Project 10
Select, assemble, and install the plan-specified structural headers over designated load-bearing openings, including the jack studs, bearing supports, and connectors required to carry the header load down to the structure below.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework, disputes, or hazards.
Task-specific safety guidance for ordinary work hazards.
Serious injury or major structural consequence is possible.
Practical work-area safety: footing, debris, standing water, and access.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for engineered members and connectors.
Clearance, layout, spacing, and reference-point guidance.
This project qualifies you to prepare and install a plan-specified structural header over a selected load-bearing opening, along with the jack studs, bearing supports, and connectors that transfer the header's load down through the wall to the foundation, beam, or approved structure below. The finished work product is one or more installed headers, seated on verified bearing, fastened to the approved schedule, with a completed load-path inspection and installation record.
You will confirm that the header size and material come from the approved plans, prescriptive code table, engineered span table, or a qualified designer; inspect the header stock and any built-up components; verify the actual rough-opening width and required bearing; assemble multi-ply headers where specified; install the supporting jack studs, posts, or bearing blocks; lift and seat the header; fasten it to the approved schedule; and verify the continuous load path above and below the header before closing the work.
This project follows the rough-opening framing taught in Project 09. Project 09 established king studs, jack studs, header limits, sill members, and cripple-stud locations for both structural and non-structural openings. This project focuses specifically on the structural header itself: selecting the correct material and ply count from the approved schedule, assembling it correctly, and installing it with a verified bearing and load path. It feeds directly into Project 11, where the completed wall — including its installed headers — is raised, plumbed, and braced.
A header carries the wall and roof or floor loads that would otherwise be carried by the wall studs removed to create a door or window opening. Every pound of load above a structural opening passes through the header, into its jack studs or posts, and down through the wall to the foundation or beam below. A header that is undersized, unsupported, or disconnected from that load path does not fail gradually — it fails as a structural event.
This project sits between Project 09, which frames the rough opening geometry, and Project 11, which raises and braces the completed wall. The load-path verification taught here — confirming that bearing continues uninterrupted from the header, through the jack studs, through the wall, and down to the structure below — is the same verification repeated in Project 20, where the capstone shed's door and window headers are checked against the same standard before the roof is framed.
This project covers:
This project does not authorize the learner to:
Header sizing for any load-bearing opening is structural work. If the approved plans, prescriptive table, or engineered table do not clearly cover the opening's span, load condition, or ply requirement, stop work and obtain direction from a qualified structural professional before proceeding.
Establish these references before cutting or assembling any header component, and do not change them once fabrication has started.
| Term | Definition |
|---|---|
| Header schedule | The approved document specifying header material, ply count, depth, length, bearing length, and fastening pattern for each scheduled opening |
| Bearing length | The horizontal length of header end resting directly on the jack stud, post, or bearing block below it, measured per the approved schedule |
| Ply | One layer of a multi-ply built-up header; plies are fastened together face-to-face to form the finished header member |
| King stud | The full-height stud at each side of a rough opening, extending from the bottom plate to the top plate, to which the header assembly connects |
| Jack stud (trimmer stud) | The stud that extends from the bottom plate to the underside of the header, providing direct bearing for the header end |
| Load path | The continuous structural route through which a load travels from the roof or floor above, through the header, jack studs, wall, and down to the foundation or beam below |
Before cutting or assembling any header component, record the controlling schedule reference and opening identification directly on the header/installation record:
Wall/opening ID: ______ Header schedule reference: ______ Header material and ply count: ______ Required bearing length: ______
Date started: ____________ Builder name: ____________
Every header installed in this project follows the same load-path logic: the roof or floor load above bears on the header, the header bears on the jack studs or posts at each end, and those jack studs or posts bear on the wall's bottom plate, which in turn bears on the floor framing or foundation established in Projects 01 through 03. A header is not a finished component until every link in that chain is verified, fastened, and free of gaps.
Header size, species, grade, ply count, and bearing length are never selected in the field from judgment or from the rough-opening width alone. These values must come from the approved plans, the header schedule supplied with the project specification, a prescriptive code table applicable to the exact span and load condition, an engineered span table for the specific product, or a qualified structural designer. If none of these sources clearly covers the opening being framed, stop work and obtain direction before cutting any header material.
Never select a header size by comparing it to a similar-looking opening elsewhere in the structure. Span, load condition, tributary width, and existing wall configuration all affect the correct header size, and two openings of the same rough width can require different headers. Confirm the exact schedule entry, prescriptive table row, or engineered value for each opening individually.
Laminated veneer lumber, glulam, and other engineered headers may not be field-cut, drilled, notched, or otherwise altered except where the manufacturer's published instructions explicitly permit it. Confirm allowable end cuts, hole locations, and handling and storage requirements from the manufacturer's current literature before cutting or drilling any engineered header.
Measure the actual rough-opening width in the field before cutting the header to length. Framed openings can vary slightly from the plan dimension even when built to the same layout. Cut the header to fit the verified field dimension and required bearing length, not to the nominal plan dimension alone, unless the approved schedule specifies an exact header length.
Plan the header lift before removing any temporary support already in place at the opening. Assign additional workers or mechanical lifting assistance for headers exceeding the single-worker safe lifting limit established for this project. Install temporary support posts or T-braces under the header immediately after it is lifted into position, before releasing it for fastening.
FR-055 – FR-060
Fabrication / Installation / Load-Path Verification
Scope: one or more completed structural headers, each installed at its scheduled opening with the specified material, ply count, bearing supports, connectors, and fastening, and each verified for elevation, level, bearing, ply contact, connector seating, and continuous load path.
| Document | Source | Confirmation Required |
|---|---|---|
| Header schedule | Design professional / plan set | Current revision; entry identified for each opening being framed |
| Prescriptive span table (where used) | Adopted code | Table row matches the exact span, load condition, and jurisdiction |
| Engineered product span table (where used) | Manufacturer / product literature | Table matches the specific product, span, and load condition |
| Connector and fastening schedule | Design professional / manufacturer | Matches the specified header-to-stud and hold-down connections |
| Rough-opening framing record | Project 09 documentation | King stud, jack stud, and opening dimensions confirmed complete |
| Check | Standard |
|---|---|
| Header material and ply count | Matches the approved header schedule entry for the specific opening; any discrepancy is logged and referred, not resolved in the field |
| Bearing length at each end | Meets or exceeds the bearing length stated on the approved schedule, with full contact between header and jack stud/post |
| Header elevation and level | Matches the plan-specified rough-opening height and reads level within the tolerance stated on the approved plan or design professional's direction |
| Ply contact and fastening | All plies of a built-up header are in full face contact with no gaps, fastened in the pattern specified on the approved schedule |
| Connector installation | Straps, hangers, hold-downs, and other connectors installed with listed fasteners in the manufacturer's specified pattern and orientation |
| Load path continuity | Continuous, unobstructed bearing confirmed from the header through the jack studs/posts to the foundation, beam, or approved structure below |
Inspect every completed header using the same checks regardless of material type or opening location.
Complete the Header/Installation Record in the Inspection Checklist section below before wall sheathing or concealment begins.
Probable cause: the jack stud or post was cut short, the header was cut long, or the opening was framed out of square, leaving a gap at one end.
Confirmation: measure the actual bearing length at each end and compare it with the schedule's required bearing length; check jack-stud height and plumb.
Correction: shim only if the approved detail permits shimming for the specific bearing condition; otherwise remove the header, correct the jack-stud height or opening framing, and reseat it. Do not force a header into a bearing condition that reduces contact area below the specified length.
Reinspection: repeat the bearing-length check at both ends after correction.
Probable cause: the plies were not clamped before fastening, the stock is bowed or twisted, or the spacer thickness does not match the specified value.
Confirmation: inspect the full length of the assembled header for daylight or gaps between plies, and verify spacer thickness against the schedule.
Correction: disassemble and reassemble with correct clamping and spacer thickness, or replace bowed or twisted stock; do not fasten plies together with a visible gap.
Reinspection: repeat the ply-contact check along the full header length before installation.
Probable cause: the jack studs on each side of the opening are cut to different lengths, or one bearing support settled during the lift.
Confirmation: measure jack-stud height on both sides of the opening and compare; check the level reading at multiple points along the header.
Correction: correct the jack-stud height on the low side per the approved detail; do not compensate by tilting the header or adding an unspecified shim thickness.
Reinspection: repeat the level check across the full header length after correction.
Probable cause: a generic fastener was substituted for a listed connector fastener, or the fastener quantity or spacing was reduced from the specified pattern.
Confirmation: compare the installed fasteners against the connector manufacturer's specified type, quantity, and pattern for the connector in use.
Correction: remove substituted fasteners and install the specified listed fasteners in the complete pattern; do not leave a partial fastener pattern in place.
Reinspection: repeat the connector check and confirm every required fastener location is filled.
Probable cause: the jack stud or post does not align with adequate bearing below (such as a floor joist, beam, or foundation point), or an intermediate framing member was omitted.
Confirmation: trace the load path from the header end down through the jack stud or post to its bearing point on the floor or foundation, checking for alignment and continuous support at every level.
Correction: stop work at that opening and obtain direction from the design professional; do not add an unapproved post, blocking, or bearing detail to close the gap without a documented decision.
Reinspection: repeat the full load-path check after the approved correction is installed.
Probable cause: the wrong header was pulled from staged material, or the schedule reference used was not the current approved revision.
Confirmation: confirm the header schedule revision date, then compare the installed header's material, depth, and ply count against the current schedule entry for that specific opening.
Correction: remove the incorrect header and install the schedule-specified header; log the substitution and the correction on the header/installation record.
Reinspection: repeat the material check and the full Acceptance Standards review for the corrected header.
This project ends with one or more installed, fastened, and documented headers, ready for the wall to be closed, sheathed, and raised in Project 11.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| FR-055 | Selects header material from the approved header schedule, prescriptive table, engineered table, or qualified designer, and correctly identifies its handling restrictions | |||
| FR-056 | Assembles multi-ply, solid-sawn, or engineered headers correctly to the approved fastener pattern, spacer requirements, and orientation | |||
| FR-057 | Installs jack studs, posts, bearing blocks, or column assemblies that provide the specified bearing beneath each header end | |||
| FR-058 | Fastens the header to king studs, jack studs, straps, hangers, or other connectors correctly according to the approved connection schedule | |||
| FR-059 | Verifies that the header's load path transfers continuously to the foundation, beam, or approved structure below, with no missing or offset support | |||
| FR-060 | Inspects the completed header installation for elevation, level, bearing length, ply contact, fastener pattern, connector seating, and wall-face alignment, and documents the results completely |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Check | Plan Value / Requirement | Field Value | Within Tolerance (Y/N) | Correction (if any) |
|---|---|---|---|---|
| Header material and ply count | Per header schedule | |||
| Header length | ||||
| Bearing length — left end | ||||
| Bearing length — right end | ||||
| Header elevation | ||||
| Header level | Within approved tolerance | |||
| Ply contact / fastening | Full contact, per fastener schedule | |||
| Connector installation | Per connector schedule | |||
| Load path — above header | Continuous, no gaps | |||
| Load path — below header | Continuous, no gaps |
Open discrepancies attached: ____________ Responsible authority for each: ____________
Header installation approved: ______ (Pass/Fail) Date: ____________ Builder name: ____________
With material selection, assembly, bearing-support installation, header lift, fastening, and load-path verification complete, review the finished header against the Acceptance Standards table and confirm the header material and ply count match the approved schedule, bearing length and contact are correct at both ends, the header reads level within tolerance, all connectors are installed with listed fasteners in the specified pattern, and the load path is continuous from the header to the foundation, beam, or approved structure below. Complete and sign the header/installation record for each header before wall sheathing begins in Project 12. If a discrepancy remains open, identify the responsible authority and required decision before proceeding.
You have completed the tenth project in the residential framing sequence: installing structural headers. This project required you to select header material from the approved schedule, prescriptive table, engineered table, or qualified designer (FR-055), assemble multi-ply, solid-sawn, or engineered headers correctly (FR-056), install jack studs, posts, or bearing blocks that provide the specified bearing (FR-057), fasten the header to king studs, jack studs, and connectors per the approved schedule (FR-058), verify the header's continuous load path to the structure below (FR-059), and inspect and document the completed installation (FR-060).
You now have one or more installed structural headers with a verified, documented load path from roof or floor load down to the foundation or beam below. That completed opening framing carries directly into the next project: raising, plumbing, bracing, and aligning the wall sections that contain these headers.
Protect the installed headers and their temporary support until the wall is raised and permanently braced. Do not remove temporary support from a header until its installation record confirms permanent fastening and bearing are complete.