Residential Construction and Building Trades Library
|
Book 04 — Residential Framing: Floors, Walls, Roof Framing, Stairs, and Structural Repairs

Project 18

Build and Install Basic Stair Stringers

Calculate rise and run from the approved stair dimensions, lay out and cut a matched pattern stringer, trace and cut the remaining stringers, and install a supported, aligned, level set of stringers in the stair opening framed in Project 17.

Field Cue System

These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework, disputes, or hazards.

△

Safety Cue

Task-specific safety guidance for ordinary work hazards.

✋

Critical Safety Cue

Serious injury or major structural consequence is possible.

⛑

Field Safety Cue

Practical work-area safety: footing, debris, standing water, and access.

▤

Code Alert

Local requirements vary. Verify permit, inspection, and jurisdictional rules.

▧

Manufacturer Cue

Follow product-specific instructions for anchors, hold-downs, and connectors.

▱

Measurement Cue

Clearance, layout, spacing, and reference-point guidance.

Job Overview

This project qualifies you to calculate stair rise and run from the approved stair dimensions, lay out and cut a matched pattern stringer, trace and cut the remaining stringers from that pattern, and install a level, supported, aligned set of stringers in the floor opening and landing framed in Project 17. The finished work product is a matched set of installed stair stringers, temporarily guarded, with a completed stair calculation record and inspection results.

You will measure the actual floor-to-floor or floor-to-landing elevation difference, determine the approved number of risers and uniform unit rise, determine the approved unit run and total run, account for tread thickness and top and bottom bearing conditions, lay out and cut one pattern stringer, verify it at the opening, trace and cut the remaining stringers from that verified pattern, install top and bottom bearing supports, set and secure all stringers at the approved spacing, and verify rise uniformity, run uniformity, headroom, and support before the stair is used.

This project follows directly from Project 17, which framed and guarded the stair opening and landing. It uses the opening dimensions, landing elevation, and structural supports established there, and it produces the stringer set that carries treads, risers, and guards in later finish work.

Skills You Will Demonstrate

  • FR-103 — Calculate total rise, number of risers, unit rise, unit run, and total run from the approved stair dimensions and field measurements.
  • FR-104 — Lay out a pattern stringer using a framing square and stair gauges, marking plumb cuts, tread and riser notches, and the bottom cut from defined references.
  • FR-105 — Cut the pattern stringer and the matching stringers without overcutting inside corners, and finish inside corners using the approved hand-tool method.
  • FR-106 — Install top and bottom bearing supports and set stringers at the approved spacing, fully supported and aligned.
  • FR-107 — Verify every tread position for level and every riser position for uniformity across the installed stringer set.
  • FR-108 — Verify total stair width, rise uniformity, run uniformity, headroom, landing clearance, and connector installation, and document the results.

Where This Skill Fits

The stair calculation performed in this project controls every tread and riser a user will step on for the life of the structure. An error of a fraction of an inch in unit rise, repeated across a full flight, becomes a trip hazard that is difficult to detect by eye and expensive to correct once treads and finish stringers are installed. This project treats the calculation, the pattern stringer, and the verification of that pattern before it is traced onto the remaining stock as three separate, sequential checkpoints, because an error caught at the pattern stage costs one board; the same error caught after all stringers are cut costs the full stringer set.

The framing square and stair-gauge layout method taught here is the same method referenced anywhere else in this book that a site-built stair or stair-like component must be laid out from a calculated rise and run.

Scope and Intended Use

This project covers:

  • calculating total rise, riser count, unit rise, unit run, and total run for a basic straight residential stair from the approved stair dimensions and field-measured elevations
  • laying out, cutting, and verifying one pattern stringer
  • tracing and cutting matching stringers from the verified pattern
  • installing top and bottom bearing supports and setting the stringer set at the approved spacing
  • verifying tread level, riser uniformity, headroom, and landing clearance across the installed set

This project does not authorize the learner to:

  • select total rise, riser count, unit rise, unit run, stringer size, species, or spacing without the approved stair dimensions and project specification; these values come from the plans, adopted code provisions applicable to the project, or a qualified designer, not from this project's general description
  • trace and cut matching stringers from a pattern stringer that has not been test-fitted and verified at the opening
  • permit use of the stair by anyone before required temporary guards are installed and the stair has passed inspection
  • alter the stair opening, landing, or headers framed in Project 17 to accommodate a stringer layout error

Any discrepancy between the field-measured elevation, the approved stair dimensions, and the calculated rise and run must be resolved before cutting the pattern stringer.

Reference Conventions

Establish these references before any layout begins, and do not change them once the pattern stringer has been marked.

TermDefinition
Total riseThe exact field-measured vertical distance from the lower finished surface to the upper finished surface the stair connects, measured from the same reference surfaces used by the approved stair design
Unit riseThe height of one riser, calculated by dividing the total rise by the approved number of risers
Unit runThe horizontal depth of one tread, taken from the approved stair specification
Total runThe unit run multiplied by the number of treads, measured horizontally from the first riser to the last riser
Pattern stringerThe single stringer laid out, cut, and verified first, used as the tracing reference for every matching stringer
Throat depthThe remaining solid width of the stringer measured from the inside corner of a tread/riser notch to the stringer's opposite edge

Stair Calculation Record

Complete and record this calculation before marking the pattern stringer:

Field-measured total rise: ______     Approved number of risers: ______     Calculated unit rise: ______

Approved unit run: ______     Number of treads: ______     Calculated total run: ______

Tread thickness/finish flooring allowance: ______     Top connection detail: ______     Bottom bearing detail: ______

Prerequisites

Common Field Fundamentals

Every stringer layout in this project follows the same sequence: measure the actual elevation, calculate rise and run, lay out and verify one pattern, then trace and cut matching stringers from that verified pattern. Skipping the verification step and cutting all stringers directly from a calculated but untested pattern is the most common cause of a stair that must be substantially rebuilt.

CalculationTotal rise, riser count, unit rise, unit run, total run recorded before cutting
Pattern layoutOne stringer marked, cut, and test-fitted at the opening
Matching stringersTraced from the verified pattern and compared for consistency
InstallationTop and bottom bearing set, spacing verified, stringers secured

Rise, Run, and the Pattern-Verification Sequence

Total rise is measured, not assumed, at the exact location the stair will be built, because floor and landing elevations vary from the plan by ordinary construction tolerance. The number of risers is fixed by the approved stair specification; dividing the field-measured total rise by that fixed riser count produces the unit rise actually used for layout. A pattern stringer that checks out on paper but has not been set in the opening can still fail on headroom, top connection, or landing clearance — conditions the calculation alone does not confirm.

FR-103 – FR-108

Calculation / Layout / Fabrication / Installation Qualification

Basic Stair Stringer Layout, Fabrication, and Installation

Difficulty: Intermediate

Estimated Time: 5–8 hours

Estimated Cost: $120–$380

Finished Work: A matched, installed set of stair stringers, temporarily guarded, with a completed calculation record and inspection results

A. Finished-Project Specification

Scope: one complete stringer set for the stair opening and landing framed in Project 17, consisting of the approved number of stringers laid out from a single verified pattern, cut, installed on approved top and bottom bearing supports, and set at the approved spacing across the full stair width.

B. Component Schedule

ComponentQuantityMaterialFinished SizePreparation
Stair stringersPer approved specificationPer approved specificationPer calculated rise/run and approved stringer depthLaid out from verified pattern, cut, inside corners hand-finished
Top bearing supportPer approved detailPer approved detailPer approved detailInstalled at header before stringers are set
Bottom bearing supportPer approved detailPer approved detailPer approved detailInstalled at lower landing or floor before stringers are set
Temporary treadsPer approved sequencePer project specificationPer stringer widthInstalled only if the approved sequence permits temporary use before finish treads

C. Fastener and Hardware Schedule

Install top hangers, ledgers, bearing blocks, posts, and stringer-to-header or stringer-to-landing connectors exactly as specified in the approved stair and connector detail. Do not substitute fastener type, diameter, length, or spacing for a listed connector's required fasteners. Where the approved detail does not specify a value, obtain it from the design professional or manufacturer instructions before installing that connection.

D. Acceptance Standards

CheckStandard
Riser uniformityEvery riser height, including top and bottom risers, within the tolerance stated on the approved stair specification
Tread uniformityEvery tread run within the tolerance stated on the approved stair specification
Throat depthRemaining stringer width at every notch meets or exceeds the minimum stated in the approved specification
Stringer matchingAll matching stringers agree with the verified pattern within the tolerance stated on the approved specification
Top and bottom bearingFull bearing contact at both ends, matching the approved connection detail
Headroom and landing clearanceMeets the minimum stated in the approved stair specification
Stringer spacingMatches the approved specification across the full stair width, measured at top, middle, and bottom

E. Calculation (Steps 1–6)

  1. Review the approved stair dimensions, total rise, available run, stair width, tread and riser requirements, landing elevations, headroom, stringer material, support, and connection details. Confirm the document revision against the project's document-control log.
  2. Measure the actual finished-floor or framing elevation difference from the same reference surfaces used by the design. Record the field-measured total rise on the stair calculation record.
  3. Determine the approved number of risers and uniform unit rise. Divide the field-measured total rise by the approved number of risers and record the result.
  4. Determine the approved unit run and total stair run. Multiply the approved unit run by the number of treads and record the calculated total run.
  5. Account for tread thickness, finished flooring, top connection, bottom bearing, and landing conditions. Adjust the top and bottom riser layout on the calculation record to reflect these conditions before marking any stock.
  6. Record the complete stair calculation before marking material. Confirm every entry on the stair calculation record is complete and consistent with the approved specification.

F. Pattern Stringer Layout and Cutting (Steps 7–16)

  1. Select straight, sound stringer stock of the specified size, grade, species, and treatment. Sight each piece for crown, bow, and twist using the straightedge before selection.
  2. Reject stock with defects in the cut zones or conditions prohibited by the project specification. Set aside and label rejected stock; do not use it for the pattern or matching stringers.
  3. Mark one pattern stringer using a framing square and approved stair gauges or layout method. Set the stair gauges to the calculated unit rise and unit run before marking the first line.
  4. Mark the top plumb cut, tread and riser notches, bottom cut, and required landing adjustments. Mark every tread and riser line from the same gauge setting without readjusting the gauges mid-layout.
  5. Verify remaining throat depth and all layout dimensions before cutting. Measure the throat depth at the narrowest notch and compare it with the minimum stated in the approved specification.
  6. Cut the pattern stringer without overcutting inside corners. Stop each circular-saw cut at the marked inside-corner point.
  7. Finish inside corners using the approved hand-tool method. Complete each inside corner with a handsaw or jigsaw so no overcut extends past the marked lines.
  8. Test-fit the pattern stringer at the opening. Set the pattern stringer in position against the header and lower bearing surface without fastening it.
  9. Verify top connection, bottom bearing, total rise, run, headroom, and landing relationship. Measure headroom from the nose line of each tread position to the framing above, and compare against the minimum in the approved specification.
  10. Correct the pattern before tracing additional stringers. If a discrepancy is found, correct the pattern stringer or obtain design direction before proceeding to Section G.

G. Matching Stringers and Installation (Steps 17–23)

  1. Trace and cut the required matching stringers from the approved pattern. Clamp the verified pattern to each piece of matching stock and trace every line before cutting.
  2. Compare all stringers for matched rise, run, top, and bottom geometry. Lay all stringers together on a flat surface and check tread and riser line alignment across the set.
  3. Install top hangers, ledgers, bearing blocks, posts, or other specified supports. Install these supports at the header and lower landing before setting any stringer.
  4. Set and temporarily secure the outside stringers. Position the outside stringers at the approved stair-width dimension and temporarily fasten each end.
  5. Install intermediate stringers at the approved spacing. Use the chalk line and tape measure to confirm spacing before permanently fastening any stringer.
  6. Verify stringers remain parallel, aligned, fully supported, and consistently spaced. Check spacing at the top, middle, and bottom of the stringer set.
  7. Install temporary or permanent treads only as permitted by the project sequence. Confirm the approved sequence before placing any tread material on the installed stringers.

H. Verification and Documentation (Steps 24–27)

  1. Check every tread position for level and every riser position for uniformity. Record each measurement on the stair calculation record.
  2. Verify total stair width, rise uniformity, run uniformity, headroom, landing clearance, support, and connector installation. Compare every result against the Acceptance Standards table in Section D.
  3. Install required temporary guards and prohibit use until the stair has passed inspection. Confirm guards are in place at every open edge before leaving the installed stringer set unattended.
  4. Record calculations, pattern dimensions, final measurements, connections, and inspection results. Complete every entry on the stair calculation record and attach it to the project's permanent documentation.

Common Verification Inspection

Inspect the completed stringer set using the same checks regardless of stair width or stringer count.

Complete the Inspection Checklist below before treads, risers, or finish stringers are installed.

Image Placeholder
Recommended image: a framing square with stair gauges set at the calculated unit rise and unit run on a pattern stringer.
Image Placeholder
Recommended image: a circular saw cut stopped at the marked inside-corner point of a tread/riser notch.
Image Placeholder
Recommended image: the verified pattern stringer test-fitted at the stair opening against the header and lower bearing surface.
Image Placeholder
Recommended image: matching stringer stock being traced from the clamped pattern stringer.
Image Placeholder
Recommended image: an installed stringer set at the approved spacing, with a level checking a tread position.
Image Placeholder
Recommended image: a completed stair calculation record with total rise, riser count, unit rise, unit run, and total run entered.

Failure Points and Troubleshooting

Cleanup

This project ends with an installed, guarded stringer set and a completed calculation record, not with finish treads, risers, or guards installed.

Field Terms

Total Rise
The field-measured vertical distance the stair connects, from the same reference surfaces used by the approved design.
Unit Rise
The height of one riser, calculated by dividing total rise by the approved riser count.
Unit Run
The horizontal depth of one tread, taken from the approved stair specification.
Total Run
The unit run multiplied by the number of treads.
Pattern Stringer
The single stringer laid out, cut, and verified first, used as the tracing reference for the remaining stringers.
Throat Depth
The remaining solid width of a stringer at a tread/riser notch.
Stair Gauges
Adjustable fittings clamped to a framing square to hold a consistent unit-rise and unit-run setting during layout.
Plumb Cut
The vertical cut at the top of a stringer that meets the header or upper bearing surface.
Seat Cut
The horizontal cut at the bottom of a stringer that bears on the lower floor or landing surface.
Headroom
The clear vertical distance from a tread's nose line to the framing or finish surface above it.

Skill Check

  1. Why is total rise field-measured rather than taken directly from the plan dimension?
  2. What happens to the unit-rise calculation if the field-measured total rise is not evenly divisible by the approved riser count, and how must that be handled?
  3. Why must the pattern stringer be test-fitted at the opening before it is used to trace matching stringers?
  4. What condition requires the stair-gauge setting to remain unchanged throughout layout of a single stringer?
  5. What must the learner verify at the pattern-stringer test fit besides total rise and run?
  6. Why is a mismatched stringer discarded and re-traced rather than trimmed to match the others?
  7. What three points on the installed stringer set must be checked for consistent spacing?
  8. Why must tread thickness and finish-flooring allowances be included in the calculation before the pattern is marked, not after?
  9. What must be true before treads, risers, or finish guards are installed on the completed stringer set?
  10. Why does a throat-depth deficiency require a design correction rather than a field notch adjustment?

Competency Rubric

CompetencyIndependent Pass StandardNot DemonstratedWith AssistanceIndependently
FR-103Calculates total rise, riser count, unit rise, unit run, and total run correctly from the approved dimensions and field measurements
FR-104Lays out a pattern stringer with correct plumb cuts, tread and riser notches, and bottom cut using a framing square and stair gauges
FR-105Cuts the pattern and matching stringers without overcutting inside corners and finishes corners with the approved hand-tool method
FR-106Installs top and bottom bearing supports and sets stringers at the approved spacing, fully supported and aligned
FR-107Verifies every tread position for level and every riser position for uniformity across the installed set
FR-108Verifies stair width, rise/run uniformity, headroom, landing clearance, and connector installation and documents results completely

Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.

Inspection Checklist — Stair Calculation and Stringer Record

CheckPlan Value / RequirementField ValueWithin Tolerance (Y/N)Correction (if any)
Field-measured total rise
Riser count
Calculated unit rise
Approved unit run
Calculated total run
Throat depth (minimum)
Pattern stringer test fitVerified before tracing
Stringer matchingAll stringers match pattern
Top/bottom bearingFull contact per detail
Stringer spacing (top/mid/bottom)
Headroom

Open discrepancies attached: ____________     Responsible authority for each: ____________

Stringer installation declared: ______ (Pass/Fail)     Date: ____________     Builder name: ____________

Performance Check

With the stair calculation complete, the pattern stringer verified, matching stringers traced and cut, bearing supports installed, and the stringer set secured at the approved spacing, review the finished work against the Acceptance Standards table and confirm every riser and tread is uniform within tolerance, throat depth meets the minimum, all stringers match the verified pattern, top and bottom bearing provide full contact, headroom and landing clearance meet the approved minimum, and stringer spacing is consistent at the top, middle, and bottom of the set. Complete the Inspection Checklist before treads, risers, or finish guards are installed. If a discrepancy remains open, identify the responsible authority and required decision before proceeding.

Project Closeout

You have completed the eighteenth project in the residential framing sequence: building and installing basic stair stringers. This project required you to calculate total rise, riser count, unit rise, unit run, and total run from the approved dimensions and field measurements (FR-103), lay out a pattern stringer with correct plumb cuts, notches, and bottom cut (FR-104), cut the pattern and matching stringers without overcutting inside corners (FR-105), install bearing supports and set the stringers at the approved spacing (FR-106), verify tread level and riser uniformity across the installed set (FR-107), and verify and document stair width, rise/run uniformity, headroom, landing clearance, and connector installation (FR-108).

You now have an installed, guarded stringer set ready for treads, risers, guards, and finish work. The identification, planning, and structural-repair skills in the next project apply to a different category of framing work: diagnosing and correcting damaged residential framing under an approved repair detail.

Do not permit use of this stair by anyone until required temporary guards remain installed and the stair has passed inspection.