Chapter 6
Install screed rails, place and screed bedding sand to uniform thickness over an accepted aggregate base, protect the screeded surface from disturbance, and inspect the finished bedding layer before paver placement.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework or hazards.
Task-specific safety guidance for ordinary work hazards.
Serious injury, utility strike, or major damage is possible.
Practical work-area safety: footing, slopes, traffic, and housekeeping.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for materials and components.
Clearance, layout, elevation, and reference-point guidance.
This chapter qualifies you to install and screed one controlled bedding-sand section over an aggregate base accepted under Chapter 5. The finished work product is one screeded bedding-sand layer at the approved thickness and slope, free of ridges, hollows, contamination, footprints, or disturbed areas, and covered with pavers before it is exposed to weather, traffic, or further handling.
You will set and support screed rails on the compacted base, place bedding sand ahead of the rails, pull a screed board along the rails to establish a uniform surface, remove the rails and fill the resulting voids, protect the finished surface from disturbance, and inspect the bedding before paver placement begins.
This chapter depends directly on Chapter 5's accepted aggregate base and feeds directly into Chapter 7's paver installation. Bedding sand is a final setting layer for the pavers above it, not a leveling layer for an uneven base below it. A base that has not been accepted under Chapter 5 must not be screeded in this chapter.
Bedding sand is the layer directly beneath every paver installed in this book, from the straight walkway in Chapter 7 to the capstone patio in Chapter 20. A screeded surface that is uneven, contaminated, or disturbed before pavers are set transfers that defect directly into the finished paver surface, where it cannot be corrected without lifting the pavers and rescreeding.
The discipline of this chapter — never walking, kneeling, wheeling equipment, or stockpiling material on screeded bedding, and covering screeded areas promptly with pavers — is carried forward into every paver-installation chapter that follows. This chapter is where you learn to treat the screeded surface as a finished reference plane, not a work surface.
This chapter covers:
This chapter does not authorize the learner to:
Any base condition that has not been accepted under Chapter 5 must be corrected and reinspected before screeding begins.
Establish these references before rail placement begins, and record them on the bedding work record.
| Term | Definition |
|---|---|
| Bedding elevation | The finished top-of-sand elevation before pavers are placed, set below the finished paver elevation by the paver thickness |
| Screed rail | A straight rail or pipe supported on the accepted base and set to the required bedding elevation, used to guide the screed board |
| Rail void | The channel left in the bedding surface after a screed rail is removed, requiring fill and strike-off before paver placement |
| Screeded surface | The finished, struck-off bedding-sand surface between rails, treated as undisturbed until covered by pavers |
| Compacted or loose thickness | The bedding-sand thickness stated in the approved specification, expressed as either the compacted result or the loose screeded depth, as specified |
Finished project: one screeded bedding-sand section over an accepted aggregate base, at the approved compacted or loose thickness, following the accepted base slope, free of ridges, hollows, contamination, and disturbed areas, and covered promptly with pavers.
Bedding material: ______ (type and gradation) Approved thickness: ______ (compacted / loose, per specification) Screed-rail method: ______ (rail size, spacing, support method)
Base elevation and slope (from Chapter 5 record): ______ Bedding elevation (base elevation plus approved thickness): ______
Acceptance standards: rail slope parallel and matching the approved base slope within the stated tolerance; screeded surface free of ridges, hollows, footprints, wheel tracks, and stockpile marks; rail voids filled and struck flush without overcompaction; bedding thickness confirmed at spot-check locations; screeded area covered with pavers before the approved exposure window expires or protected with an approved covering.
Every bedding-sand installation in this book depends on the same sequence: confirm the base is accepted and ready, set rails to the correct elevation and slope, place and screed sand in a controlled motion, remove rails and fill voids without overcompacting, protect the finished surface from disturbance, and cover it promptly. Learning that sequence here means every paver-installation chapter that follows starts from a bedding layer you can trust.
This chapter requires the installer to halt or repeat work whenever the base or the screeded surface does not meet the conditions this chapter depends on.
Do not set screed rails or place bedding sand over an aggregate base that has not been checked and accepted for elevation, slope, thickness, and stability under Chapter 5. Bedding sand conceals base defects rather than correcting them, and a defect concealed here reappears as settlement or unevenness in the finished paver surface.
Do not walk, kneel, wheel a cart, or stockpile material on screeded bedding sand. Plan material staging and work sequence so that every screeded section is approached only from an unscreeded area or from pavers already installed.
Set screed-rail elevation using the base elevation and slope recorded in the Chapter 5 acceptance record, not by eye against the surrounding grade. Check rail slope and parallel alignment with a line level or laser level before placing any bedding sand.
Use bedding sand at the gradation and moisture condition specified by the approved bedding-material specification. Do not screed sand that is frozen, saturated, contaminated, or visibly segregated, and do not substitute a different material without confirming compatibility with the specified paver and joint system.
Confirm that drains, edge restraints, borders, and other fixed-elevation features are coordinated with the bedding elevation before screeding begins. Screeding over an uncoordinated fixed feature creates a transition defect that cannot be corrected without lifting the affected pavers later.
HC-031 – HC-036
Paver Installation / Bedding Preparation Qualification
Deliverable: one screeded bedding-sand section over an accepted aggregate base, installed using screed rails set to the approved elevation and slope, struck to a uniform surface, with rail voids filled flush, free of ridges, hollows, contamination, footprints, and disturbed areas, and covered with pavers before the approved exposure window expires.
| Record | Required Content | Source |
|---|---|---|
| Base confirmation | Acceptance date, elevation, slope, cleanliness, and dryness at time of screeding | Chapter 5 acceptance record and reconfirmation |
| Rail placement | Rail elevation, support method, slope check, and parallel alignment check | Field measurement |
| Bedding placement | Material source, gradation, moisture condition, and placement method | Field inspection |
| Screeding | Screed-board method, low-area fill, high-area removal | Field work |
| Rail-void repair | Fill material, strike-off method, and confirmation no overcompaction occurred | Field inspection |
| Surface protection | Method used to prevent traffic, wheeled equipment, or stockpiling on the screeded area | Field observation |
| Thickness and surface check | Spot-check thickness results and surface condition findings | Field measurement |
| Coverage | Time and date screeded areas were covered with pavers or protective covering | Field record |
| Check | Standard |
|---|---|
| Base confirmation | The base is accepted under Chapter 5, dry enough to screed, clean, and undisturbed immediately before rail placement |
| Rail elevation and slope | Screed rails are set to the bedding elevation calculated from the accepted base elevation plus the approved bedding thickness, with slope matching the accepted base slope and rails parallel within the stated tolerance |
| Bedding material | Sand is free of visible contamination, segregation, freezing, or saturation at the time of placement |
| Screeded surface | The struck surface is free of ridges, hollows, footprints, wheel tracks, and stockpile marks across the full screeded area |
| Rail-void repair | Rail voids are filled with matching bedding material and struck flush without overcompacting the surrounding bedding |
| Thickness | Spot-check measurements confirm the approved compacted or loose thickness across the screeded area |
| Surface protection | No footprint, wheel track, or stockpile mark is present on the screeded surface at the time of paver coverage |
| Coverage timing | Every screeded area is covered with pavers or an approved protective covering within the approved exposure window |
Review every screeded section using the same checks regardless of area or shape.
Complete the Bedding Sand Inspection Checklist below before beginning Chapter 7.
Probable cause: the screed board lost contact with one or both rails during the pull, or sand was placed unevenly ahead of the board.
Confirmation: sight along the screeded surface and check with a straightedge at several points across the affected section.
Correction: rescreed the affected section completely, adding or removing sand as needed and maintaining continuous rail contact through the full pull.
Reinspection: repeat the surface check for the rescreeded section before covering it with pavers.
Probable cause: a worker or wheeled cart crossed the screeded surface instead of approaching from an unscreeded area or installed pavers.
Confirmation: visually inspect the surface for depressions matching foot or wheel patterns.
Correction: rescreed the full affected section rather than smoothing the mark in place, and revise the work sequence to eliminate the crossing.
Reinspection: repeat the surface check and confirm the revised approach route before continuing.
Probable cause: the void fill was tamped rather than struck flush, compressing the bedding below the surrounding elevation.
Confirmation: check the rail-void line with a straightedge against the adjacent screeded surface.
Correction: remove the compacted fill, add fresh matching bedding material, and strike it flush by hand without tamping.
Reinspection: repeat the thickness and surface check along the full rail-void line.
Probable cause: rail elevation was set incorrectly, or the base elevation used to calculate rail elevation was not the accepted Chapter 5 record.
Confirmation: recheck the rail elevation calculation against the Chapter 5 acceptance record and remeasure rail elevation in the field.
Correction: reset rails to the correct elevation and rescreed the affected section.
Reinspection: repeat the thickness spot-check across the corrected section.
Probable cause: paver placement fell behind the screeding pace, or weather or a work stoppage delayed coverage without an approved protective covering being installed.
Confirmation: compare the screeding completion time against the coverage time recorded on the bedding work record.
Correction: inspect the exposed section for contamination, disturbance, or moisture change; rescreed if any defect is found, or proceed to paver placement if the surface remains undisturbed and within specification.
Reinspection: repeat the full surface and thickness check before paver placement on the affected section.
Probable cause: stockpiled sand was left uncovered during rain, or was stored where it could mix with adjacent soil or base material.
Confirmation: visually inspect the stockpile for color change, clumping, or visible soil mixing.
Correction: do not use the affected material; obtain replacement bedding sand meeting the approved specification.
Reinspection: confirm the replacement material's gradation and moisture condition before placement resumes.
This chapter ends with a covered or protected screeded surface and a completed bedding work record, not an exposed sand layer left for the next work session.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| HC-031 | Sets screed rails to the elevation and slope calculated from the accepted base record, with rails supported, parallel, and checked before sand placement | |||
| HC-032 | Places bedding sand ahead of the rails using material free of segregation, contamination, freezing, or saturation | |||
| HC-033 | Screeds a uniform surface using a controlled screed-board motion, maintaining continuous rail contact and correcting low and high areas during the pull | |||
| HC-034 | Maintains uniform bedding thickness across the screeded area, including rail-void fill struck flush without overcompaction | |||
| HC-035 | Completes the screeded work without walking, kneeling, wheeling equipment, or stockpiling material on the finished bedding surface | |||
| HC-036 | Inspects the bedding layer for ridges, hollows, contamination, and disturbed areas, and rescreeds any damaged section completely before paver placement |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Record | Finding | Deficiency (if any) | Corrective Action | Status |
|---|---|---|---|---|
| Base confirmation | ||||
| Rail elevation and slope | ||||
| Bedding material condition | ||||
| Screeded surface | ||||
| Rail-void repair | ||||
| Thickness spot-checks | ||||
| Surface protection | ||||
| Coverage timing |
Final acceptance: ______ (Accepted / Rescreed Required) Notes: ____________
Date: ____________ Installer name: ____________ Reinspection date (if applicable): ____________
With the bedding sand screeded and every record on the Bedding Sand Work Record completed, review the finished work against the Acceptance Standards table and confirm that the base was reconfirmed accepted before screeding, rail elevation and slope match the Chapter 5 record, the bedding material met the approved specification, the screeded surface is free of ridges, hollows, contamination, and disturbance, rail voids are filled flush, thickness spot-checks pass, and every screeded area is covered or protected within the exposure window. If any item is incomplete or a deficiency remains unresolved, rescreed the affected section and reinspect it before beginning Chapter 7.
You have completed the sixth chapter in the hardscaping sequence: screeding bedding sand for paver installation. This chapter required you to install screed rails (HC-031), place bedding sand (HC-032), screed sand evenly (HC-033), maintain uniform thickness (HC-034), avoid disturbing the screeded surface (HC-035), and inspect the bedding layer (HC-036).
You now have a clean, uniform, undisturbed bedding layer at the approved thickness and slope, ready for immediate paver placement. That finished bedding layer carries directly into the next chapter: installing a straight paver walkway using the exact bedding elevation, slope, and undisturbed surface produced here.
Retain the completed Bedding Sand Work Record together with the Chapter 5 base-acceptance record. You will reference these exact records throughout the remaining paver-installation chapters of this book, including the Chapter 20 capstone.