a verified load path from the foundation upward. That beam system is the bearing surface for every floor joist installed in the next project.

Protect the installed beam system and its temporary restraint. Do not apply floor-joist or other loading until Project 03 confirms the system is ready.