Prepare a de-energized metal box or training enclosure with correctly selected knockouts and listed cable connectors for the approved wiring method, so that every cable entering the enclosure is sized to its opening, seated in a connector listed for the exact cable and enclosure condition, and supported without crushing the sheath or losing grounding continuity.

Field Cue System

These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before a knockout is enlarged, a connector is mismatched, or a cable is crushed.

△

Safety Cue

Task-specific safety guidance for ordinary work hazards.

✋

Critical Safety Cue

Serious injury, shock, electrocution, or arc flash is possible.

⛑

Field Safety Cue

Practical work-area safety: lighting, footing, access, and housekeeping.

▤

Code Alert

Local requirements vary. Verify permit, inspection, and jurisdictional rules.

▧

Manufacturer Cue

Follow product-specific instructions for connectors, punches, and enclosures.

▱

Measurement Cue

Reference-point, sizing, and verification guidance.

Job Overview

This project qualifies you to remove correctly sized knockouts from a metal enclosure and install listed cable connectors for the approved wiring method. The finished work product is one de-energized enclosure with each intended knockout removed cleanly, deburred, and fitted with a connector listed for the exact cable, raceway, conductor material, size range, and enclosure condition; each cable seated and supported at the connector without a nicked conductor or a crushed sheath; and every unused opening closed with a listed closure.

You will review the enclosure type, wiring method, and connector listing; verify the enclosure is disconnected from all power sources; plan cable-entry locations that preserve bending space, box fill, grounding hardware, and cover installation; select and remove the correct knockout for each connector; deburr the opening; install and tighten each connector; prepare and insert the cable; secure the cable outside the box; close unused openings; and inspect the finished assembly.

This project builds directly on the box installation skills from Chapters 3 and 4 and prepares the enclosure for the NM cable routing taught in Chapter 6 and the splicing and grounding work taught in Chapters 7 and 8. A correctly sized knockout and a correctly seated connector are what keep a cable's sheath and grounding path intact from the moment it enters the box through every later termination.

Skills You Will Demonstrate

  • EL-025 — Remove box knockouts of the correct size using the approved punch, knockout tool, or controlled hand-tool procedure without enlarging or deforming the opening.
  • EL-026 — Select cable connectors listed for the exact cable, raceway, conductor material, size range, and enclosure condition.
  • EL-027 — Install connectors through the knockout and tighten the locknut, bushing, or threaded body using the approved tool and seating method.
  • EL-028 — Protect cable sheathing while preparing and inserting the cable end through the connector.
  • EL-029 — Secure cables at boxes with the required cable support outside the box at the code- and product-controlled location.
  • EL-030 — Inspect connector fit, seating, sheath protection, cable support, and grounding continuity, and correct any distorted knockout, damaged connector, or crushed cable.

Where This Skill Fits

Chapter 3 and Chapter 4 installed and supported the box itself. This project prepares that box to receive cable: every knockout removed here is a permanent opening in the enclosure, and every connector installed here is the only protection the cable sheath has as it passes through the metal edge. Chapter 6 assumes an enclosure already fitted with correctly sized, correctly seated connectors before any cable is pulled through framing. Chapter 8 assumes the metal connectors and raceway fittings installed here provide bonding continuity as part of the equipment-grounding path.

An oversized or torn-out knockout cannot be restored to a listed condition; it must be treated as a defect and corrected before proceeding, which is why this chapter separates knockout removal from connector installation as distinct, inspected steps.

Scope and Intended Use

This project covers:

  • reviewing the enclosure type, wiring method, cable or raceway type, conductor count, connector listing, environmental rating, and grounding requirement
  • verifying the enclosure is disconnected from all power sources before any knockout or connector work begins
  • planning cable-entry locations that preserve bending space, box fill, grounding hardware, device clearance, and cover installation
  • selecting and removing the correct knockout size for each listed connector without enlarging or deforming the opening
  • selecting, installing, and tightening a connector listed for the exact cable, raceway, conductor material, size range, and enclosure condition
  • preparing and inserting the cable end without nicking conductors or removing excessive sheath, then securing the required cable support outside the box
  • closing unused openings with listed closures and inspecting the finished assembly

This project does not authorize the learner to:

  • work on an enclosure that has not been verified disconnected from all power sources
  • enlarge, redrill, or force open a knockout beyond its manufactured size
  • substitute an unlisted connector, an incompatible conductor-material connector, or a connector not rated for the enclosure's environmental condition
  • leave a cable connector loose, an unused opening uncovered, or a cable unsupported at the required location

Any enclosure, knockout, or connector condition that fails inspection in this chapter must be corrected before the cable routing project in Chapter 6 begins.

Reference Conventions

Establish these references before any knockout is removed, and do not change the defined cable-entry plan mid-project.

TermDefinition
Scored knockoutThe manufactured, pre-sized circular opening in the enclosure wall, defined by a scored line and designed to be removed as a unit
Concentric ringA stepped, nested knockout allowing selection of more than one connector size at a single location
Listed connectorA cable or raceway connector identified by its listing for the exact cable type, conductor material, size range, and enclosure environmental condition
Locknut or bushingThe threaded component tightened against the inside or outside of the enclosure wall to seat and secure the connector
Cable support pointThe location outside the box, at the code- and product-controlled distance, where the cable is stapled or otherwise secured
Closure plugA listed device installed in an unused knockout opening to restore the enclosure's rated closure

Enclosure and Connector Record

Before removing any knockout, record the enclosure and planned connectors directly on the Knockout and Connector Verification Worksheet:

Enclosure type and location: ______     Wiring method: ______     Number of planned cable entries: ______

Enclosure verified disconnected: ______ (Yes/No)     Connector types and sizes planned: ______     Date started: ____________     Builder name: ____________

Prerequisites

Common Field Fundamentals

A knockout and its connector are a matched pair: the connector is listed for a specific knockout size, and a connector installed in the wrong size opening cannot seat, tighten, or protect the cable sheath as intended. Confirm the connector before removing the knockout, not after.

Enclosure reviewWiring method, cable type, conductor count, and connector listing confirmed before any knockout is touched
De-energized verificationEnclosure confirmed disconnected from all power sources before work begins
Entry planningCable-entry locations planned to preserve bending space, box fill, grounding hardware, and cover clearance
Knockout removalCorrect size selected and removed cleanly without enlarging or deforming the opening
Connector selectionListed for the exact cable, raceway, conductor material, size range, and enclosure condition
Connector seatingLocknut, bushing, or threaded body installed and tightened by the approved method
Cable preparation and supportSheath protected through the connector and cable secured at the required distance outside the box
Closure and inspectionUnused openings closed with listed plugs; finished assembly inspected before concealment

Knockout Sizing and Connector Compatibility

Every knockout removed in this chapter is selected to match one specific listed connector. Concentric or eccentric knockouts allow more than one size at a single location; remove only the ring that matches the intended connector, working from the innermost ring outward if a smaller size is later found to be incorrect. A connector must never be forced into an opening larger than its listed size, and a knockout must never be enlarged by filing, drilling, or cutting to fit an oversized connector.

EL-025 – EL-030

Enclosure Preparation / Knockout Removal / Cable Connector Installation Qualification

Make Knockouts and Install Cable Connectors

Difficulty: Beginner to Intermediate

Estimated Time: 2–3 hours

Estimated Cost: $15–$45

Finished Work: One de-energized enclosure with correctly sized knockouts removed, listed connectors installed and tightened, cable sheath protected and supported, and unused openings closed

A. Finished-Project Specification

Quantity: one metal box or training enclosure with each intended knockout removed at the correct size, fitted with a connector listed for the exact cable, raceway, conductor material, size range, and enclosure condition, tightened by the approved method, with cable sheath protected through the connector, cable secured at the required support point outside the box, and all unused openings closed with listed closures.

B. Component Schedule

ComponentQuantityMaterialFinished SizePreparation
Metal enclosure1Listed metal box or training enclosurePer approved planVerified disconnected from all power sources
Knockout opening1 per cable entryManufactured scored knockout in enclosure wallMatched to listed connector sizeRemoved cleanly and deburred
Cable connector1 per cable entryListed for cable type, conductor material, and enclosure conditionMatched to knockout and cable diameterDisassembled per manufacturer instructions before insertion
Locknut or bushing1 per connector (or as supplied)Connector manufacturer's listed componentMatched to connector bodyTightened by approved method
Closure plug1 per unused openingListed for the enclosure knockout sizeMatched to unused knockout sizeSeated and secured
Cable support (staple or clamp)As required by cable count and routeListed for the cable typeMatched to cable diameterInstalled outside the box at the required distance

C. Material Takeoff

  • Enclosure: one metal box or training enclosure with concentric or single-size knockouts sized for the planned connectors.
  • Connectors: one listed cable connector per planned cable entry, sized and typed to the cable and enclosure condition.
  • Closures: one listed closure plug per unused knockout opening.
  • Cable support hardware: listed staples or cable clamps sufficient for the required support point at each cable entry.
  • Cable or raceway samples: lengths of NM cable or raceway sufficient to demonstrate preparation and insertion at each connector.

D. Reference Conventions

Use the reference terms defined in the Reference Conventions table above: scored knockout, concentric ring, listed connector, locknut or bushing, cable support point, and closure plug. Do not remove a knockout or install a connector without first confirming these terms against the specific enclosure and connector in hand.

E. Acceptance Standards

CheckStandard
Knockout removalCorrect size removed cleanly, without tearing past the scored line or enlarging the opening
DeburringOpening free of sharp edges without enlargement or deformation
Connector selectionListed for the exact cable, raceway, conductor material, size range, and enclosure condition
Connector seatingLocknut, bushing, or threaded body fully tightened by the manufacturer-approved method and tool
Sheath protectionNo nicked conductors or excessive sheath removal; correct sheath insertion length through the connector
Cable withdrawal checkCable cannot be withdrawn from the connector under the approved hand check
Cable supportRequired cable support installed outside the box at the code- and product-controlled location
Closure of unused openingsEvery unused knockout closed with a listed closure plug

F. Enclosure Review and De-Energized Verification

  1. Review the enclosure type, wiring method, cable or raceway type, conductor count, connector listing, environmental rating, and grounding requirement. Record these on the Knockout and Connector Verification Worksheet before proceeding.
  2. Verify that the enclosure is disconnected from all power sources. Apply the Chapter 1 lockout and verified de-energization procedure if the enclosure is or could become part of an energized system.
  3. Inspect the enclosure for sharp edges, corrosion, missing parts, damaged threads, and prohibited openings. Correct or replace the enclosure before proceeding if any defect is found.

G. Cable-Entry Planning

  1. Plan cable-entry locations to preserve conductor bending space, box fill, grounding hardware, device clearance, and cover installation. Mark each planned entry location on the enclosure before removing any knockout.
  2. Select the correct knockout size for each listed connector. Confirm the connector's listed knockout size against the enclosure's knockout markings before proceeding.

H. Knockout Removal

  1. Support the enclosure on a stable work surface. Confirm the enclosure cannot shift or roll during knockout removal.
  2. Remove the selected knockout using the approved punch, knockout tool, or controlled hand-tool procedure. Follow the tool manufacturer's instructions for setup and operation.
  3. Remove only the intended knockout and protect adjacent concentric rings. Stop immediately if an adjacent ring begins to loosen or deform.
  4. Deburr the opening without enlarging or deforming it. Inspect the opening under adequate light for remaining sharp edges before proceeding.

I. Connector Selection and Installation

  1. Select a connector listed for the exact cable, raceway, conductor material, size range, and enclosure condition. Confirm the connector's marked listing against the project's wiring method and environmental requirement.
  2. Disassemble the connector only as required by its instructions. Keep all removed parts identified and available for reassembly.
  3. Insert the connector through the opening in the correct direction. Confirm the connector's orientation matches its listed installation method.
  4. Install and tighten the locknut, bushing, or threaded body using the approved tool and seating method. Confirm full engagement before proceeding.
  5. Orient connector screws or clamps for access. Position the connector so its clamp screws remain reachable after the cable is installed.

J. Cable Preparation and Insertion

  1. Prepare the cable end without nicking conductors or removing excessive sheath. Inspect the prepared end under adequate light before inserting it into the connector.
  2. Insert enough sheath through the connector to satisfy the listed installation and box requirements. Confirm the sheath insertion length against the connector manufacturer's instructions.
  3. Tighten the connector clamp evenly without crushing the cable or damaging insulation. Inspect the sheath immediately after tightening for deformation.
  4. Verify that the cable cannot be withdrawn under the approved hand check. Apply a firm, steady hand-pull without force sufficient to damage the cable.

K. Cable Support and Enclosure Closure

  1. Install the required cable support outside the box at the code- and product-controlled location. Confirm the support point matches the connector and cable manufacturer's stated distance.
  2. Close unused openings with listed closures. Confirm each closure plug is fully seated and cannot be dislodged by hand.

L. Inspection and Correction

  1. Inspect connector seating, locknut engagement, sheath protection, cable support, grounding continuity, and environmental rating. Complete every item on the Acceptance Standards table before concealment.
  2. Replace any distorted knockout, damaged connector, or crushed cable. Do not conceal or proceed past a failed item; correct it and repeat the affected inspection step.

Common Readiness Inspection

Inspect every completed enclosure using the same checks regardless of which cable, raceway, or connector type the project involves.

Complete the Knockout and Connector Verification Worksheet in the Inspection Checklist section below before beginning Project 06.

Image Placeholder
Recommended image: a knockout punch seated on a concentric knockout before removal.
Image Placeholder
Recommended image: a deburred knockout opening compared against an undeburred opening.
Image Placeholder
Recommended image: a listed cable connector partially disassembled, showing locknut, bushing, and body.
Image Placeholder
Recommended image: a cable inserted through a tightened connector with the correct sheath insertion length visible.
Image Placeholder
Recommended image: a completed enclosure with all connectors seated, cable supported, and unused knockouts closed with listed plugs.

Failure Points and Troubleshooting

Cleanup

This project ends with a de-energized, inspected enclosure ready for the cable-routing work of Chapter 6.

Field Terms

Scored Knockout
The manufactured, pre-sized circular opening in the enclosure wall, defined by a scored line and designed to be removed as a unit.
Concentric Ring
A stepped, nested knockout allowing selection of more than one connector size at a single location.
Listed Connector
A cable or raceway connector identified by its listing for the exact cable type, conductor material, size range, and enclosure environmental condition.
Locknut or Bushing
The threaded component tightened against the inside or outside of the enclosure wall to seat and secure the connector.
Cable Support Point
The location outside the box, at the code- and product-controlled distance, where the cable is stapled or otherwise secured.
Closure Plug
A listed device installed in an unused knockout opening to restore the enclosure's rated closure.
Sheath Insertion Length
The measured length of cable sheath required to pass through and remain inside a connector, as controlled by the connector manufacturer's instructions.
Hand-Pull Withdrawal Check
The approved firm, steady hand-pull test used to confirm a cable cannot be withdrawn from an installed connector.

Skill Check

  1. Why must a connector's listed knockout size be confirmed before any knockout is removed, rather than after?
  2. What must be verified about an enclosure before any knockout or connector work begins?
  3. Why can an enlarged or torn-out knockout not be corrected by selecting a larger connector?
  4. What information must a listed cable connector match to be correctly selected for a given installation?
  5. Why must the cable-entry plan be established before any knockout is removed?
  6. What test confirms that a cable is correctly seated in an installed connector?
  7. Why must unused knockout openings be closed with a listed closure plug rather than left open?
  8. What conditions at a metal connector location could prevent confirmed grounding continuity?
  9. Why must a connector be tightened evenly rather than at a single point?
  10. What must the learner do if a knockout tears past its scored line during removal?

Competency Rubric

CompetencyIndependent Pass StandardNot DemonstratedWith AssistanceIndependently
EL-025Removes box knockouts of the correct size using the approved punch, knockout tool, or controlled hand-tool procedure without enlarging or deforming the opening
EL-026Selects cable connectors listed for the exact cable, raceway, conductor material, size range, and enclosure condition
EL-027Installs connectors through the knockout and tightens the locknut, bushing, or threaded body using the approved tool and seating method
EL-028Protects cable sheathing while preparing and inserting the cable end through the connector, without nicking conductors or crushing the sheath
EL-029Secures cables at boxes with the required cable support outside the box at the code- and product-controlled location
EL-030Inspects connector fit, seating, sheath protection, cable support, and grounding continuity, and corrects any distorted knockout, damaged connector, or crushed cable

Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.

Inspection Checklist — Knockout and Connector Verification Worksheet

ItemTarget ConditionResultPass/FailCorrection (if any)
Enclosure de-energizedVerified disconnected from all power sources before work began
Cable-entry planEstablished before any knockout removal, preserving box fill, bending space, and grounding hardware
Knockout removalCorrect size removed cleanly without enlargement or deformation
Connector selectionListed for the exact cable, raceway, conductor material, size range, and enclosure condition
Connector seatingLocknut, bushing, or threaded body fully tightened by approved method
Sheath protectionNo nicked conductors, no excessive sheath removal, correct insertion length
Cable supportInstalled outside the box at the required distance
Closure of unused openingsEvery unused knockout closed with a listed closure plug

Unresolved defects and correction plan: ____________________________________________

Enclosure declared ready: ______ (Pass/Fail)     Date: ____________     Builder name: ____________

Performance Check

With every intended knockout removed, each connector selected, installed, and tightened, cable sheath protected and supported, and unused openings closed, review the finished enclosure against the Acceptance Standards table and confirm each knockout matches its connector without enlargement, each connector is listed for the exact cable, conductor material, and enclosure condition, each connector is fully seated and passes the hand-pull withdrawal check, cable support is installed at the correct location, and every unused opening carries a listed closure plug. Complete the Knockout and Connector Verification Worksheet and correct any failed item before beginning Project 06. If an item fails, identify whether the error occurred in knockout sizing, connector selection, connector seating, cable preparation, or closure before correcting it and re-running the affected check.

Project Closeout

You have completed the fifth project in the residential electrical sequence: making knockouts and installing cable connectors. This project required you to review the enclosure and wiring method, verify the enclosure was disconnected from all power sources, plan cable-entry locations, remove correctly sized knockouts, select and install listed connectors, protect and secure the cable, close unused openings, and inspect the finished assembly (EL-025 through EL-030).

You now have a de-energized enclosure with every cable entry correctly sized, connected, and supported, ready for the NM cable routing taught in the next project. That readiness carries directly into Chapter 6, where the cable prepared and supported at this enclosure will be run and secured through open wood framing to reach it.

Keep the enclosure protected from debris and keep the Knockout and Connector Verification Worksheet with it. You will reference this exact connector seating and cable-support condition when routing cable in Chapter 6 and when splicing and grounding conductors in Chapters 7 and 8.