Business Risk Cue
A pricing choice that increases financial exposure if left unaddressed.
Project 07
Build, test, and approve one controlled contractor pricing worksheet that converts an approved scope into current material cost, burdened labor, equipment, subcontractor cost, jobsite general conditions, overhead recovery, defined risk and contingency, and an approved selling price — the pricing engine every proposal, contract, change order, and job-cost review in the rest of this book will reference.
These cues appear at the point of work. They identify pricing, overhead, and approval-authority issues before an unrecovered cost or an unauthorized discount reaches a customer.
A pricing choice that increases financial exposure if left unaddressed.
An action that must not be taken until a specific cost, review, or approval condition is satisfied.
Practical controls that keep the worksheet honest as it is actually used.
Formulas and categories must match the company's actual chart of accounts, not a generic template.
A point where the CPA, bookkeeper, or management must confirm an overhead, tax, or labor-burden figure.
A figure, formula, or approval that must be written down, dated, and locked in the worksheet.
This project produces one controlled contractor pricing worksheet built on the Book 24 estimating workbook structure and the company's current chart of accounts and cost codes. The finished work product is a locked, tested worksheet that converts a defined scope from Chapter 6 into current material cost, burdened labor, equipment, subcontractor cost, jobsite general conditions, company overhead recovery, profit, defined risk, and contingency, resulting in one approved selling price for each pricing type the business uses.
You will define which pricing types the worksheet supports, build every required cost field, separate wage from fully burdened labor cost, build overhead-recovery formulas from actual accounting data, apply the company's approved markup or margin method, build risk and contingency fields tied to specific uncertainty, test the worksheet on one standard service, compare it against historical job costs and current market quotes, and obtain review and approval before locking the formulas.
This worksheet sits between the service menu built in Chapter 6 and the proposal and contract templates built in Chapters 8 and 9. No proposal may be issued and no contract may be signed using a price that did not pass through this worksheet.
This project depends directly on the approved business model from Chapter 1, the licensing and insurance limits confirmed in Chapters 3 and 4, the financial-control system built in Chapter 5, and the service menu and scope library built in Chapter 6. Every field in this worksheet must trace back to a cost code in the Chapter 5 chart of accounts and a scope identifier in the Chapter 6 scope library; it may not introduce a disconnected duplicate cost system.
The worksheet produced here becomes the pricing engine for the estimate and proposal templates in Chapter 8, the contract-ready scope of work in Chapter 9, the change-order and allowance pricing in Chapter 10, and the job-cost and profit review in Chapter 18. The discipline of comparing a calculated price against actual historical job-cost results, rather than trusting the formula blindly, is the same discipline used again in Chapter 18 and in the Chapter 20 capstone.
This project covers:
This project does not authorize the learner to:
Any pricing type, cost field, or formula that cannot be supported by the company's actual accounting data or current market cost must be corrected before the worksheet is approved.
Establish these references before building the worksheet, and do not change their meaning mid-document.
| Term | Definition |
|---|---|
| Direct cost | Material, burdened labor, equipment, and subcontractor cost specifically consumed by a project |
| General conditions | Jobsite-level cost not tied to one task, such as protection, sanitation, temporary utilities, supervision, travel, parking, and project administration |
| Overhead | Company-level cost not tied to any one project, recovered across all priced work through the approved allocation formula |
| Markup | A percentage added to cost to calculate selling price (selling price = cost × (1 + markup)) |
| Margin | The percentage of the selling price that is gross profit (margin = gross profit ÷ selling price) |
| Contingency | A priced allowance for a specific, named uncertainty, approved by a specific authority, and never used to cover known unmeasured work |
| Burdened labor cost | Wage plus payroll burden, workers' compensation, benefits, vehicle, and small-tool cost attributable to an hour of labor |
| Pricing worksheet | The single approved, locked document produced by this chapter that converts scope into an approved selling price |
Before the worksheet is built, record the following directly on the worksheet template:
Company (legal) name: ______ Pricing date and market: ______ Validity period: ______
Estimator: ____________ Reviewer(s): ____________ Approval date: ____________
Every price this business quotes, from a single service call to the largest project in its approved size range, must pass through the same sequence: measured scope, current direct cost, full labor burden, jobsite general conditions, company overhead recovery, named risk, and an approved profit calculation. Skipping any one of these categories does not make the price simpler — it makes the price wrong, and the business absorbs the difference as unrecovered cost.
Labor cost is never the employee's wage alone. Every labor field in this worksheet must include payroll burden, workers' compensation, benefits, vehicle cost, and small-tool cost approved by the company's accounting system before it is added to a price. A wage-only labor number is treated as an incomplete field, not a usable cost.
Do not use employee wage alone as labor cost anywhere in this worksheet. Every labor field must resolve to a fully burdened rate approved by the bookkeeper or CPA before the worksheet is tested in Section H.
Every contingency field must identify the specific uncertainty it covers and the authority required to release it. A contingency line with no named uncertainty is not a contingency; it is an unexplained price increase and must be removed or corrected before approval.
Once approved in Section H, protect the worksheet's formulas from edits by sales or field personnel while still allowing current material, labor, and subcontractor cost data to be updated. Changing a protected formula requires the same signing authority defined in the Chapter 2 signing-authority matrix.
The overhead-allocation basis used in Section G must be confirmed with the CPA and reconciled against actual accounting data from Chapter 5. Do not adopt an industry rule-of-thumb overhead percentage without confirming it against this company's real cost structure.
PC-037 – PC-042
Financial Planning / Pricing System Construction
Quantity: one approved and formula-locked contractor pricing worksheet, tested on at least one standard service from the Chapter 6 scope library, reviewed by the estimator, field lead, bookkeeper, CPA, and management, with a documented revision and expiration procedure and a post-job feedback link to Chapter 18.
| Component | Quantity | Source | Content Required | Preparation / Purpose |
|---|---|---|---|---|
| Header and identification fields | 1 set | Built in Section E | Scope identifier, project, customer, location, estimate type, estimator, reviewer, revision | Ties every priced estimate to a controlled scope and revision |
| Material cost fields | 1 set | Built in Section F | Quantity, waste, purchase unit, unit price, freight, delivery, tax, return | Converts measured scope into current material cost |
| Labor cost fields | 1 set | Built in Section F | Task, quantity, production rate, skill, crew, hours, wage, burden, workers' compensation, benefits, vehicle, small tools | Converts labor hours into fully burdened labor cost |
| Equipment, subcontractor, and general-condition fields | 1 set | Built in Section F | Equipment rental and fuel, subcontractor and permit cost, jobsite general conditions | Captures cost outside direct labor and material |
| Overhead, profit, and risk fields | 1 set | Built in Section G | Overhead allocation, markup or margin, named risk categories, contingency, callback and warranty treatment | Converts direct cost into an approved selling price |
| Summary and approval fields | 1 set | Built in Section G–H | Direct cost, overhead, profit, selling price, gross margin, labor hours, cash requirement, approval thresholds | Presents the final price and protects it from unauthorized change |
| Check | Standard |
|---|---|
| Pricing-type coverage | The worksheet supports every pricing type — time-and-material, unit-price, fixed-price, service-call, maintenance-plan, or cost-plus — that this business actually uses |
| Labor cost | Every labor field resolves to a fully burdened rate, never wage alone, confirmed by the bookkeeper or CPA |
| Material cost | Every material field includes quantity, waste, unit price, freight, delivery, and tax from a current source |
| Overhead recovery | The overhead formula is built from actual accounting data and does not duplicate cost already captured in labor, equipment, general conditions, or subcontractor pricing |
| Markup and margin | Markup and margin are calculated with the company's approved method and displayed separately |
| Risk and contingency | Every contingency field names its specific uncertainty and required approval authority; no field covers known unmeasured work |
| Testing | The worksheet has been tested on at least one standard service and compared against historical job cost, current quotes, and market position, with differences investigated rather than forced |
| Review and approval | The estimator, field lead, bookkeeper, CPA, and management have reviewed the worksheet and their comments are recorded and addressed before formulas are locked |
Inspect the completed worksheet using the same checks regardless of which service or pricing type is involved.
Complete the Pricing Worksheet Approval Record in the Inspection Checklist section below before beginning Project 08.
Probable cause: production rates are optimistic, a labor-burden component is missing, or an overhead category was omitted from the allocation formula.
Confirmation: compare the worksheet's labor hours, burden rate, and overhead recovery line by line against a completed project's actual job-cost report.
Correction: update the production rate or burden rate from the actual data and add any missing overhead category to the allocation formula.
Reinspection: rerun the test in Section H on the corrected worksheet and compare again.
Probable cause: the contingency was added as a general cushion rather than tied to a specific risk category from Section G.
Confirmation: review the contingency field against the risk table and confirm whether a specific uncertainty and approval authority are recorded.
Correction: either assign the contingency to a named risk category with a specific approval authority, or remove it and price the known item directly.
Reinspection: repeat the risk check on the corrected worksheet.
Probable cause: a cost such as vehicle expense or small tools appears in both the labor-burden fields and the general overhead allocation.
Confirmation: cross-check every overhead category against the direct-cost and general-condition fields to identify duplication.
Correction: remove the duplicated category from whichever field is not the company's designated location for that cost, per the Chapter 5 chart of accounts.
Reinspection: repeat the overhead check on the corrected worksheet.
Probable cause: formula protection was not applied, or the discount-approval threshold was not enforced in the software.
Confirmation: review the worksheet's edit history or version log and compare the discount against the approved thresholds from Section G.
Correction: restore the protected formula, correct any price issued under the unauthorized change, and reapply protection consistent with the Chapter 2 signing-authority matrix.
Reinspection: repeat the review check with management confirming the corrected protection is functioning.
Probable cause: the overhead allocation was estimated internally without reconciling it against actual accounting data.
Confirmation: check the approval record for the CPA's name, review date, and recorded comments on the overhead basis.
Correction: suspend reliance on the worksheet for new proposals until the CPA has reviewed and confirmed the overhead basis.
Reinspection: repeat the professional-review check before re-approving the worksheet.
Probable cause: the worksheet was built around only one pricing type when the business actually quotes several.
Confirmation: compare the pricing types listed in Section E, Step 2 against the pricing types actually used in recent proposals.
Correction: build the missing pricing-type calculation path using the same direct-cost, overhead, and profit structure as the existing paths.
Reinspection: repeat the pricing-type coverage check on the corrected worksheet.
This project ends with the approved worksheet locked and filed for reuse, not left as an editable draft.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| PC-037 | Calculates labor cost using production rates, crew composition, and a fully burdened labor rate confirmed by the bookkeeper or CPA | |||
| PC-038 | Calculates material cost using measured quantity, waste allowance, current unit price, freight, delivery, and tax | |||
| PC-039 | Builds an overhead-recovery formula from the company's actual chart of accounts without duplicating cost captured elsewhere | |||
| PC-040 | Applies the company's approved markup or margin method and displays both separately | |||
| PC-041 | Builds risk and contingency fields that name specific uncertainty and required approval authority, with none covering known unmeasured work | |||
| PC-042 | Produces a tested, reviewed, and formula-locked pricing worksheet capable of pricing the company's standard services, filed in the company record system |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Standard | Complete (Y/N) | Notes / Correction |
|---|---|---|---|
| Pricing-type coverage | Every pricing type the business uses is supported | ||
| Labor cost fields | Every labor field resolves to a fully burdened rate | ||
| Material cost fields | Quantity, waste, unit price, freight, delivery, and tax included and current | ||
| Equipment, subcontractor, and general-condition fields | Built and tied to current quotes and jobsite duration | ||
| Overhead-recovery formula | Built from actual accounting data; no duplication with other fields | ||
| Markup and margin | Calculated with approved method; displayed separately | ||
| Risk and contingency fields | Every field names a specific uncertainty and approval authority | ||
| Approval thresholds | Discount, margin-reduction, and contingency-use thresholds recorded and protected | ||
| Testing and comparison | Tested on one standard service; compared against historical job cost and current market | ||
| Professional review completed | Estimator, field lead, bookkeeper, CPA, and management reviewed; comments recorded and addressed | ||
| Formulas locked | Protection applied consistent with signing-authority matrix |
Pricing worksheet declared complete: ______ (Pass/Fail) Date: ____________ Approving manager: ____________
Reviewing CPA or bookkeeper: ____________ Next scheduled revision date: ____________
With the worksheet built and tested, review it against the Acceptance Standards table and confirm every labor field is fully burdened, every material field is current, the overhead formula is built from actual accounting data without duplication, markup and margin are displayed separately using the approved method, every contingency names a specific uncertainty and authority, and the estimator, field lead, bookkeeper, CPA, and management have reviewed and the business has addressed their comments. Complete the Pricing Worksheet Approval Record and correct any failed item before beginning Project 08. If an item fails, identify whether the gap is in labor burden, material currency, overhead allocation, profit calculation, risk definition, or professional review before revising the worksheet.
You have completed the seventh project in the professional-contractor sequence: pricing labor, materials, overhead, and profit. This project required you to calculate fully burdened labor cost (PC-037), calculate current material cost (PC-038), add overhead recovery built from actual accounting data (PC-039), add profit using the approved markup or margin method (PC-040), account for risk and contingency using named uncertainty and approval authority (PC-041), and build, test, and lock a complete pricing worksheet (PC-042).
You now have one tested, reviewed, and formula-locked contractor pricing worksheet built on the Book 24 estimating structure and the company's actual accounting data. That worksheet carries directly into the next project: creating the standard estimate and proposal templates that will present this worksheet's calculated price to customers with clear scope, options, exclusions, and jurisdiction-appropriate legal language.
Store your approved pricing worksheet in a secure, controlled location with formula protection applied. You will reference this exact worksheet in every remaining chapter of this book.