Project 10
Shape the building site to the required rough elevations and drainage pattern by cutting high areas, filling low areas with approved compacted material, and directing runoff away from excavations and active work, producing a stable rough-graded site that supports construction and channels water away from the work.
These cues appear at the point of work. They identify safety, code, documentation, and grading issues before drainage misdirection, unsuitable fill, or an unverified elevation compromises the site.
Task-specific safety guidance for ordinary grading and earthmoving hazards.
A condition that must stop work until corrected and reverified.
Practical work-area safety around grading equipment, haul routes, and open excavations.
Local requirements vary. Verify drainage, setback, and grading-plan requirements before shaping.
Follow product-specific instructions for compaction equipment operating limits and fill-material handling.
Elevation, slope, and drainage guidance for accurate, reproducible rough-grade results.
This project qualifies you to rough grade a residential building site consisting of re-established grade stakes and benchmarks, controlled cutting of high areas, controlled filling and compaction of low areas, shaped temporary drainage, and a verified rough-grade surface, using the approved grading plan, benchmark, proposed elevations, drainage arrows, building-pad limits, and tolerances. The finished work product is a stable rough-graded site that supports construction traffic and directs water away from excavations, foundations, and active work areas.
You will review the grading plan and re-establish disturbed grade stakes and benchmarks; identify cut areas, fill areas, haul routes, stockpiles, and no-disturbance zones; confirm fill suitability and remove unsuitable material from fill areas; cut high areas and place compacted fill in low areas; shape temporary drainage and rough slopes away from the building area; check elevations and drainage; and correct high spots, low spots, loose fill, rutting, and blocked drainage before updating the grading record.
This is the tenth project in the site preparation sequence. It follows the utility trenches excavated and prepared in Project 9, which must be backfilled and compacted before rough grading proceeds over them. The rough grade established here supports the concrete slab building pad of Project 11 and the foundation backfill and drainage work of Projects 12 through 14, and must remain protected until those projects proceed.
Project 9 prepared and protected the utility trenches that must be backfilled and compacted before this project shapes grade over them; a trench that is still open or unprotected is a stop-work condition for this project, not a grading obstacle to work around. Project 6 established the compaction discipline this project extends to broader site areas, and Project 4 established the cleared, stripped limits within which cutting and filling occur.
The rough grade established here remains in place, protected from traffic, rain, and rutting, until Project 11 builds the concrete slab building pad and Projects 12 through 14 backfill and drain the foundation. Do not proceed to Project 11 while a required rough elevation, drainage shape, or compaction condition established in this project remains uncorrected.
This project covers:
This project does not authorize the learner to:
Any condition requiring a revised elevation, a different fill source, an engineer's determination, or a decision outside the approved grading plan must be escalated before work proceeds in that area.
Use these references, established in Projects 01 through 09, throughout this project. Do not redefine them.
| Term | Definition |
|---|---|
| Rough grade | The site surface shaped to the proposed elevation and drainage pattern before finish grading, topsoil placement, or paving |
| Cut area | A location where existing material exceeds the proposed rough elevation and must be removed |
| Fill area | A location where existing material is below the proposed rough elevation and requires approved compacted fill |
| Haul route | The approved path used to move cut material, fill material, or spoil between locations on the site |
| Drainage arrow | A plan symbol indicating the required direction of surface water flow at a given location |
| No-disturbance zone | An area the grading plan or prior project identifies as excluded from cutting, filling, or equipment travel |
Before grading begins, record the following:
Grading plan reviewed: ______ Benchmark and grade stakes re-established: ______ Project 9 trenches confirmed backfilled and cleared for grading: ______
Fill material source confirmed suitable: ____________ Date started: ____________ Builder name: ____________
A rough grade only supports the work that follows it if it reaches the correct elevation, drains water away from the building area and active excavations, and is built from material that will remain stable under later construction traffic and loading. A rough grade that traps water against a foundation, buries unsuitable material, or leaves loose or rutted fill compromises every project that depends on it.
Every area graded in this chapter depends on the Project 9 utility trenches being confirmed backfilled and compacted before equipment travels over them, and on the Project 4 cleared limits and protected topsoil stockpile locations remaining respected. Recheck both at Step 2 of this project before grading begins. If a field condition suggests the approved grading plan conflicts with an unbackfilled trench or a protected stockpile location, stop and obtain direction before grading around the conflict; do not reroute equipment over an unprotected trench to avoid a delay.
Cut and fill to the proposed rough elevation shown on the grading plan, maintaining the required elevation below future finished surfaces and the specified slope away from the building area. Check elevations at the regular interval identified by the plan. Where no specific interval is stated, treat this as an unresolved condition and obtain direction before proceeding, since an unverified interval may allow a low spot or reverse slope to go undetected over a large graded area.
Confirm required drainage direction, discharge locations, and any permit conditions affecting runoff onto neighboring property or public drainage systems from the approved grading plan or applicable regulatory authority before shaping temporary or rough drainage. These requirements vary by jurisdiction and site condition; do not assume a drainage direction used on a prior site applies here.
Operate grading and compaction equipment within its manufacturer-rated slope, load, and moisture-condition limits for the fill material being placed. Equipment operated outside its rated limits may fail to achieve the required compaction or may become unstable on a graded slope.
Do not operate grading or compaction equipment over a utility trench that has not been confirmed backfilled, compacted, and cleared for grading. Stop work immediately if unsuitable material, groundwater, or instability is discovered in a cut or fill area, and obtain direction before continuing.
Keep haul routes, stockpile locations, and equipment travel within the areas identified in Step 4, and maintain clearance from preserved grade stakes, benchmarks, and no-disturbance zones at all times during cutting, filling, and compaction.
SP-055 – SP-060
Rough Grading Qualification
Deliverable: one rough-graded building site matching the approved grading plan's proposed elevations, drainage arrows, building-pad limits, and tolerances; cut in controlled passes and filled with approved compacted material in low areas; shaped to provide rough slopes and temporary drainage away from the building area without ponding pockets; equipment access maintained without rutting prepared subgrades; and documented through a completed rough-grading record confirming final elevations and any unresolved conditions.
| Item | Quantity | Form | Content Requirement | Purpose |
|---|---|---|---|---|
| Re-established grade stakes and benchmark | Full graded area | Marked stakes and protected benchmark | Matches the approved grading plan and prior projects' preserved control points | Controlling cut and fill elevation throughout grading |
| Cut and fill area markings | Full graded area | Marked cut areas, fill areas, haul routes, stockpiles, no-disturbance zones | Identified before equipment enters the area | Directing controlled earthmoving without unnecessary disturbance |
| Compacted fill | As required by low areas | Placed and compacted lifts | Approved material, specified lift thickness, moisture, and compaction condition | Bringing low areas to the proposed rough elevation |
| Cut surfaces | As required by high areas | Shaped surface | Reduced to the proposed rough elevation in controlled passes | Bringing high areas to the proposed rough elevation |
| Shaped drainage | Full graded area | Rough slopes and temporary drainage shaping | Matches drainage arrows on the approved plan; no ponding pockets | Directing runoff away from the building area and active excavations |
| Rough grading record | 1 record for the graded area | Written record | Final rough elevations, drainage review findings, and unresolved conditions documented | Confirming readiness for the concrete slab building pad and following work |
| Check | Standard |
|---|---|
| Rough elevation | Matches the approved grading plan within the stated tolerance at every checked location |
| Fill material and placement | Approved material placed in compactable lifts, moisture-conditioned and compacted as required |
| Drainage direction | Matches the drainage arrows on the approved plan; no ponding pockets or reverse slope |
| Building-area slope | Rough slope away from the building area maintained per the approved plan |
| Transitions | Blended without abrupt humps or depressions |
| Equipment access | Maintained without rutting of prepared subgrades |
| Documentation | Rough grading record complete with final elevations, drainage review, and unresolved conditions |
Inspect the completed rough grade using the same checks regardless of site size or cut-and-fill volume.
Complete the Rough Grading Record Sheet in the Inspection Checklist section below before the concrete slab building pad work of Project 11 proceeds.
Probable cause: grade stakes were not re-established accurately, or elevation was not checked at the specified interval during cutting or filling.
Confirmation: measure elevation against the re-established benchmark at closer intervals along the affected area.
Correction: obtain direction before correcting overcut or underfill areas; add approved fill or remove excess material as directed.
Reinspection: re-check elevation along the corrected area before proceeding.
Probable cause: the shaped slope did not follow the drainage arrows on the approved plan, or a transition created an unintended low point.
Confirmation: observe or measure runoff direction against the approved drainage arrows.
Correction: reshape the affected area to restore the required slope and flow direction; obtain direction before altering a discharge point.
Reinspection: repeat the drainage review after reshaping.
Probable cause: fill was placed in lifts exceeding the specified thickness, moisture was outside the permitted range, or unsuitable material was not fully removed before placement.
Confirmation: inspect the fill area for soft spots, and compare lift thickness and moisture records against the specification.
Correction: remove and replace the affected fill in properly conditioned lifts and recompact.
Reinspection: re-check elevation and compaction condition of the corrected area.
Probable cause: a transition between cut and fill areas was not blended, leaving a low point that does not drain.
Confirmation: observe the area during or after rainfall, or measure elevation across the transition.
Correction: reshape the transition to eliminate the low point and restore continuous flow toward the approved drainage direction.
Reinspection: repeat the drainage review after reshaping.
Probable cause: equipment traveled outside the approved haul route, or the subgrade was worked while saturated.
Confirmation: inspect the affected area for rutting depth and compare against the approved haul route markings.
Correction: obtain direction before recompacting or replacing rutted material; restrict equipment to the approved haul route going forward.
Reinspection: re-check the repaired area for elevation and compaction condition.
Probable cause: organic, saturated, frozen, or contaminated material was not fully identified and removed during Step 6.
Confirmation: inspect the fill area before further placement and compare the exposed material against the project specification.
Correction: remove the unsuitable material to the approved limits before placing further fill; obtain direction if the extent of unsuitable material is unclear.
Reinspection: reverify the exposed base before fill placement resumes.
This project ends with a protected, rough-graded site ready for the next operation, not a finish-graded or unprotected surface.
| Competency | Independent Pass Standard | Not Demonstrated | With Assistance | Independently |
|---|---|---|---|---|
| SP-055 | Reviews the grading plan, benchmark, proposed elevations, drainage arrows, building-pad limits, and tolerances, and re-establishes disturbed grade stakes and protected benchmarks | |||
| SP-056 | Identifies cut areas, fill areas, haul routes, stockpiles, and no-disturbance zones, and shapes temporary drainage so runoff does not enter excavations or neighboring property | |||
| SP-057 | Confirms fill material suitability, removes unsuitable material from fill areas, and places approved fill in compactable lifts in low areas | |||
| SP-058 | Cuts high areas in controlled passes, moisture-conditions and compacts fill as required, and blends transitions without abrupt humps, depressions, or ponding pockets | |||
| SP-059 | Maintains required elevation below future finished surfaces, provides rough slopes away from the building area, and maintains equipment access without rutting prepared subgrades | |||
| SP-060 | Checks elevations, performs a visual and measured drainage review, corrects high spots, low spots, loose fill, rutting, and blocked drainage, and updates the grading record with final rough elevations and unresolved conditions |
Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.
| Item | Approved / Specified Value | Field Result | Within Requirement (Y/N) | Correction (if any) |
|---|---|---|---|---|
| Rough elevation | ||||
| Fill material and compaction | ||||
| Drainage direction | ||||
| Building-area slope | ||||
| Transitions | ||||
| Equipment access condition |
Escalations and direction obtained (list): ____________ Unresolved conditions: ____________
Rough grade declared ready for the next operation: ______ (Yes/No) Date: ____________ Builder name: ____________
With cutting, filling, compaction, and drainage shaping complete, review the completed rough grade against the Acceptance Standards table and confirm the rough elevation matches the approved plan within tolerance, fill material is approved and properly compacted, shaped drainage matches the approved drainage arrows with no ponding pockets, rough slope away from the building area is maintained, transitions are blended without abrupt grade breaks, and equipment access has not rutted prepared subgrades. Complete the Rough Grading Record Sheet and correct any failed item before Project 11 proceeds.
You have completed the tenth project in the site preparation sequence: rough grading a residential building site to the required elevation and drainage pattern while protecting the utility trenches, controls, and stockpiles established in earlier projects. This project required you to review the grading plan and re-establish disturbed grade stakes and benchmarks (SP-055), identify cut areas, fill areas, haul routes, stockpiles, and no-disturbance zones and shape temporary drainage (SP-056), confirm fill suitability and place approved fill in compactable lifts (SP-057), cut high areas, compact fill, and blend transitions (SP-058), maintain required elevation and rough slopes while protecting equipment access (SP-059), and check elevations, perform a drainage review, correct deficiencies, and update the grading record (SP-060).
You now have a stable, correctly graded, and documented rough-graded site with drainage directed away from the building area and active work.
Protect the rough grade from traffic, rain, freezing, contamination, and rutting. The concrete slab building pad of Project 11 depends on this rough grade remaining at its verified elevation and undisturbed until that project begins.