Project 15

Install Roof Trusses

Receive, stage, set, brace, connect, and inspect an approved prefabricated roof-truss package on a designated structure, using the sealed truss drawings, placement diagram, and permanent-bracing information as the controlling design.

Field Cue System

These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework, disputes, or hazards.

△

Safety Cue

Task-specific safety guidance for ordinary work hazards.

✋

Critical Safety Cue

Serious injury or major structural consequence is possible.

⛑

Field Safety Cue

Practical work-area safety: footing, debris, standing water, and access.

▤

Code Alert

Local requirements vary. Verify permit, inspection, and jurisdictional rules.

▧

Manufacturer Cue

Follow product-specific instructions for anchors, hold-downs, and connectors.

▱

Measurement Cue

Clearance, layout, spacing, and reference-point guidance.

Job Overview

This project qualifies you to receive, stage, set, brace, connect, and inspect a prefabricated roof-truss package on a designated structure. The finished work product is a complete truss roof system installed at the plan-specified spacing, seated fully on bearing, restrained by the required temporary bracing during erection, and connected and permanently braced according to the sealed truss documents.

You will obtain the sealed truss design drawings and placement diagram, confirm the structure was designed for a truss roof, inspect delivered trusses for damage and correct identification, stage and arrange the trusses in installation order, mark truss centers on the bearing walls, set and plumb the first truss with temporary bracing, erect the remaining trusses in sequence with continuous lateral restraint, install the required connectors and permanent bracing, and verify the completed system against the truss documents before it is closed in with roof sheathing.

This project follows Chapter 13, Frame Ceiling Joists, and depends on the wall system raised, plumbed, braced, and sheathed in Chapters 11 and 12. It is an alternate roof-framing method to the site-built rafter system in Chapter 14 and must not be combined with that system on the same roof. The completed truss roof becomes the structure that receives the roof sheathing installed in Chapter 16.

Skills You Will Demonstrate

  • FR-085 — Receive, inspect, and stage a delivered truss package according to the supplier's handling instructions and the sealed truss documents.
  • FR-086 — Lay out truss spacing on the bearing walls from a common reference point and mark the location of every truss, including special trusses.
  • FR-087 — Set each truss on its marked location, seat it fully on bearing, and restrain it against twisting or rolling during erection.
  • FR-088 — Install and maintain the temporary bracing system required to hold trusses plumb, spaced, and stable until permanent bracing is complete.
  • FR-089 — Fasten truss connectors, clips, ties, hangers, bolts, and straps according to the approved connector schedule using listed fasteners.
  • FR-090 — Inspect the completed truss system for identification, placement, spacing, plumb, bearing, connectors, and bracing, and document the results.

Where This Skill Fits

The wall system raised, plumbed, connected, and sheathed in Chapters 11 and 12 exists to carry the loads this truss roof will impose. The truss centers marked on the top plates in this project must align with the wall framing and any concentrated-load points identified in the wall and truss documents. The temporary-bracing discipline introduced for individual walls in Chapter 11 is extended here into a continuous system across an entire roof plane, where an unbraced or improperly spaced truss can fail without warning during erection.

The completed and permanently braced truss system becomes the platform for the roof sheathing installed in Chapter 16, and the connector and load-path verification performed here is the same verification repeated at the capstone shed roof in Chapter 20 if a truss roof is selected for that structure.

Scope and Intended Use

This project covers:

  • obtaining and reviewing the sealed truss design drawings, placement diagram, permanent-bracing information, and connector schedule
  • inspecting delivered trusses for identification, orientation, damage, broken plates, field alterations, and moisture exposure
  • staging trusses upright or flat only as permitted by the supplier
  • marking truss centers and setting, plumbing, and temporarily bracing each truss in sequence
  • installing the listed connectors and completing the permanent bracing shown on the truss documents
  • inspecting and documenting the completed truss system

This project does not authorize the learner to:

  • cut, drill, notch, splice, or otherwise alter any truss member or metal connector plate
  • substitute a different truss, spacing, or connector for the one specified on the sealed truss documents
  • remove temporary bracing before permanent bracing required by the truss documents is complete
  • set trusses on a structure that was not designed for a truss roof, or combine truss framing with the site-built rafter system from Chapter 14 on the same roof without an engineered transition detail
  • direct a crane or mechanical lift without a qualified operator, an approved lift plan, and required signaling and exclusion-zone controls

Any damaged, unidentified, or field-altered truss must be quarantined and referred to the truss designer or manufacturer before it is used.

Reference Conventions

Establish these references before any truss is lifted, and do not change them once erection has started.

TermDefinition
Placement diagramThe sealed drawing identifying the location, orientation, and identification mark of every truss in the roof system
Common trussA standard repeating truss used at the plan-specified spacing across the majority of the roof
Girder trussA truss designed to carry the reaction load of other trusses or members and requiring its own specified connectors
Gable-end trussThe truss set at a gable end, typically requiring specified vertical webs and permanent lateral bracing
Temporary bracingThe lumber and connectors installed during erection to hold trusses plumb, spaced, and stable before permanent bracing is complete
Permanent bracingThe web, chord, and lateral bracing shown on the truss documents that remains in the finished roof and is required for the truss to perform as designed
Common reference pointThe single wall-top location, identified from the placement diagram, from which all truss-center marks are measured

Truss-Erection Log

Before setting any truss, record the controlling documents and structure identification directly on the truss-erection log:

Structure ID: ______     Truss design drawing set and revision date: ______     Placement diagram revision: ______     Supplier and delivery date: ______

Date started: ____________     Builder/crew lead name: ____________

Prerequisites

Common Field Fundamentals

Every truss-erection sequence in this book, whether a common truss, girder truss, or gable-end truss, follows the same pattern: review the sealed documents, verify the supporting structure, inspect the delivered trusses, lay out and mark placement, set and temporarily brace each truss in sequence, install permanent bracing and connectors, and inspect and document the completed system. Learning that sequence here protects the roof framing that carries every later roofing and enclosure project in this book series.

Document reviewSealed drawings, placement diagram, and connector schedule confirmed current
Delivery inspectionIdentification, damage, plates, and moisture condition checked before staging
Setting and bracingTrusses set, plumbed, and temporarily braced in the prescribed sequence
Connection and inspectionListed connectors and permanent bracing installed and verified

Temporary Bracing and the Load Path

A single unbraced truss has no lateral stability and can roll or fall under its own weight or a light wind load. The temporary-bracing system specified by the truss documents ties trusses together as they are erected, so that the erected section resists lateral movement as a unit rather than relying on any single truss. Permanent bracing performs a different function: it holds individual truss members — webs and chords — in the position the design requires so the truss develops its rated capacity. Removing temporary bracing before permanent bracing is complete removes the only lateral restraint the roof has at that stage.

FR-085 – FR-090

Erection / Structural Connection / Inspection Qualification

Prefabricated Roof-Truss Erection

Difficulty: Intermediate–Advanced

Estimated Time: 6–10 hours, crew of three or more

Estimated Cost: Truss package plus bracing and connector material; obtain current pricing

Finished Work: A complete, braced, connected, and inspected prefabricated truss roof system

A. Finished-Project Specification

Scope: one completed truss-roof erection covering every common, girder, gable-end, attic, and valley-set truss shown on the placement diagram for the designated structure, with all specified temporary bracing removed only after permanent bracing and connectors are complete, and a signed truss-erection log with attached inspection results.

B. Required Documentation Schedule

DocumentSourceConfirmation Required
Sealed truss design drawingsTruss designer / manufacturerCurrent revision on site, sealed by the responsible engineer
Truss-placement diagramTruss designer / supplierMatches the delivered truss package and structure
Permanent-bracing informationTruss designer / manufacturerIdentifies all required web, chord, and lateral bracing
Connector scheduleTruss designer / connector manufacturerMatches installed connector type and fastener requirements
Approved building plansDesign professional / plan setCurrent revision, confirms structure is designed for trusses
Lift planGeneral contractor / crane operatorEquipment, crew roles, exclusion zones, and wind limits confirmed

C. Erection Materials and Consumables

  • Temporary-bracing lumber: sized and located per the truss documents or supplier's standard temporary-bracing detail; sufficient for continuous lateral restraint of every erected truss until permanent bracing is complete.
  • Permanent-bracing material: type, size, and location specified by the truss documents.
  • Truss connectors and fasteners: listed clips, ties, hangers, bolts, and straps matching the approved connector schedule; only listed fasteners for each connector.
  • Documentation: one truss-erection log and inspection checklist per structure.

D. Acceptance Standards

CheckStandard
Truss identification and placementEvery truss matches its identification mark and location on the placement diagram; no substitutions
SpacingTruss centers match the spacing specified on the placement diagram, held with approved gauges or spacers
PlumbEach truss is plumb within the tolerance specified by the truss documents or design professional before permanent bracing is fastened
BearingEach truss is fully seated on its bearing wall or beam without twist or roll, matching the bearing condition shown on the truss drawings
ConnectorsType, quantity, fastener, and orientation match the approved connector schedule for every truss-to-wall and truss-to-truss connection
Temporary and permanent bracingTemporary bracing is continuous and intact until permanent bracing shown on the truss documents is fully installed
Member conditionNo truss member or metal connector plate is cut, drilled, notched, spliced, or altered in the field

E. Document Review and Delivery Inspection (Steps 1–5)

  1. Obtain the sealed truss design drawings, truss-placement diagram, permanent-bracing information, connector schedule, handling instructions, and approved building plans. Confirm the revision date of each document against the project's document-control log before using it.
  2. Confirm that the selected structure is designed for trusses and is separate from the site-built rafter project in Chapter 14. Verify against the approved building plans before any truss is staged.
  3. Verify bearing walls, top plates, wall bracing, dimensions, truss supports, and lifting access. Confirm the wall system has passed the inspection required before truss loading and record the confirmation on the truss-erection log.
  4. Inspect delivered trusses for identification, orientation, damage, broken plates, cuts, field alterations, and moisture exposure. Check each truss against its identification mark on the placement diagram as it is inspected.
  5. Quarantine damaged or unidentified trusses and obtain manufacturer or engineer direction. Tag each quarantined truss, record its identification and defect, and do not stage it for erection until direction is received.

F. Staging and Layout (Steps 6–9)

  1. Stage trusses upright or flat only as permitted by the supplier, with adequate support and restraint. Confirm the staging method matches the supplier's handling instructions before trusses are unloaded from the delivery vehicle.
  2. Arrange trusses in installation order according to the placement diagram. Sequence the staged trusses so each is accessible in the order it will be lifted.
  3. Mark truss centers on both bearing walls from a common reference point. Measure every truss-center mark from the same wall-top reference point identified in Section G below; do not measure sequentially from the previous mark.
  4. Mark girder trusses, gable-end frames, attic trusses, valley sets, and special trusses by location. Label each special-truss location directly from the placement diagram and confirm it does not conflict with the common-truss layout.

G. Lift Planning and First-Truss Erection (Steps 10–12)

  1. Review the lift plan, crane or mechanical equipment, tag lines, crew roles, exclusion zones, wind limits, and fall protection. Confirm every crew member's role and the location of the exclusion zone before the first lift.
  2. Set the first truss at the designated location. Align the truss with its marked centerline and seat it fully on bearing before releasing rigging tension.
  3. Plumb and brace the first truss using the approved temporary-bracing system. Install temporary bracing per the truss documents or supplier's standard detail before releasing the lifting equipment.

H. Sequential Erection and Restraint (Steps 13–16)

  1. Set the second and subsequent trusses in the prescribed sequence. Follow the order established in Step 7 and confirm each truss's identification against the placement diagram before it is lifted.
  2. Install continuous lateral restraint and diagonal bracing as trusses are erected. Do not allow any erected truss to stand without temporary lateral restraint, even briefly.
  3. Maintain specified spacing using approved gauges or temporary spacers. Check spacing at both the top chord and bottom chord of each truss as it is set.
  4. Seat each truss fully on bearing without twisting or rolling it. Verify full bearing contact and plumb before moving to the next truss.

I. Connectors and Permanent Bracing (Steps 17–20)

  1. Install clips, ties, hangers, bolts, straps, or other connectors using listed fasteners. Match connector type, quantity, and orientation to the approved connector schedule for each truss-to-wall and truss-to-truss connection.
  2. Install gable-end bracing and restraint according to the truss and building design. Complete gable-end vertical and lateral bracing before removing temporary bracing at that location.
  3. Complete permanent web and chord bracing shown on the truss documents. Install every permanent brace shown on the truss drawings before releasing any corresponding temporary brace.
  4. Do not cut, drill, notch, splice, or alter any truss member or metal plate. Refer any fit, damage, or conflict issue to the truss designer for a documented repair or modification detail.

J. Inspection and Documentation (Steps 21–24)

  1. String and inspect truss peaks, heels, tails, and bearing lines. Sight along the string line and record any truss that deviates beyond the tolerance specified by the truss documents.
  2. Verify truss identification, placement, spacing, plumb, bearing, connectors, temporary bracing, and permanent bracing. Complete the full acceptance-standards table in Section D for every truss before concealment.
  3. Obtain repair details from the truss designer for any damage or installation conflict. Log the conflict, the date reported, and the party contacted; do not conceal the affected truss until direction is received.
  4. Record truss documents, delivery condition, placement, connectors, repairs, and inspection results. Complete every required entry on the truss-erection log before roof sheathing begins.

Common Verification Inspection

Inspect the completed truss system using the same checks regardless of which section of the roof it covers.

Complete the Truss-Erection Log in the Inspection Checklist section below before beginning Project 16.

Image Placeholder
Recommended image: a delivered truss package staged upright and restrained according to the supplier's handling instructions.
Image Placeholder
Recommended image: truss centers marked on a bearing wall top plate from a common reference point.
Image Placeholder
Recommended image: a crane lift setting a truss with tag lines controlling its position.
Image Placeholder
Recommended image: continuous diagonal temporary bracing installed across a run of erected trusses.
Image Placeholder
Recommended image: a listed truss-to-wall connector installed with the specified fasteners.
Image Placeholder
Recommended image: a completed truss-erection log with placement, spacing, and inspection results entered.

Failure Points and Troubleshooting

Cleanup

This project ends with a complete, braced, connected, and inspected truss roof system, not with roof sheathing installed.

Field Terms

Placement Diagram
The sealed drawing identifying the location, orientation, and identification mark of every truss in the roof system.
Common Truss
A standard repeating truss used at the plan-specified spacing across the majority of the roof.
Girder Truss
A truss designed to carry the reaction load of other trusses or members, requiring its own specified connectors.
Gable-End Truss
The truss set at a gable end, typically requiring specified vertical webs and permanent lateral bracing.
Temporary Bracing
Lumber and connectors installed during erection to hold trusses plumb, spaced, and stable before permanent bracing is complete.
Permanent Bracing
Web, chord, and lateral bracing shown on the truss documents that remains in the finished roof.
Common Reference Point
The single wall-top location from which all truss-center marks are measured.
Connector Schedule
The approved document specifying connector type, quantity, fastener, and orientation for each truss connection.
Quarantine
Setting aside a damaged or unidentified truss and withholding it from erection until the designer or manufacturer provides direction.
Truss-Erection Log
The signed document confirming delivery condition, placement, spacing, bearing, connectors, bracing, and inspection results.

Skill Check

  1. Why must every truss-center mark be measured from a single common reference point rather than sequentially from the previous truss?
  2. What is the functional difference between temporary bracing and permanent bracing, and why can one not substitute for the other?
  3. What must the learner do if a delivered truss shows damage or cannot be identified against the placement diagram?
  4. Why is field cutting, drilling, notching, or splicing a truss member or metal connector plate never authorized under this project?
  5. What conditions require the learner to stop work and obtain direction from the truss designer or manufacturer?
  6. Why must permanent bracing be complete before any corresponding temporary bracing is removed?
  7. What information must be verified for a truss-to-wall connector before it is accepted as installed correctly?
  8. Why does a girder truss or gable-end truss require separate identification during layout rather than being treated as a common truss?
  9. What must be true of the truss-erection log before roof sheathing begins in Project 16?
  10. Why must this project not be combined with the site-built rafter system from Chapter 14 on the same roof without an engineered transition detail?

Competency Rubric

CompetencyIndependent Pass StandardNot DemonstratedWith AssistanceIndependently
FR-085Receives, inspects, and stages a delivered truss package according to the supplier's handling instructions and the sealed truss documents
FR-086Lays out truss spacing on the bearing walls from a common reference point and correctly marks every truss location, including special trusses
FR-087Sets each truss on its marked location, seats it fully on bearing, and restrains it against twisting or rolling during erection
FR-088Installs and maintains the temporary bracing system required to hold trusses plumb, spaced, and stable until permanent bracing is complete
FR-089Fastens truss connectors, clips, ties, hangers, bolts, and straps according to the approved connector schedule using listed fasteners
FR-090Inspects the completed truss system for identification, placement, spacing, plumb, bearing, connectors, and bracing, and documents the results completely

Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.

Inspection Checklist — Truss-Erection Log

CheckPlan Value / RequirementField ValueWithin Tolerance (Y/N)Correction (if any)
Bearing-wall inspection completeComplete before truss loading
Delivered truss conditionNo damage, correct identification
Truss spacingPer placement diagram
Truss plumbWithin specified tolerance
Bearing seatingFull bearing, no twist or roll
Girder/gable-end/special trussesCorrect location per placement diagram
Connectors and fastenersMatches approved connector schedule
Temporary bracingContinuous and intact until permanent bracing complete
Permanent bracingMatches truss documents, complete
Truss member/plate conditionNo cutting, drilling, notching, or alteration

Open discrepancies attached: ____________     Responsible authority for each: ____________

Truss erection declared: ______ (Pass/Fail)     Date: ____________     Builder/crew lead name: ____________

Performance Check

With document review, delivery inspection, layout, sequential erection, temporary bracing, connector installation, and permanent bracing complete, review the finished truss system against the Acceptance Standards table and confirm every truss matches its identification and location on the placement diagram, spacing and plumb are within tolerance, every truss is fully seated on bearing, every connector matches the approved schedule, and permanent bracing is complete for every section where temporary bracing has been removed. Complete and sign the truss-erection log before roof sheathing begins in Project 16. If a discrepancy remains open, identify the responsible authority and required decision before proceeding.

Project Closeout

You have completed the fifteenth project in the residential framing sequence: installing a prefabricated roof-truss system. This project required you to receive, inspect, and stage the delivered truss package (FR-085), lay out truss spacing and mark every truss location (FR-086), set and seat each truss on bearing (FR-087), install and maintain the required temporary bracing system (FR-088), fasten the specified connectors using listed fasteners (FR-089), and inspect and document the completed truss system (FR-090).

You now have a complete, braced, connected, and inspected truss roof system ready to receive roof sheathing. That completed roof deck framing carries directly into the next project: installing the structural roof sheathing that creates the roof deck for the roofing work covered in Book 5.

Protect all temporary bracing until every permanent brace shown on the truss documents is confirmed installed. Do not begin roof sheathing over any section where permanent bracing is incomplete.