Project 17

Frame a Basic Stair Opening and Landing

Lay out and frame an approved floor opening and structural landing for a basic residential stair, using the supplied stair and framing design, so the opening, headers, trimmers, and landing are ready to receive the stair stringers built in Project 18.

Field Cue System

These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework, disputes, or hazards.

△

Safety Cue

Task-specific safety guidance for ordinary work hazards.

✋

Critical Safety Cue

Serious injury or major structural consequence is possible.

⛑

Field Safety Cue

Practical work-area safety: footing, debris, standing water, and access.

▤

Code Alert

Local requirements vary. Verify permit, inspection, and jurisdictional rules.

▧

Manufacturer Cue

Follow product-specific instructions for hangers, connectors, and fasteners.

▱

Measurement Cue

Clearance, layout, spacing, and reference-point guidance.

Job Overview

This project qualifies you to frame an approved floor opening and structural landing for a basic residential stair. The finished work product is a framed, headed, trimmed, and supported stair opening with an installed landing frame, guarded on every open edge, and documented on a signed stair-opening framing record.

You will review the approved stair plan, confirm the opening and landing have been designed and approved before any floor framing is cut, mark the opening on the existing subfloor, install temporary support below affected joists, remove only the subfloor area required, double the trimmer joists before cutting interrupted joists, set headers with the specified hangers and connections, frame the landing, verify clearances and headroom, and guard every open edge until the stringers in Project 18 are installed.

This project follows the completed floor, wall, ceiling, and roof framing chapters and uses the reference lines, floor framing, and structural connections established in Projects 1 through 16. It sits immediately before Project 18, which builds and installs the stair stringers that will bear on the opening and landing framed here.

Skills You Will Demonstrate

  • FR-097 — Lay out the stair opening on the subfloor from controlling wall and floor references and the approved stair plan.
  • FR-098 — Frame the floor opening, including temporary support, joist removal, and doubled trimmer installation.
  • FR-099 — Install opening headers with the specified hangers, bearing, and connections.
  • FR-100 — Build the landing frame according to the approved plan, including perimeter, supports, posts, beams, and joists.
  • FR-101 — Verify opening and landing clearances, headroom, and dimensions against the approved plan.
  • FR-102 — Inspect stair-framing support and document the completed opening, landing, and load path.

Where This Skill Fits

The stair opening interrupts completed floor framing, so it carries every requirement from Project 3's joist installation and Project 4's blocking and bridging into a new structural condition: cut joists that no longer carry load directly but instead transfer it through headers into doubled trimmers. An opening framed without full trimmer support, or a header hung without the specified connector, transfers that missing capacity into whatever loads the stair, landing, and any framing above it during Project 18 and beyond.

The temporary-support and controlled-cutting sequence used here is the same sequence required in Chapter 19 for structural repairs: support first, expose only what is needed, connect before releasing, and inspect before concealment.

Scope and Intended Use

This project covers:

  • reviewing the approved stair plan for floor-to-floor height, opening size, stair width, headroom, landing size, joist direction, headers, trimmers, posts, and guard requirements
  • marking the finished opening perimeter, rough framing limits, header locations, and landing position on the existing subfloor
  • installing temporary support, removing only the required subfloor area, and doubling trimmer joists before cutting interrupted joists
  • installing headers with the specified hangers, bearing, and connections and framing the landing perimeter, supports, posts, beams, and joists
  • verifying opening and landing dimensions, square, elevation, clearances, and headroom
  • installing temporary guards and covers around every open edge and documenting the completed work

This project does not authorize the learner to:

  • cut any floor joist before the stair opening and structural landing have been designed or approved and temporary support is installed
  • cut a joist before its adjacent doubled trimmer is installed and fastened
  • select header size, span, or bearing without the approved stair plan; header sizing is not a field decision in this project
  • install treads, risers, or a walking surface across the opening or landing before the framing and structural inspection required by Section H are complete
  • remove temporary guards or covers from an open floor edge before the stair stringers are installed in Project 18

Any condition suggesting a conflict between the opening and a beam, bearing wall, or utility must stop work in that area until direction is obtained.

Reference Conventions

Establish these references before any layout begins, and do not change them once the opening is marked.

TermDefinition
Finished openingThe stair opening dimension shown on the approved plan after all framing and finish material is installed
Rough framing limitThe larger dimension at the framing stage that, once finished material is added, produces the finished opening
Trimmer joistThe doubled member running parallel to the regular joists along each long side of the opening, supporting the header ends
HeaderThe member running perpendicular to the regular joists at each end of the opening, carrying the cut joist ends
LandingThe framed platform at the top or bottom of the stair run, built to the approved perimeter, support, and elevation
HeadroomThe vertical clear distance measured from the nose of each tread, or the stair-plan reference point, to the nearest overhead framing or finish surface

Reference and Framing Record

Before marking the opening, record the controlling documents and reference lines directly on the stair-opening framing record:

Structure/level ID: ______     Stair plan set and revision date: ______     Controlling wall/floor reference: ______     Floor-to-floor height at this location: ______

Date started: ____________     Builder name: ____________

Prerequisites

Common Field Fundamentals

Framing a stair opening interrupts a completed structural system rather than building a new one from unbroken bearing. Every step in this project follows the same discipline used for any interruption of completed structure: verify the design and approval, support before cutting, expose only what is needed, connect the new load path before releasing temporary support, and inspect before concealment.

LayoutOpening perimeter, header locations, and landing position marked from controlling references
Support and cuttingTemporary shoring, subfloor removal, and controlled joist cutting
Headers and trimmersDoubled trimmers installed first, then headers set with specified hangers
LandingPerimeter, supports, posts, beams, and joists framed to the plan

Load Path Through the Opening

Every joist cut for the opening transfers its load into a header instead of directly to its original bearing point. Each header transfers that combined load into the trimmer joists at its ends. Each trimmer transfers the combined load of its header reactions, plus its own tributary floor load, to its own bearing point. This project does not proceed past joist cutting until the doubled trimmer that will carry that new load is installed and fastered at both ends.

FR-097 – FR-102

Structural Layout / Floor Framing / Landing Construction

Stair Opening and Landing Framing

Difficulty: Intermediate

Estimated Time: 5–8 hours

Estimated Cost: Set by the approved stair plan's material list

Finished Work: A framed, headed, trimmed, guarded stair opening and structural landing, documented and inspected

A. Finished-Project Specification

Scope: one completed stair-opening layout, floor-opening framing, header installation, and landing frame, built to the dimensions, headers, trimmers, connectors, and landing schedule stated on the approved stair plan, with every open edge guarded and the completed work documented on a signed stair-opening framing record.

B. Required Documentation Schedule

DocumentSourceConfirmation Required
Approved stair planDesign professional / plan setCurrent revision on site, including opening size, headroom, and landing size
Header and trimmer scheduleDesign professional / plan setHeader size, ply count, bearing, and hanger schedule confirmed
Landing framing detailDesign professional / plan setPerimeter, supports, posts, beams, joists, and elevation confirmed
Existing floor framing planDesign professional / Projects 3–4 recordsJoist direction, spacing, and bearing at the opening location confirmed
Temporary support planDesign professional / qualified supervisionShoring locations, materials, and release conditions confirmed
Permit and inspection requirementsAuthority having jurisdictionFraming and structural inspection scheduled before concealment

C. Layout and Framing Materials

  • Trimmer and header stock: species, grade, size, and ply count specified by the approved stair plan; no substitution without a documented revision.
  • Hangers and connectors: the exact products specified by the header and trimmer schedule, with listed fasteners only.
  • Landing framing materials: perimeter, support, post, beam, and joist stock specified by the landing framing detail.
  • Temporary support materials: shoring posts, beams, and cribbing sufficient for the load and duration specified by the temporary support plan.
  • Guards and covers: sufficient material to guard every open edge created during this project.
  • Documentation: one stair-opening framing record per opening and landing.

D. Acceptance Standards

CheckStandard
Opening width and lengthMatches the rough framing limits calculated from the approved finished-opening dimension and finish-material allowance, within the tolerance stated on the approved plan
Opening squareDiagonals of the opening differ by no more than the tolerance stated on the approved plan
Header bearing and connectionFull bearing on each trimmer with the specified hanger, fastener pattern, and seating condition
Trimmer installationFully fastened along its full length to the adjacent joist before any supported joist is cut
Landing elevation and supportMatches the plan-specified elevation and bearing, level within the tolerance stated on the plan
Headroom clearanceMeets or exceeds the minimum stated on the approved plan and adopted code, measured from the plan reference point
Edge protectionEvery open edge guarded or covered whenever the area is unattended
Documentation completenessEvery required dimension, structural member, connector, and inspection result recorded before the record is signed

E. Layout and Verification (Steps 1–5)

  1. Review the approved stair plan, floor-to-floor height, opening size, stair width, headroom, landing size, joist direction, headers, trimmers, posts, and guard requirements. Confirm the plan revision date against the project's document-control log.
  2. Confirm that the stair geometry and structural opening have been designed or approved before removing or cutting floor framing. Do not proceed to layout without this confirmation recorded on the stair-opening framing record.
  3. Identify the opening location on the subfloor from controlling wall and floor references. Use the reference corners and baseline established in Project 1.
  4. Mark the finished opening perimeter, rough framing limits, header locations, and landing position. Calculate rough framing limits from the finished-opening dimension plus the plan-specified finish-material allowance and mark both the finished and rough lines, labeled separately.
  5. Verify that the opening does not conflict with beams, bearing walls, utilities, ducts, or other structural components. Cross-check the marked opening against the floor framing plan and any installed utility locations; log and refer any conflict before proceeding.

F. Temporary Support and Controlled Cutting (Steps 6–10)

  1. Install temporary support below affected floor members where required by the approved sequence. Position shoring posts and beams per the temporary support plan and verify they are stable before proceeding.
  2. Remove only the subfloor area required to expose the affected joists. Cut along the marked rough framing limits using controlled, supported cutting methods.
  3. Identify and mark joists to remain, joists to be cut, doubled trimmers, and headers. Mark "cut" and "keep" directly on each joist top before removing any additional material.
  4. Install doubled trimmer joists or other side supports before cutting interrupted joists. Fasten each trimmer to its adjacent joist along its full length per the approved schedule before any joist scheduled for removal is cut.
  5. Cut joists only at the approved locations using controlled support. Confirm temporary support is carrying the load at each cut location immediately before cutting.

G. Header Installation and Landing Framing (Steps 11–14)

  1. Install opening headers with the specified hangers, bearing, or connections. Seat each header fully on its trimmer bearing and install the specified hanger before releasing any temporary support at that location.
  2. Connect cut joists to headers using approved hangers and fasteners. Confirm each cut joist end is fully seated in its hanger with the complete specified fastener pattern.
  3. Frame the landing perimeter, supports, posts, beams, and joists according to the plan. Follow the landing framing detail for member size, spacing, and connection.
  4. Install landing subfloor or temporary decking only after framing inspection permits it. Do not install any walking surface across the landing before Section H's verification is complete.

H. Verification, Guarding, and Documentation (Steps 15–20)

  1. Verify opening width, length, square, floor elevation, landing elevation, and clearances. Compare every measurement against the Acceptance Standards table.
  2. Check the continuous load path from headers and trimmers to supports below. Confirm each trimmer's bearing point and each header's hanger connection matches the approved schedule with no gaps or missed fasteners.
  3. Install temporary guards and covers around all open edges. Guard every edge of the opening and landing before leaving the area unattended.
  4. Verify required headroom, approach, landing dimensions, and future finish allowances. Measure headroom from the plan-specified reference point and compare against the plan minimum.
  5. Correct authorized framing or alignment deficiencies. Re-verify any corrected dimension, connection, or bearing condition before continuing.
  6. Record opening dimensions, structural members, connectors, temporary support, and inspection results. Complete every entry on the stair-opening framing record before signing.

Common Verification Inspection

Inspect the completed opening and landing using the same checks regardless of which level or stair run it serves.

Complete the Stair-Opening Framing Record in the Inspection Checklist section below before beginning Project 18.

Image Placeholder
Recommended image: the finished opening perimeter and rough framing limits chalk-lined on the subfloor, labeled separately.
Image Placeholder
Recommended image: temporary shoring posts and beams installed below the affected joists before any cutting begins.
Image Placeholder
Recommended image: a doubled trimmer joist fully fastened to its adjacent joist before an interrupted joist is cut.
Image Placeholder
Recommended image: a header seated in its hanger at the trimmer, with the complete specified fastener pattern installed.
Image Placeholder
Recommended image: the completed landing frame with perimeter, supports, and joists installed to the plan-specified elevation.
Image Placeholder
Recommended image: temporary guards and covers installed around every open edge of the opening and landing.

Failure Points and Troubleshooting

Cleanup

This project ends with a framed, guarded stair opening and landing and a signed framing record, not with stringers, treads, or a finished walking surface installed.

Field Terms

Finished Opening
The stair opening dimension shown on the approved plan after all framing and finish material is installed.
Rough Framing Limit
The larger framing-stage dimension that, with finish material added, produces the finished opening.
Trimmer Joist
The doubled member along each long side of the opening that supports the header ends.
Header
The member at each end of the opening that carries the cut joist ends and bears on the trimmers.
Landing
The framed platform at the top or bottom of a stair run, built to the approved perimeter, support, and elevation.
Headroom
The vertical clear distance from the plan-specified reference point to the nearest overhead framing or finish surface.
Temporary Support
Shoring installed below affected floor members before cutting, sized and placed per the approved support plan.
Load Path
The continuous route by which a cut joist's load transfers through a header, into a trimmer, and into its bearing point.
Stair-Opening Framing Record
The signed document confirming dimensions, structural members, connectors, temporary support, and inspection results.
Stop-Work Condition
A defined condition, such as an unapproved opening conflict or missing bearing, that requires work to stop until direction is obtained.

Skill Check

  1. Why must the rough framing limits be calculated from the finished-opening dimension rather than marked directly at finished size?
  2. What must be confirmed and installed before any joist scheduled for removal is cut?
  3. Why must a doubled trimmer be fully fastened before the joist it will support is cut?
  4. What load does a header transfer, and where does that load go next?
  5. What must the learner do if the marked opening conflicts with a beam, bearing wall, or utility?
  6. From what reference point is headroom measured, and why must that reference be defined before measuring?
  7. What conditions require temporary guards or covers to remain installed at the end of a work session?
  8. What must be true of the stair-opening framing record before material is staged for Project 18?
  9. Why is a hand-pressure check of the landing frame not a substitute for the structural inspection required in Section H?
  10. What must the learner do if a landing support settles or shows movement after installation?

Competency Rubric

CompetencyIndependent Pass StandardNot DemonstratedWith AssistanceIndependently
FR-097Lays out the stair opening on the subfloor correctly from controlling wall and floor references and the approved stair plan
FR-098Frames the floor opening with correctly sequenced temporary support, controlled joist removal, and fully fastened doubled trimmers
FR-099Installs opening headers with the specified hangers, full bearing, and complete connections
FR-100Builds the landing frame to the approved perimeter, support, post, beam, joist, and elevation specifications
FR-101Verifies opening and landing clearances, headroom, and dimensions correctly against the approved plan and adopted code
FR-102Inspects stair-framing support and documents the completed opening, landing, and load path completely on the signed framing record

Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.

Inspection Checklist — Stair-Opening Framing Record

CheckPlan Value / RequirementField ValueWithin Tolerance (Y/N)Correction (if any)
Stair plan and revision confirmedCurrent revision on site
Opening width (rough)
Opening length (rough)
Opening diagonal A
Opening diagonal B
Trimmer fastening (per schedule)Complete before joist cutting
Header bearing and hangerMatches header/trimmer schedule
Landing elevation
Headroom clearanceMeets plan/code minimum
Open-edge guardingInstalled on every open edge

Open discrepancies attached: ____________     Responsible authority for each: ____________

Framing and structural inspection completed: ______ (Pass/Fail)     Date: ____________     Builder name: ____________

Performance Check

With layout, temporary support, controlled joist cutting, trimmer and header installation, landing framing, and verification complete, review the finished opening and landing against the Acceptance Standards table and confirm opening dimensions and square are within the approved plan tolerance, every header and trimmer shows full bearing and complete fastening, the landing is built to the approved elevation and support, headroom meets or exceeds the plan and code minimum, and every open edge is guarded. Complete and sign the stair-opening framing record, and complete the required framing and structural inspection, before material is staged for Project 18. If a discrepancy remains open, identify the responsible authority and required decision before proceeding.

Project Closeout

You have completed the seventeenth project in the residential framing sequence: framing a basic stair opening and landing. This project required you to lay out the opening from controlling references and the approved stair plan (FR-097), frame the floor opening with correctly sequenced temporary support, controlled cutting, and doubled trimmers (FR-098), install headers with the specified hangers and connections (FR-099), build the landing frame to the approved plan (FR-100), verify opening and landing clearances, headroom, and dimensions (FR-101), and inspect and document the completed structural support (FR-102).

You now have a framed, supported, guarded stair opening and landing, verified against the approved plan and ready to receive the stair stringers. That opening and landing carry directly into the next project: calculating rise and run and building the matched stringers that will bear on the framing you just completed.

Keep every open edge of the opening and landing guarded or covered until the stringers are installed in Project 18.