Receive, stage, set, brace, connect, and inspect an approved prefabricated roof-truss package on a designated structure, using the sealed truss drawings, placement diagram, and permanent-bracing information as the controlling design.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework, disputes, or hazards.
Task-specific safety guidance for ordinary work hazards.
Serious injury or major structural consequence is possible.
Practical work-area safety: footing, debris, standing water, and access.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for anchors, hold-downs, and connectors.
Clearance, layout, spacing, and reference-point guidance.
This project qualifies you to receive, stage, set, brace, connect, and inspect a prefabricated roof-truss package on a designated structure. The finished work product is a complete truss roof system installed at the plan-specified spacing, seated fully on bearing, restrained by the required temporary bracing during erection, and connected and permanently braced according to the sealed truss documents.
You will obtain the sealed truss design drawings and placement diagram, confirm the structure was designed for a truss roof, inspect delivered trusses for damage and correct identification, stage and arrange the trusses in installation order, mark truss centers on the bearing walls, set and plumb the first truss with temporary bracing, erect the remaining trusses in sequence with continuous lateral restraint, install the required connectors and permanent bracing, and verify the completed system against the truss documents before it is closed in with roof sheathing.
This project follows Chapter 13, Frame Ceiling Joists, and depends on the wall system raised, plumbed, braced, and sheathed in Chapters 11 and 12. It is an alternate roof-framing method to the site-built rafter system in Chapter 14 and must not be combined with that system on the same roof. The completed truss roof becomes the structure that receives the roof sheathing installed in Chapter 16.
The wall system raised, plumbed, connected, and sheathed in Chapters 11 and 12 exists to carry the loads this truss roof will impose. The truss centers marked on the top plates in this project must align with the wall framing and any concentrated-load points identified in the wall and truss documents. The temporary-bracing discipline introduced for individual walls in Chapter 11 is extended here into a continuous system across an entire roof plane, where an unbraced or improperly spaced truss can fail without warning during erection.
The completed and permanently braced truss system becomes the platform for the roof sheathing installed in Chapter 16, and the connector and load-path verification performed here is the same verification repeated at the capstone shed roof in Chapter 20 if a truss roof is selected for that structure.
This project covers:
This project does not authorize the learner to:
Any damaged, unidentified, or field-altered truss must be quarantined and referred to the truss designer or manufacturer before it is used.
Establish these references before any truss is lifted, and do not change them once erection has started.
| Term | Definition |
|---|---|
| Placement diagram | The sealed drawing identifying the location, orientation, and identification mark of every truss in the roof system |
| Common truss | A standard repeating truss used at the plan-specified spacing across the majority of the roof |
| Girder truss | A truss designed to carry the reaction load of other trusses or members and requiring its own specified connectors |
| Gable-end truss | The truss set at a gable end, typically requiring specified vertical webs and permanent lateral bracing |
| Temporary bracing | The lumber and connectors installed during erection to hold trusses plumb, spaced, and stable before permanent bracing is complete |
| Permanent bracing | The web, chord, and lateral bracing shown on the truss documents that remains in the finished roof and is required for the truss to perform as designed |
| Common reference point | The single wall-top location, identified from the placement diagram, from which all truss-center marks are measured |
Before setting any truss, record the controlling documents and structure identification directly on the truss-erection log:
Structure ID: ______ Truss design drawing set and revision date: ______ Placement diagram revision: ______ Supplier and delivery date: ______
Date started: ____________ Builder/crew lead name: ____________
Every truss-erection sequence in this book, whether a common truss, girder truss, or gable-end truss, follows the same pattern: review the sealed documents, verify the supporting structure, inspect the delivered trusses, lay out and mark placement, set and temporarily brace each truss in sequence, install permanent bracing and connectors, and inspect and document the completed system. Learning that sequence here protects the roof framing that carries every later roofing and enclosure project in this book series.
A single unbraced truss has no lateral stability and can roll or fall under its own weight or a light wind load. The temporary-bracing system specified by the truss documents ties trusses together as they are erected, so that the erected section resists lateral movement as a unit rather than relying on any single truss. Permanent bracing performs a different function: it holds individual truss members — webs and chords — in the position the design requires so the truss develops its rated capacity. Removing temporary bracing before permanent bracing is complete removes the only lateral restraint the roof has at that stage.
Do not remove or modify temporary truss bracing until the permanent bracing shown on the truss documents is installed and complete for that section of roof. A roof section that appears stable can collapse laterally if temporary bracing is removed before the permanent system is in place. Stop work and restore temporary bracing immediately if any is found loose, damaged, or missing.
Follow the approved lift plan for every truss lift. Assign one person to direct the lift and to stop the operation immediately for loss of control, changing wind conditions, or any worker inside the exclusion zone. Use tag lines to control truss position and rotation; do not steady a suspended truss by hand.
Use fall protection whenever working on wall tops, ladders, or truss top chords during erection and bracing. Keep the erection area clear of stored material, offcuts, and tripping hazards, and maintain a clear path for temporary-bracing installation at every truss.
Do not cut, drill, notch, splice, or otherwise alter any truss member or metal connector plate. If a truss is damaged, does not fit its marked location, or conflicts with another building component, stop work at that truss and obtain a repair or modification detail from the truss designer or manufacturer before proceeding.
FR-085 – FR-090
Erection / Structural Connection / Inspection Qualification
Scope: one completed truss-roof erection covering every common, girder, gable-end, attic, and valley-set truss shown on the placement diagram for the designated structure, with all specified temporary bracing removed only after permanent bracing and connectors are complete, and a signed truss-erection log with attached inspection results.
| Document | Source | Confirmation Required |
|---|---|---|
| Sealed truss design drawings | Truss designer / manufacturer | Current revision on site, sealed by the responsible engineer |
| Truss-placement diagram | Truss designer / supplier | Matches the delivered truss package and structure |
| Permanent-bracing information | Truss designer / manufacturer | Identifies all required web, chord, and lateral bracing |
| Connector schedule | Truss designer / connector manufacturer | Matches installed connector type and fastener requirements |
| Approved building plans | Design professional / plan set | Current revision, confirms structure is designed for trusses |
| Lift plan | General contractor / crane operator | Equipment, crew roles, exclusion zones, and wind limits confirmed |
| Check | Standard |
|---|---|
| Truss identification and placement | Every truss matches its identification mark and location on the placement diagram; no substitutions |
| Spacing | Truss centers match the spacing specified on the placement diagram, held with approved gauges or spacers |
| Plumb | Each truss is plumb within the tolerance specified by the truss documents or design professional before permanent bracing is fastened |
| Bearing | Each truss is fully seated on its bearing wall or beam without twist or roll, matching the bearing condition shown on the truss drawings |
| Connectors | Type, quantity, fastener, and orientation match the approved connector schedule for every truss-to-wall and truss-to-truss connection |
| Temporary and permanent bracing | Temporary bracing is continuous and intact until permanent bracing shown on the truss documents is fully installed |
| Member condition | No truss member or metal connector plate is cut, drilled, notched, spliced, or altered in the field |
Inspect the completed truss system using the same checks regardless of which section of the roof it covers.
Complete the Truss-Erection Log in the Inspection Checklist section below before beginning Project 16.
Probable cause: spacing was measured sequentially from the previous truss rather than from the common reference point, allowing small errors to accumulate.
Confirmation: re-measure every truss center in the affected run from the common reference point identified in Step 8, and compare each mark against the placement diagram.
Correction: loosen temporary bracing only as needed to reposition the affected trusses to their correct marked centers, then re-install temporary bracing before continuing.
Reinspection: repeat the spacing check across the full run after correction.
Probable cause: the bearing wall top plate is out of level, the truss heel is obstructed, or the wrong truss was set at that location.
Confirmation: verify the truss identification against the placement diagram, check the top plate for level at the bearing point, and inspect the heel area for obstructions.
Correction: if the wrong truss was set, remove and replace it with the correct identified truss; if the top plate is out of level, obtain direction before shimming, since an unauthorized shim can alter the bearing condition assumed by the truss design.
Reinspection: repeat the bearing check once the correction is confirmed.
Probable cause: damage was not visible during the delivery inspection, or occurred during lifting or setting.
Confirmation: photograph and document the damage, its exact location on the truss, and the truss identification mark.
Correction: do not conceal, brace, or sheath over the damaged truss; contact the truss designer or manufacturer and obtain a documented repair detail before proceeding at that location.
Reinspection: re-inspect the repaired truss against the approved repair detail before permanent bracing and sheathing continue at that location.
Probable cause: insufficient fastening at the bracing connection, undersized bracing lumber, or bracing spacing wider than the truss documents specify.
Confirmation: inspect every temporary-bracing connection in the affected run for fastener condition, bracing size, and spacing against the truss documents or supplier's standard detail.
Correction: stop erection in the affected area, re-fasten or replace the failed bracing, and add bracing where spacing exceeds the specified interval before resuming work.
Reinspection: re-verify plumb and stability of every truss in the affected run after bracing is corrected.
Probable cause: an incorrect connector was installed, or a generic fastener was substituted for the listed fastener required by the connector.
Confirmation: compare the installed connector type, size, and fastener against the approved connector schedule for that specific connection.
Correction: remove the incorrect connector or fastener and install the specified listed connector and fastener; do not leave a mismatched connector in place.
Reinspection: repeat the connector check at that location and at any other location where the same substitution may have occurred.
Probable cause: the crew treated a plumb, connected truss run as complete without verifying every permanent brace shown on the truss documents was installed.
Confirmation: compare the installed bracing against the permanent-bracing information from the truss documents, member by member, for the affected section.
Correction: re-install temporary bracing at the affected section if it was removed, then install every missing permanent brace before removing temporary bracing again.
Reinspection: repeat the full bracing check for the affected section before proceeding to roof sheathing.
This project ends with a complete, braced, connected, and inspected truss roof system, not with roof sheathing installed.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| FR-085 | Receives, inspects, and stages a delivered truss package according to the supplier's handling instructions and the sealed truss documents | |||
| FR-086 | Lays out truss spacing on the bearing walls from a common reference point and correctly marks every truss location, including special trusses | |||
| FR-087 | Sets each truss on its marked location, seats it fully on bearing, and restrains it against twisting or rolling during erection | |||
| FR-088 | Installs and maintains the temporary bracing system required to hold trusses plumb, spaced, and stable until permanent bracing is complete | |||
| FR-089 | Fastens truss connectors, clips, ties, hangers, bolts, and straps according to the approved connector schedule using listed fasteners | |||
| FR-090 | Inspects the completed truss system for identification, placement, spacing, plumb, bearing, connectors, and bracing, and documents the results completely |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Check | Plan Value / Requirement | Field Value | Within Tolerance (Y/N) | Correction (if any) |
|---|---|---|---|---|
| Bearing-wall inspection complete | Complete before truss loading | |||
| Delivered truss condition | No damage, correct identification | |||
| Truss spacing | Per placement diagram | |||
| Truss plumb | Within specified tolerance | |||
| Bearing seating | Full bearing, no twist or roll | |||
| Girder/gable-end/special trusses | Correct location per placement diagram | |||
| Connectors and fasteners | Matches approved connector schedule | |||
| Temporary bracing | Continuous and intact until permanent bracing complete | |||
| Permanent bracing | Matches truss documents, complete | |||
| Truss member/plate condition | No cutting, drilling, notching, or alteration |
Open discrepancies attached: ____________ Responsible authority for each: ____________
Truss erection declared: ______ (Pass/Fail) Date: ____________ Builder/crew lead name: ____________
With document review, delivery inspection, layout, sequential erection, temporary bracing, connector installation, and permanent bracing complete, review the finished truss system against the Acceptance Standards table and confirm every truss matches its identification and location on the placement diagram, spacing and plumb are within tolerance, every truss is fully seated on bearing, every connector matches the approved schedule, and permanent bracing is complete for every section where temporary bracing has been removed. Complete and sign the truss-erection log before roof sheathing begins in Project 16. If a discrepancy remains open, identify the responsible authority and required decision before proceeding.
You have completed the fifteenth project in the residential framing sequence: installing a prefabricated roof-truss system. This project required you to receive, inspect, and stage the delivered truss package (FR-085), lay out truss spacing and mark every truss location (FR-086), set and seat each truss on bearing (FR-087), install and maintain the required temporary bracing system (FR-088), fasten the specified connectors using listed fasteners (FR-089), and inspect and document the completed truss system (FR-090).
You now have a complete, braced, connected, and inspected truss roof system ready to receive roof sheathing. That completed roof deck framing carries directly into the next project: installing the structural roof sheathing that creates the roof deck for the roofing work covered in Book 5.
Protect all temporary bracing until every permanent brace shown on the truss documents is confirmed installed. Do not begin roof sheathing over any section where permanent bracing is incomplete.