The Professional Contractor
|
Book 27 — Business Formation, Licensing, Contracts, Pricing, Insurance, Marketing, and Customer Relations

Project 07

Price Labor, Materials, Overhead, and Profit

Build, test, and approve one controlled contractor pricing worksheet that converts an approved scope into current material cost, burdened labor, equipment, subcontractor cost, jobsite general conditions, overhead recovery, defined risk and contingency, and an approved selling price — the pricing engine every proposal, contract, change order, and job-cost review in the rest of this book will reference.

Field Cue System

These cues appear at the point of work. They identify pricing, overhead, and approval-authority issues before an unrecovered cost or an unauthorized discount reaches a customer.

△

Business Risk Cue

A pricing choice that increases financial exposure if left unaddressed.

✋

Critical Compliance Cue

An action that must not be taken until a specific cost, review, or approval condition is satisfied.

⛑

Operational Discipline Cue

Practical controls that keep the worksheet honest as it is actually used.

▤

Cost-Code Alert

Formulas and categories must match the company's actual chart of accounts, not a generic template.

▧

Professional Advisor Cue

A point where the CPA, bookkeeper, or management must confirm an overhead, tax, or labor-burden figure.

▱

Documentation Cue

A figure, formula, or approval that must be written down, dated, and locked in the worksheet.

Job Overview

This project produces one controlled contractor pricing worksheet built on the Book 24 estimating workbook structure and the company's current chart of accounts and cost codes. The finished work product is a locked, tested worksheet that converts a defined scope from Chapter 6 into current material cost, burdened labor, equipment, subcontractor cost, jobsite general conditions, company overhead recovery, profit, defined risk, and contingency, resulting in one approved selling price for each pricing type the business uses.

You will define which pricing types the worksheet supports, build every required cost field, separate wage from fully burdened labor cost, build overhead-recovery formulas from actual accounting data, apply the company's approved markup or margin method, build risk and contingency fields tied to specific uncertainty, test the worksheet on one standard service, compare it against historical job costs and current market quotes, and obtain review and approval before locking the formulas.

This worksheet sits between the service menu built in Chapter 6 and the proposal and contract templates built in Chapters 8 and 9. No proposal may be issued and no contract may be signed using a price that did not pass through this worksheet.

Skills You Will Demonstrate

  • PC-037 — Calculate labor cost using production rates, crew composition, and fully burdened labor rates rather than wage alone.
  • PC-038 — Calculate material cost using measured quantity, waste allowance, current unit price, freight, and tax.
  • PC-039 — Add overhead recovery to a project price using a formula built from the company's actual accounting data.
  • PC-040 — Add profit margin using the company's approved markup or margin method, displayed separately from overhead.
  • PC-041 — Account for risk and contingency using named uncertainty categories and an approved authorization procedure.
  • PC-042 — Create, test, and lock a pricing worksheet capable of pricing the company's standard services.

Where This Skill Fits

This project depends directly on the approved business model from Chapter 1, the licensing and insurance limits confirmed in Chapters 3 and 4, the financial-control system built in Chapter 5, and the service menu and scope library built in Chapter 6. Every field in this worksheet must trace back to a cost code in the Chapter 5 chart of accounts and a scope identifier in the Chapter 6 scope library; it may not introduce a disconnected duplicate cost system.

The worksheet produced here becomes the pricing engine for the estimate and proposal templates in Chapter 8, the contract-ready scope of work in Chapter 9, the change-order and allowance pricing in Chapter 10, and the job-cost and profit review in Chapter 18. The discipline of comparing a calculated price against actual historical job-cost results, rather than trusting the formula blindly, is the same discipline used again in Chapter 18 and in the Chapter 20 capstone.

Scope and Intended Use

This project covers:

  • defining which pricing types — time-and-material, unit-price, fixed-price, service-call, maintenance-plan, or cost-plus — the worksheet supports
  • building material, labor, equipment, subcontractor, and general-condition cost fields tied to the Book 24 workbook structure
  • separating wage from fully burdened labor cost using payroll burden, workers' compensation, benefits, vehicle, and small-tool costs
  • building overhead-recovery formulas from the company's actual accounting categories
  • applying the company's approved markup or margin method and displaying each separately
  • building risk, contingency, callback, warranty, and bad-debt cost treatment consistent with company policy
  • building approval thresholds that restrict who may change protected formulas or approve discounts
  • testing, comparing, reviewing, and locking the worksheet

This project does not authorize the learner to:

  • issue a customer-facing price before the worksheet is tested, reviewed, and approved under Section H below
  • base a selling price solely on a competitor's price, a simple labor multiplier, a square-foot number, or the customer's stated budget
  • treat contingency as a way to conceal known scope or habitual underestimating
  • promise a fixed price for undefined conditions without an approved allowance, unit price, exclusion, investigation, or risk authorization
  • change a protected formula, overhead rate, or approved markup without the authority defined in the Chapter 2 signing-authority matrix

Any pricing type, cost field, or formula that cannot be supported by the company's actual accounting data or current market cost must be corrected before the worksheet is approved.

Reference Conventions

Establish these references before building the worksheet, and do not change their meaning mid-document.

TermDefinition
Direct costMaterial, burdened labor, equipment, and subcontractor cost specifically consumed by a project
General conditionsJobsite-level cost not tied to one task, such as protection, sanitation, temporary utilities, supervision, travel, parking, and project administration
OverheadCompany-level cost not tied to any one project, recovered across all priced work through the approved allocation formula
MarkupA percentage added to cost to calculate selling price (selling price = cost × (1 + markup))
MarginThe percentage of the selling price that is gross profit (margin = gross profit ÷ selling price)
ContingencyA priced allowance for a specific, named uncertainty, approved by a specific authority, and never used to cover known unmeasured work
Burdened labor costWage plus payroll burden, workers' compensation, benefits, vehicle, and small-tool cost attributable to an hour of labor
Pricing worksheetThe single approved, locked document produced by this chapter that converts scope into an approved selling price

Reference and Approval Record

Before the worksheet is built, record the following directly on the worksheet template:

Company (legal) name: ______     Pricing date and market: ______     Validity period: ______

Estimator: ____________     Reviewer(s): ____________     Approval date: ____________

Prerequisites

Common Field Fundamentals

Every price this business quotes, from a single service call to the largest project in its approved size range, must pass through the same sequence: measured scope, current direct cost, full labor burden, jobsite general conditions, company overhead recovery, named risk, and an approved profit calculation. Skipping any one of these categories does not make the price simpler — it makes the price wrong, and the business absorbs the difference as unrecovered cost.

Direct CostMaterial, burdened labor, equipment, subcontractors — Section F
General ConditionsJobsite-level cost not tied to one task — Section F
Overhead and ProfitCompany-level recovery and approved markup or margin — Section G
Risk and ContingencyNamed uncertainty, approved response, and authorization — Section G
Testing and ComparisonSample pricing run against historical job cost — Section H
Approval and LockReviewed, approved, and formula-locked worksheet — Section H

Labor Cost Discipline

Labor cost is never the employee's wage alone. Every labor field in this worksheet must include payroll burden, workers' compensation, benefits, vehicle cost, and small-tool cost approved by the company's accounting system before it is added to a price. A wage-only labor number is treated as an incomplete field, not a usable cost.

PC-037 – PC-042

Financial Planning / Pricing System Construction

Contractor Pricing Worksheet

Difficulty: Intermediate

Estimated Time: 10–16 hours across one to three weeks

Estimated Cost: CPA and management review time

Finished Work: One tested, reviewed, and locked pricing worksheet

A. Finished-Project Specification

Quantity: one approved and formula-locked contractor pricing worksheet, tested on at least one standard service from the Chapter 6 scope library, reviewed by the estimator, field lead, bookkeeper, CPA, and management, with a documented revision and expiration procedure and a post-job feedback link to Chapter 18.

B. Component Schedule

ComponentQuantitySourceContent RequiredPreparation / Purpose
Header and identification fields1 setBuilt in Section EScope identifier, project, customer, location, estimate type, estimator, reviewer, revisionTies every priced estimate to a controlled scope and revision
Material cost fields1 setBuilt in Section FQuantity, waste, purchase unit, unit price, freight, delivery, tax, returnConverts measured scope into current material cost
Labor cost fields1 setBuilt in Section FTask, quantity, production rate, skill, crew, hours, wage, burden, workers' compensation, benefits, vehicle, small toolsConverts labor hours into fully burdened labor cost
Equipment, subcontractor, and general-condition fields1 setBuilt in Section FEquipment rental and fuel, subcontractor and permit cost, jobsite general conditionsCaptures cost outside direct labor and material
Overhead, profit, and risk fields1 setBuilt in Section GOverhead allocation, markup or margin, named risk categories, contingency, callback and warranty treatmentConverts direct cost into an approved selling price
Summary and approval fields1 setBuilt in Section G–HDirect cost, overhead, profit, selling price, gross margin, labor hours, cash requirement, approval thresholdsPresents the final price and protects it from unauthorized change

C. Data Takeoff

  • Book 24 structure: the estimating workbook fields, cost codes, and layout this worksheet must align with, gathered before Step 1.
  • Chart of accounts data: current overhead categories, payroll burden rates, and cost-code figures from Chapter 5, gathered before Section G.
  • Market data: current material unit prices, freight, subcontractor quotes, and equipment rental rates for the service area, gathered before Section F.
  • Historical job-cost data: at least one completed or in-progress project's actual labor hours, material cost, and gross profit, gathered before Section H testing.

D. Acceptance Standards

CheckStandard
Pricing-type coverageThe worksheet supports every pricing type — time-and-material, unit-price, fixed-price, service-call, maintenance-plan, or cost-plus — that this business actually uses
Labor costEvery labor field resolves to a fully burdened rate, never wage alone, confirmed by the bookkeeper or CPA
Material costEvery material field includes quantity, waste, unit price, freight, delivery, and tax from a current source
Overhead recoveryThe overhead formula is built from actual accounting data and does not duplicate cost already captured in labor, equipment, general conditions, or subcontractor pricing
Markup and marginMarkup and margin are calculated with the company's approved method and displayed separately
Risk and contingencyEvery contingency field names its specific uncertainty and required approval authority; no field covers known unmeasured work
TestingThe worksheet has been tested on at least one standard service and compared against historical job cost, current quotes, and market position, with differences investigated rather than forced
Review and approvalThe estimator, field lead, bookkeeper, CPA, and management have reviewed the worksheet and their comments are recorded and addressed before formulas are locked

E. Worksheet Structure and Identification

  1. Import the Book 24 estimating workbook structure and the current company chart of accounts and cost codes. Confirm the worksheet's categories and field names align with both before any formula is built.
  2. Define whether the worksheet supports time-and-material, unit-price, fixed-price, service-call, maintenance-plan, or cost-plus work. Record the approved pricing types this business uses and build a separate calculation path for each.
  3. Identify the approved pricing date, market, service area, tax treatment, and validity period. Record these on the worksheet header and set an expiration rule.
  4. Create fields for scope identifier, project, customer, location, estimate type, estimator, reviewer, and revision. Link the scope identifier field directly to the Chapter 6 scope library.

F. Direct Cost, Labor, Equipment, and General Conditions

  1. Create material quantity, waste, purchase unit, unit price, freight, delivery, tax, return, and total fields. Tie unit prices to a current, dated supplier quote or price list.
  2. Create labor task, quantity, production rate, skill, crew, direct hours, setup, cleanup, supervision, and total-hour fields. Base production rates on historical job-cost data where available.
  3. Create wage, payroll burden, workers' compensation, benefits, vehicle, small-tool, and other approved labor-cost fields. Confirm each rate with the bookkeeper or CPA before use.
  4. Do not use employee wage alone as labor cost. Verify every labor total resolves through the burden fields before it reaches the cost summary.
  5. Create equipment, rental, fuel, delivery, operator, consumable, and minimum-period fields. Use current rental agreements or dated quotes.
  6. Create subcontractor, permit, inspection, testing, design, disposal, and specialty-service fields. Tie each to a current subcontractor or vendor quote where available.
  7. Create jobsite general-condition fields for protection, sanitation, temporary utilities, supervision, travel, parking, and project administration. Base these on project duration and crew size rather than a flat estimate.

G. Overhead, Profit, Risk, and Contingency

  1. Create company overhead categories from actual accounting data. Import the overhead categories directly from the Chapter 5 chart of accounts.
  2. Determine the approved overhead allocation basis with the CPA and management. Record the chosen basis — such as percentage of direct cost, percentage of labor, or per-project fixed allocation — and the reviewing CPA's name and date.
  3. Create formulas that recover overhead without duplicating costs already in labor, equipment, general conditions, or subcontractor pricing. Cross-check every overhead category against the direct-cost fields built in Section F to confirm no category appears twice.
  4. Create a profit calculation using the approved markup or margin method. Confirm the method matches company policy before building the formula.
  5. Display markup and margin separately to prevent confusion. Label each field clearly with its formula visible to the reviewer.
  6. Create risk categories for scope, existing condition, customer, access, schedule, material, labor, weather, permit, and subcontractor uncertainty. List each category as its own row.
  7. Create approved responses for each risk: investigate, clarify, exclude, allow, alternate, unit price, contingency, or decline. Assign one response to each risk category identified in the previous step.
  8. Create contingency fields that identify the specific uncertainty and approval authority. Do not create a generic, unnamed contingency line.
  9. Do not use contingency for known unmeasured work. Verify every contingency traces to a named, uncertain condition rather than an item that should instead be measured and priced directly.
  10. Create callback, warranty, punch, and bad-debt cost treatment according to company policy. Record the approved treatment and its source policy document.
  11. Create minimum service-call, mobilization, diagnostic, emergency, and after-hours pricing only after legal and market review. Confirm these figures with management and, where required, counsel before adding them to the worksheet.
  12. Create deposit, payment schedule, retainage, financing, and cash-flow considerations without inserting unreviewed customer terms. Leave contract-specific payment language to the Chapter 9 attorney-reviewed scope of work.
  13. Create sensitivity checks for labor hours, material price, schedule, and hidden conditions. Build a simple variance test that shows the effect of a defined percentage change in each input.
  14. Create summary views for direct cost, overhead, profit, selling price, gross margin, labor hours, and cash requirement. Present these as one clear summary table at the top or end of the worksheet.
  15. Create approval thresholds for discounts, margin reduction, contingency use, and nonstandard terms. Record the specific dollar or percentage threshold and the approving role for each.
  16. Prohibit sales personnel from changing protected formulas or approving unauthorized discounts. Apply spreadsheet or software protection consistent with the Chapter 2 signing-authority matrix.

H. Testing, Review, and Approval

  1. Test the worksheet on one standard service from Chapter 6. Run a complete price calculation using current data and record the resulting selling price.
  2. Compare the price with historical job costs, current supplier quotes, subcontractor input, and market position. Record each comparison figure alongside the worksheet's calculated price.
  3. Investigate differences rather than forcing a target price. Identify whether a difference comes from production rate, material price, overhead allocation, or an omitted cost category before adjusting the worksheet.
  4. Review the worksheet with the estimator, field lead, bookkeeper, CPA, and management as applicable. Record each reviewer's name, role, comments, and date.
  5. Approve the worksheet and lock formulas. Obtain the authorized manager's signature and date, then apply formula protection.
  6. Create a pricing revision and expiration procedure. Record the review interval and the specific conditions — cost-code change, overhead change, market shift — that trigger an earlier revision.
  7. Create a post-job feedback process from Chapter 18 to update rates and assumptions. Record how completed-project job-cost results will be routed back into this worksheet's production rates and cost data.

Common Worksheet Inspection

Inspect the completed worksheet using the same checks regardless of which service or pricing type is involved.

Complete the Pricing Worksheet Approval Record in the Inspection Checklist section below before beginning Project 08.

Image Placeholder
Recommended image: a completed sample pricing worksheet summary view showing direct cost, overhead, profit, selling price, and gross margin fields.
Image Placeholder
Recommended image: a labor-cost field set showing wage, payroll burden, workers' compensation, benefits, vehicle, and small-tool cost building to a fully burdened rate.
Image Placeholder
Recommended image: a risk and contingency table with named uncertainty categories, approved responses, and authorization fields.
Image Placeholder
Recommended image: a sensitivity-check table showing the effect of a defined change in labor hours or material price on the final selling price.

Failure Points and Troubleshooting

Cleanup

This project ends with the approved worksheet locked and filed for reuse, not left as an editable draft.

Field Terms

Direct Cost
Material, burdened labor, equipment, and subcontractor cost specifically consumed by a project.
General Conditions
Jobsite-level cost not tied to one task, such as protection, sanitation, and supervision.
Overhead
Company-level cost recovered across all priced work through the approved allocation formula.
Markup
A percentage added to cost to calculate selling price.
Margin
The percentage of the selling price that is gross profit.
Contingency
A priced allowance for a specific, named uncertainty, approved by a specific authority.
Burdened Labor Cost
Wage plus payroll burden, workers' compensation, benefits, vehicle, and small-tool cost.
Pricing Worksheet
The single approved, locked document that converts scope into an approved selling price.
General Condition Cost
Jobsite administrative and support cost distinct from company overhead.
Formula Lock
Protection applied to a worksheet's formulas preventing unauthorized edits while allowing data updates.

Skill Check

  1. Why is employee wage alone never an acceptable labor cost in this worksheet?
  2. What is the difference between markup and margin, and why must the worksheet display them separately?
  3. What must every contingency field identify before it is approved?
  4. Why must the overhead-recovery formula be built from actual accounting data rather than an industry rule-of-thumb percentage?
  5. What is the difference between a direct cost, a general-condition cost, and an overhead cost?
  6. What must happen before a difference between the worksheet's calculated price and historical job cost is corrected by adjusting the worksheet?
  7. Who must review the completed worksheet before it is approved and locked?
  8. What is prohibited from sales personnel once the worksheet's formulas are locked?
  9. What triggers an earlier-than-scheduled revision of the pricing worksheet?
  10. What is the purpose of the Chapter 18 post-job feedback link to this worksheet?

Competency Rubric

CompetencyIndependent Pass StandardNot DemonstratedWith AssistanceIndependently
PC-037Calculates labor cost using production rates, crew composition, and a fully burdened labor rate confirmed by the bookkeeper or CPA
PC-038Calculates material cost using measured quantity, waste allowance, current unit price, freight, delivery, and tax
PC-039Builds an overhead-recovery formula from the company's actual chart of accounts without duplicating cost captured elsewhere
PC-040Applies the company's approved markup or margin method and displays both separately
PC-041Builds risk and contingency fields that name specific uncertainty and required approval authority, with none covering known unmeasured work
PC-042Produces a tested, reviewed, and formula-locked pricing worksheet capable of pricing the company's standard services, filed in the company record system

Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.

Inspection Checklist — Pricing Worksheet Approval Record

ItemStandardComplete (Y/N)Notes / Correction
Pricing-type coverageEvery pricing type the business uses is supported
Labor cost fieldsEvery labor field resolves to a fully burdened rate
Material cost fieldsQuantity, waste, unit price, freight, delivery, and tax included and current
Equipment, subcontractor, and general-condition fieldsBuilt and tied to current quotes and jobsite duration
Overhead-recovery formulaBuilt from actual accounting data; no duplication with other fields
Markup and marginCalculated with approved method; displayed separately
Risk and contingency fieldsEvery field names a specific uncertainty and approval authority
Approval thresholdsDiscount, margin-reduction, and contingency-use thresholds recorded and protected
Testing and comparisonTested on one standard service; compared against historical job cost and current market
Professional review completedEstimator, field lead, bookkeeper, CPA, and management reviewed; comments recorded and addressed
Formulas lockedProtection applied consistent with signing-authority matrix

Pricing worksheet declared complete: ______ (Pass/Fail)     Date: ____________     Approving manager: ____________

Reviewing CPA or bookkeeper: ____________     Next scheduled revision date: ____________

Performance Check

With the worksheet built and tested, review it against the Acceptance Standards table and confirm every labor field is fully burdened, every material field is current, the overhead formula is built from actual accounting data without duplication, markup and margin are displayed separately using the approved method, every contingency names a specific uncertainty and authority, and the estimator, field lead, bookkeeper, CPA, and management have reviewed and the business has addressed their comments. Complete the Pricing Worksheet Approval Record and correct any failed item before beginning Project 08. If an item fails, identify whether the gap is in labor burden, material currency, overhead allocation, profit calculation, risk definition, or professional review before revising the worksheet.

Project Closeout

You have completed the seventh project in the professional-contractor sequence: pricing labor, materials, overhead, and profit. This project required you to calculate fully burdened labor cost (PC-037), calculate current material cost (PC-038), add overhead recovery built from actual accounting data (PC-039), add profit using the approved markup or margin method (PC-040), account for risk and contingency using named uncertainty and approval authority (PC-041), and build, test, and lock a complete pricing worksheet (PC-042).

You now have one tested, reviewed, and formula-locked contractor pricing worksheet built on the Book 24 estimating structure and the company's actual accounting data. That worksheet carries directly into the next project: creating the standard estimate and proposal templates that will present this worksheet's calculated price to customers with clear scope, options, exclusions, and jurisdiction-appropriate legal language.

Store your approved pricing worksheet in a secure, controlled location with formula protection applied. You will reference this exact worksheet in every remaining chapter of this book.