Chapter 14
Configure one approved GTAW station for mild-steel practice with a correctly assembled torch, prepared and uncontaminated tungsten, leak-checked shielding gas, approved polarity and current controls, clean filler rod, a sound work-clamp connection, and a completed readiness inspection.
These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become fires, injuries, contaminated tungsten, or an unstable arc.
Task-specific safety guidance for ordinary work hazards.
Serious injury, fire, or major damage is possible.
Practical work-area safety: cords, hoses, footing, and housekeeping.
Local requirements vary. Verify permit, inspection, and jurisdictional rules.
Follow product-specific instructions for tools, materials, and equipment.
Tungsten extension, cup size, flow, and dimensional guidance.
This chapter qualifies you to configure one gas tungsten arc welding (GTAW) station for approved mild-steel practice. You will assemble the torch, select and prepare the tungsten electrode, connect and leak-check the shielding gas, verify polarity and current controls, attach the work clamp, select and clean filler rod, and complete a documented setup inspection before any sustained arc is struck.
No practice beads are run in this chapter beyond a brief instructor-authorized test arc used to verify that the station is functioning. Running controlled autogenous and filler-added beads on mild steel is the work of Chapter 15, and that chapter depends entirely on the station you configure and document here.
This chapter assumes the welding area, PPE, machine, leads, work clamp, and gas system have already passed the readiness inspections in Chapters 1 through 3. This chapter adds the process-specific GTAW setup: torch assembly, tungsten preparation, and filler-rod handling.
Chapters 7 through 13 built SMAW, GMAW, and FCAW competence on the same authorize-inspect-connect-verify pattern used throughout this book. This chapter applies that same pattern to a process with different setup demands: a nonconsumable tungsten electrode, a separately handled filler rod, and gas shielding that must be leak-checked and flow-verified before any arc is struck. Chapter 15 uses the station documented here to run autogenous and filler-added beads. Every later GTAW reference in this book assumes the torch, tungsten, and gas system were set up according to this chapter.
This chapter covers:
This chapter does not authorize the learner to:
Establish these references before setup begins, and do not change them without re-running the affected portion of the readiness inspection.
| Term | Definition |
|---|---|
| Tungsten extension | The length of tungsten protruding beyond the cup, set according to the approved procedure, joint access, and cup size |
| Collet body / gas lens | The torch component that holds the collet and shapes gas flow around the tungsten; not interchangeable with a standard collet body without matching the cup |
| Pre-flow / post-flow | Shielding-gas flow before arc initiation and after arc termination, set only where the machine control is adjustable |
| Test coupon | The clean, identified mild-steel scrap used only for the brief instructor-authorized test arc in this chapter |
| Setup readiness record | The signed document confirming torch, tungsten, gas, polarity, controls, and filler rod have passed inspection before the test arc is authorized |
Before the test arc, record the following directly on the GTAW setup readiness checklist:
Station or machine ID: ______________________ Approved GTAW procedure reference: ______________________
Tungsten type/diameter: ______________________ Filler rod classification/diameter: ______________________ Shielding gas: ______________________
Responsible person: ______________________ Date: ____________ Builder/learner name: ____________
GTAW setup follows the same authorize-inspect-connect-verify sequence used for every process in this book, applied to torch assembly, tungsten preparation, gas connection, and filler-rod handling before any arc is struck.
Tungsten contamination and torch-component mismatch are the two most common causes of an unstable GTAW arc at setup. Torch components must be matched to the cup and gas-flow requirement of the approved procedure, and tungsten must be prepared only on equipment reserved for tungsten.
Set tungsten extension according to the cup size, joint access, and the approved procedure. Do not extend tungsten beyond the length the cup and gas flow are designed to shield. Confirm the extension after installing the back cap, not before.
Turn off and isolate the machine before assembling the torch, installing tungsten, or changing collet, cup, or back cap components. Do not assemble or adjust the torch on an energized station.
Prepare tungsten only on grinding equipment reserved for tungsten. Do not use a contaminated general-purpose grinding wheel. Control tungsten dust according to the material and shop requirements for the tungsten type in use.
Verify gas label, regulator or flowmeter, hose, and fitting compatibility against the torch and cylinder manufacturer information before connecting the system. Use only clean, undamaged, compatible fittings.
WF-079 – WF-084
Equipment Setup / Readiness Qualification
Outcome: one GTAW station with a correctly assembled torch, prepared and uncontaminated tungsten at the specified extension, a leak-checked and flow-verified shielding-gas system, verified polarity and current controls, a sound work-clamp connection, clean staged filler rod, a completed brief test arc, and a signed GTAW setup readiness checklist. No practice beads are produced as part of this chapter's finished work.
| Component | Quantity | Source / Identification | Setup Condition |
|---|---|---|---|
| Torch body, back cap, collet, collet body or gas lens, cup | 1 set | Matched to the approved GTAW procedure and tungsten diameter | Assembled with correct fittings, no overtightening, verified compatible and undamaged |
| Tungsten electrode | As required by procedure | Approved type and diameter, identified by color code or marking | Ground to the specified point, taper, or end shape on dedicated equipment, cleaned after grinding |
| Shielding-gas cylinder, regulator or flowmeter, hose | 1 system | Gas type specified by the approved GTAW procedure | Secured upright, leak-checked, flow set to the approved starting range |
| Foot pedal or hand control | 1 | Compatible with the power source | Connected and positioned for stable operator use |
| Work clamp and lead | 1 | Inspected in Chapter 3 | Attached to clean sound metal close to the test coupon |
| Filler rod | As required | Approved classification and diameter, identified by package label | Cleaned, free of rust, oil, paint, or bent ends, staged in a clean labeled holder |
| Test coupon | 1 | Clean identified mild-steel scrap | Reserved only for the brief authorized test arc |
| Check | Standard |
|---|---|
| Torch assembly | Collet, collet body or gas lens, cup, tungsten, and back cap installed with correct fittings, undamaged, not overtightened |
| Tungsten condition | Approved type and diameter, free of contamination, splits, excessive erosion, or mixed identification; ground to the specified end shape on dedicated equipment |
| Tungsten extension | Set according to cup size, joint access, and the approved procedure |
| Gas system | Cylinder secured upright, label and fittings verified, connections leak-checked using the approved method, flow set to the approved starting range |
| Polarity and controls | Machine polarity verified for mild-steel GTAW; current type, start method, amperage limit, slope, and pulse set only as specified |
| Work clamp | Attached to clean sound base metal close to the test coupon |
| Filler rod | Approved classification and diameter, free of rust, oil, paint, mixed identity, or bent ends, staged in a clean labeled holder |
| Test arc | Stable arc, adequate gas coverage, no tungsten contamination, correct machine response, completed only under instructor authorization |
| Readiness record | GTAW setup readiness checklist completed and signed before further practice |
Inspect the station using the same checks regardless of tungsten diameter, cup size, or gas type in use.
Complete the GTAW Setup Readiness Checklist in the Inspection Checklist section below before beginning Chapter 15.
Probable cause: tungsten contamination from the base metal, filler rod, or an unclean grind; or a loose torch connection.
Confirmation: inspect the tungsten tip for a blue, black, or ball-shaped contaminated end and check torch fitting tightness.
Correction: regrind or replace the contaminated tungsten on the dedicated grinder and reseat torch connections.
Reinspection: repeat the tungsten condition check and the test arc under instructor authorization.
Probable cause: incorrect cup size for the flow rate, a leak in the gas line, or drafts in the work area disturbing the shielding envelope.
Confirmation: repeat the leak check on all fittings and confirm cup size against the approved procedure's flow recommendation.
Correction: replace damaged fittings, correct the cup and flow match, or relocate the test coupon away from drafts.
Reinspection: repeat the gas-flow check and leak check before the next test arc.
Probable cause: the torch cooling system is not functioning, or the torch is rated below the current in use.
Confirmation: verify torch cooling per the manufacturer instructions and confirm the torch's rated current against the machine setting.
Correction: correct the cooling system or reduce current only within the approved procedure's range, or substitute the correctly rated torch.
Reinspection: repeat the torch-cooling verification before any further test arc.
Probable cause: the pedal or hand control is not correctly connected, or a control setting was changed outside the approved procedure.
Confirmation: verify the pedal or hand control connection and compare every current-related setting against the approved procedure.
Correction: reseat the control connection and reset any setting that does not match the approved procedure.
Reinspection: repeat the control check and confirm response during a brief authorized test arc.
Probable cause: filler rod was stored without protection from rust, oil, or mixed identification with other rod.
Confirmation: inspect the rod surface and packaging label against the approved GTAW procedure's classification and diameter.
Correction: clean the rod using the approved method or replace it with correctly identified stock.
Reinspection: repeat the filler-rod inspection before staging it in the holder.
This chapter ends with a documented, ready station, not a completed weld. Housekeeping here protects the setup record for Chapter 15.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| WF-079 | Correctly identifies torch body, back cap, collet, collet body or gas lens, cup, tungsten, and power connection | |||
| WF-080 | Selects, inspects, and grinds tungsten to the specified end shape on dedicated equipment without contamination | |||
| WF-081 | Connects, leak-checks, and sets flow on the shielding-gas system to the approved starting range | |||
| WF-082 | Verifies polarity and sets current type, amperage limit, and other controls only as specified by the approved procedure | |||
| WF-083 | Selects, inspects, cleans, and stages filler rod in a clean labeled holder | |||
| WF-084 | Completes the GTAW setup checklist, corrects every failed item, and obtains authorization before the test arc |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Standard | Pass (Y/N) | Correction (if any) |
|---|---|---|---|
| Torch assembly | Correct components, correctly seated, not overtightened | ||
| Tungsten type/diameter | Matches approved procedure, free of contamination | ||
| Tungsten grind | Specified end shape, prepared on dedicated equipment | ||
| Tungsten extension | Set to procedure, cup, and joint-access requirement | ||
| Gas system | Secured, leak-checked, correct flow, pre-flow, post-flow | ||
| Polarity | Verified for mild-steel GTAW | ||
| Current controls | Type, amperage limit, slope, pulse set only as specified | ||
| Foot pedal / hand control | Connected, positioned for stable use | ||
| Work clamp | Attached to clean sound metal near test coupon | ||
| Filler rod | Identified, clean, correctly staged | ||
| Test arc | Authorized, stable, no contamination or overheating |
Station declared ready: ______ (Pass/Fail) Responsible person signature: ____________________ Date: ____________ Builder/learner name: ____________
With the test arc complete, review the finished station against the Acceptance Standards table and confirm the torch is correctly assembled, the tungsten is uncontaminated and correctly ground and extended, the gas system is leak-checked and flowing at the approved rate, polarity and current controls match the approved procedure, the work clamp is attached to clean sound metal near the test coupon, and filler rod is identified, clean, and staged. Complete the GTAW Setup Readiness Checklist and correct any failed item before obtaining the responsible person's signature. Do not proceed to Chapter 15 until the readiness record is signed.
You have completed the GTAW station setup chapter. This chapter required you to identify TIG torch components (WF-079), prepare tungsten (WF-080), connect shielding gas (WF-081), set machine controls (WF-082), position filler rod (WF-083), and complete a TIG setup inspection (WF-084).
You now have a documented, leak-checked, and inspected GTAW station with a stable brief test arc on record. That station, and the setup readiness record behind it, carries directly into the next chapter: running controlled autogenous and filler-added GTAW beads on mild steel.
Store the signed GTAW Setup Readiness Checklist with your other project records. You will confirm this station's readiness before beginning Chapter 15.