Practical Trades Manual Series
|
Residential Roofing — Book 5: Underlayment, Shingles, Flashing, Gutters, and Water Control

Chapter 10

Install Step Flashing at a Sidewall

Integrate individual step-flashing pieces with asphalt-shingle courses and the approved wall drainage layer at a roof-to-sidewall intersection, one course at a time, so wall and roof water reach the exterior without relying on exposed sealant joints.

Field Cue System

These cues appear at the point of work. They identify safety, code, manufacturer, and measurement issues before they become rework or hazards.

△

Safety Cue

Task-specific safety guidance for ordinary work hazards.

✋

Critical Safety Cue

Serious injury, fall, or major damage is possible.

⛑

Field Safety Cue

Practical work-area safety: footing, weather, housekeeping, and access.

▤

Code Alert

Local requirements vary. Verify permit, inspection, and jurisdictional rules.

▧

Manufacturer Cue

Follow product-specific instructions for materials, fastening schedules, and equipment.

▱

Measurement Cue

Slope, span, clearance, and reference-point guidance.

Job Overview

This chapter qualifies you to integrate individual step-flashing pieces with asphalt-shingle courses at a roof-to-sidewall intersection. The finished work product is a complete, course-by-course step-flashing assembly that begins at a properly installed kickout flashing, alternates one flashing piece per shingle course up the sidewall, and terminates in the approved headwall, counterflashing, or transition detail at the top of the wall.

You will confirm the roof-to-wall detail, verify that the wall drainage layer or approved counterflashing will protect the upper flashing legs, install or verify kickout flashing at the base of the wall, prepare individual step-flashing pieces to the specified dimensions, and alternate shingle courses and flashing pieces one at a time up the sidewall while keeping every piece within its required laps and fastening zone.

Step flashing cannot be corrected after the shingle field and siding conceal it. Every piece installed in this chapter becomes a permanent, inaccessible part of the roof-to-wall water path, so each piece must be verified before the next shingle course covers it.

Skills You Will Demonstrate

  • RF-055 — Identify sidewall flashing locations, including the kickout point, wall drainage interface, and upper termination.
  • RF-056 — Install individual step-flashing pieces at the specified dimensions and fastening zone.
  • RF-057 — Lap each flashing piece with the shingle courses above and below it in correct shingle-lap order.
  • RF-058 — Protect the wall transition with correctly installed kickout flashing and upper-leg integration.
  • RF-059 — Integrate the wall drainage layer or approved counterflashing with the step-flashing upper legs.
  • RF-060 — Inspect the completed flashing sequence for laps, fastening, kickout direction, and drainage continuity.

Where This Skill Fits

This chapter depends on the roof deck, underlayment, self-adhered membrane, layout, starter strips, and shingle-field work completed in Chapters 1 through 8, and it applies the valley principle from Chapter 9 that flashing must be integrated while the shingle field is installed, never inserted afterward. The corresponding wall-flashing skill for a roof-to-wall intersection that runs across the slope rather than along it is taught separately in Chapter 11, Headwall and Apron Flashing.

The step-flashing sequence you complete here feeds directly into the Chapter 20 capstone, where the same course-by-course method is applied to any sidewall condition included in the approved capstone design.

Scope and Intended Use

This chapter covers:

  • reviewing the approved roof-to-wall detail, step-flashing dimensions, metal compatibility, wall drainage or counterflashing sequence, kickout flashing, and siding clearance
  • installing or verifying kickout flashing at the base of the sidewall before standard step flashing begins
  • preparing individual step-flashing pieces to the specified length, width, bend, and corrosion resistance
  • alternating shingle courses and step-flashing pieces one course at a time up the sidewall
  • integrating the upper flashing legs with the wall drainage layer, counterflashing, or siding-system components
  • inspecting the completed sequence before it is concealed by siding or counterflashing

This chapter does not authorize the learner to:

  • install headwall or apron flashing at a wall transition that runs across the roof slope; that work is taught in Chapter 11
  • insert step flashing beneath a completed shingle field; step flashing must be integrated course-by-course as the field shingles are installed
  • install or modify siding, trim, or wall-cladding components beyond the minimum integration required to protect the flashing upper legs
  • fasten through both the roof and wall legs of a flashing piece in a way that restricts movement or creates an exposed leakage path, unless the approved detail specifically requires it

Any sidewall condition that does not match the approved detail, including missing kickout provisions or an incompatible wall drainage system, must be recorded and referred to the responsible authority before flashing proceeds at that location.

Reference Conventions

Establish these references before cutting or installing any flashing piece, and use them consistently across the inspection record.

TermDefinition
SidewallA vertical wall surface that meets a roof plane along its slope, running from eave toward ridge
Step flashingA series of individual, bent metal pieces installed one per shingle course, each lapping the piece below it and the shingle above it
Roof legThe portion of a step-flashing piece that lies flat on the roof deck beneath the shingle course
Wall legThe portion of a step-flashing piece that turns up against the sidewall
Kickout flashingA diverter piece installed at the lower termination of a sidewall that directs roof and wall water away from the wall and into the gutter or off the roof edge
CounterflashingA wall-mounted or reglet-set metal component that laps over the upper leg of step flashing in place of, or in addition to, the wall drainage layer
Wall drainage layer / WRBThe water-resistive barrier on the wall that must lap over the upper legs of the step flashing

Sidewall Flashing Record

Before beginning installation, record the controlling documents and site identification directly on the inspection record used at the end of this chapter:

Project / address: ______     Roof-to-wall detail reference: ______     Sidewall location: ______

Date started: ____________     Installer name: ____________

Prerequisites

Common Field Fundamentals

Step flashing depends on maintaining the same shingle-lap water path used throughout this book: every upper layer sheds onto the layer below it. At a sidewall, that path runs from the wall drainage layer, down over the step-flashing wall leg, onto the step-flashing roof leg, and onto the shingle course below. Breaking this order at any single course creates a concealed entry point that will not appear until water finds it.

Kickout pointLower termination; diverts water away from the wall and into the gutter or roof edge
Course-by-course runOne step-flashing piece per shingle course, alternating up the wall
Upper leg integrationWall drainage layer or counterflashing laps over each wall leg
Upper terminationHeadwall, counterflashing, or approved transition at the top of the wall

Kickout Flashing Before Standard Step Flashing

Install or verify the required kickout flashing at the lower roof-to-wall termination before the first standard step-flashing piece is installed. The kickout piece directs both roof runoff and wall drainage away from the wall base and into the gutter or off the roof edge; without it, water is directed behind the gutter and into the wall assembly at the most vulnerable point in the entire sidewall run.

RF-055 – RF-060

Flashing Integration / Sidewall Water Control

Sidewall Step-Flashing Installation

Difficulty: Intermediate

Estimated Time: 4–7 hours

Estimated Cost: Moderate

Finished Work: A complete, inspected, course-by-course step-flashing assembly from kickout to upper termination

A. Finished-Work Specification

Deliverable: one continuous sidewall flashing assembly consisting of a correctly installed kickout piece at the base, one individual step-flashing piece integrated with each shingle course up the sidewall, upper flashing legs integrated with the wall drainage layer or approved counterflashing, and a completed upper termination detail, all photographed before concealment.

B. Governing Documents

DocumentConfirmed CurrentNotes
Roof-to-wall detail
Step-flashing dimensions and metal specification
Wall WRB or counterflashing sequence
Kickout-flashing detail
Siding-clearance requirement
Fastening restrictions / schedule

C. Acceptance Standards

CheckStandard
Kickout flashingInstalled at the lower termination before standard step flashing begins, draining onto the lower roofing layer or gutter, not behind it
Step-flashing piecesCut and formed to the specified length, width, bend, and corrosion resistance; no cracked, overbent, or incompatible pieces installed
FasteningEach piece fastened only in the approved upper area and to the permitted substrate; no fastener placed through both roof and wall legs unless the approved detail requires it
Course-by-course lapEach flashing piece laps the shingle course below by the required amount, and each subsequent piece laps over the shingle placed on the prior piece by the required vertical and horizontal amount
Wall-leg integrationUpper legs integrated beneath WRB, counterflashing, or siding-system components in the approved shingle-lap sequence
Siding clearanceRequired clearance between roofing and siding or trim maintained along the full sidewall run
Upper terminationCompleted using the approved headwall, counterflashing, or transition detail
DocumentationPhotographs of the flashing sequence taken before concealment by siding or counterflashing

D. Required Project Sequence

  1. Review the approved roof-to-wall detail, step-flashing dimensions, metal compatibility, wall WRB or counterflashing sequence, kickout flashing, siding clearance, and fastening restrictions. Confirm the revision or date on each document before using it as a reference, and record the confirmation on the governing-documents table above.
  2. Confirm that the sidewall, roof deck, underlayment, membrane, and lower drainage outlet are ready. Verify these items were accepted under their governing chapter before beginning flashing work at this sidewall.
  3. Verify that the wall drainage layer can lap over the upper legs of the step flashing or that approved counterflashing will provide equivalent protection. Identify which method applies to this sidewall and record it on the flashing record before cutting any pieces.
  4. Install or verify the required kickout flashing at the lower roof-to-wall termination before standard step flashing begins. Confirm the kickout piece directs water away from the wall base and into the gutter or off the roof edge, not behind either.
  5. Establish the first shingle course and step-flashing position from the eave reference. Confirm the course position matches the layout lines established in Chapter 6 as they cross the sidewall.
  6. Prepare individual step-flashing pieces to the specified length, width, bend, and corrosion resistance. Cut and form the full run of pieces needed for this sidewall before beginning installation, and reject any piece that does not meet the specified dimensions or bend angle.
  7. Position the first flashing piece so its lower edge drains onto the lower roofing layer or kickout flashing. Confirm the roof leg bears fully on the roof deck and the wall leg sits flat against the sidewall before fastening.
  8. Fasten each step-flashing piece only in the approved upper area and to the permitted substrate. Use the fastener type, quantity, and location specified in the fastening schedule, and keep fasteners out of the lower, exposed portion of each piece.
  9. Do not fasten through both the roof and wall legs in a way that restricts movement or creates exposed leakage paths unless the approved detail requires it. Confirm each piece can move independently with normal building movement before covering it with the next shingle course.
  10. Install the corresponding shingle course over the roof leg of the flashing. Fasten the shingle using the fastening zone and pattern established in Chapter 8, keeping shingle fasteners out of the flashing's prohibited zones identified in Step 13.
  11. Place the next step-flashing piece over the shingle with the required vertical and horizontal lap. Confirm the lap dimension against the approved detail before fastening the piece.
  12. Continue alternating shingle and flashing pieces one course at a time. Do not install two shingle courses before placing the intervening flashing piece, and do not stage multiple flashing pieces ahead of the shingle courses that support them.
  13. Keep shingle joints, nails, and cut edges out of prohibited flashing zones. Verify no shingle fastener penetrates the step-flashing metal and no shingle joint lands directly over a flashing lap.
  14. Fit flashing around wall transitions without flattening the upturned leg or creating reverse laps. Form each piece individually at inside corners, outside corners, or changes in wall plane rather than bending a straight piece to force a fit.
  15. Integrate the upper flashing legs beneath WRB, counterflashing, or siding-system components in the approved shingle-lap sequence. Confirm the wall drainage layer or counterflashing overlaps each wall leg from above, never from below.
  16. Maintain required siding and trim clearance above the roof surface. Measure the clearance at representative points along the sidewall and record any shortfall as a deficiency.
  17. Complete the upper termination with the approved headwall, counterflashing, or transition detail. Confirm the top of the step-flashing run ties into the governing detail for the upper wall or roof condition, coordinating with Chapter 11 where a headwall condition is also present.
  18. Inspect kickout direction, individual laps, flashing height, fastener placement, WRB integration, siding clearance, and drainage continuity. Complete this inspection before any siding, trim, or counterflashing conceals the assembly.
  19. Correct omitted pieces, short laps, exposed fasteners, blocked kickouts, or reverse-lapped wall layers. Remove and replace any piece that fails inspection rather than adding sealant to compensate for a missing or misplaced piece.
  20. Photograph the flashing sequence before siding or counterflashing conceals it. Label each photograph with its location along the sidewall and attach it to the flashing record.

Common Sidewall Flashing Checks

Apply the same checks to every step-flashing piece along the sidewall, regardless of run length or wall configuration.

Complete the Sidewall Flashing Inspection Record below before siding, trim, or counterflashing conceals this work.

Image Placeholder
Recommended image: kickout flashing installed at the base of a sidewall, shown diverting water into the gutter rather than behind it.
Image Placeholder
Recommended image: an individual step-flashing piece positioned with its roof leg over a shingle course and its wall leg against the sidewall, before the next shingle course is installed.
Image Placeholder
Recommended image: a completed run of alternating shingle courses and step-flashing pieces up a sidewall, with the wall drainage layer folded back to show the upper flashing legs.
Image Placeholder
Recommended image: the upper termination of the sidewall run, showing the transition into the approved headwall or counterflashing detail.
Image Placeholder
Recommended image: a correctly formed inside-corner or outside-corner step-flashing piece contrasted with a flattened or forced example.

Failure Points and Troubleshooting

Cleanup

This chapter ends with a photographed, inspected flashing assembly and an organized record set, not loose metal offcuts on the roof or ground.

Field Terms

Step Flashing
A series of individual, bent metal pieces installed one per shingle course at a sidewall.
Roof Leg
The portion of a step-flashing piece bearing flat on the roof deck beneath a shingle course.
Wall Leg
The upturned portion of a step-flashing piece bearing against the sidewall.
Kickout Flashing
A diverter piece at the base of a sidewall that directs roof and wall water away from the wall and into the gutter or roof edge.
Counterflashing
A wall-mounted or reglet-set metal component that laps over the step-flashing upper leg.
Wall Drainage Layer / WRB
The water-resistive barrier on the wall that must lap over the step-flashing upper legs.
Sidewall
A vertical wall surface meeting a roof plane along its slope, running from eave toward ridge.
Upper Termination
The approved headwall, counterflashing, or transition detail completing the top of a step-flashing run.

Skill Check

  1. Why must kickout flashing be installed before the first standard step-flashing piece?
  2. Why is each step-flashing piece installed as an independent piece rather than as one continuous strip?
  3. What is the required relationship between the wall drainage layer or counterflashing and the step-flashing upper legs?
  4. Under what condition, if any, may a fastener cross both the roof and wall legs of a step-flashing piece?
  5. Why must step flashing be integrated course-by-course rather than installed after the shingle field is complete?
  6. What must a learner do upon finding that the available wall drainage system does not match the approved detail?
  7. Why must the flashing sequence be photographed before siding or counterflashing conceals it?
  8. What is the difference between the step-flashing work in this chapter and the headwall flashing work taught in Chapter 11?
  9. What corrective action is required when a step-flashing piece will not sit flat against the wall?
  10. Why does closing a siding-clearance shortfall with sealant fail the acceptance standard for that check?

Competency Rubric

CompetencyIndependent Pass StandardNot DemonstratedWith AssistanceIndependently
RF-055Correctly identifies the kickout point, wall drainage interface, and upper termination for the sidewall before installation begins
RF-056Installs individual step-flashing pieces at the specified dimensions, bend, and fastening zone
RF-057Laps every flashing piece with the shingle courses above and below it in correct shingle-lap order, with no skipped or doubled course
RF-058Installs kickout flashing and completes upper-leg integration so wall and roof water are protected at every transition
RF-059Integrates the wall drainage layer or approved counterflashing with the step-flashing upper legs in the correct lap order
RF-060Inspects and documents the completed flashing sequence for laps, fastening, kickout direction, and drainage continuity before concealment

Mark one column per competency. Only Demonstrated Independently awards the competency; Demonstrated with Assistance authorizes additional supervised practice but does not complete the requirement.

Inspection Checklist — Sidewall Flashing Inspection Record

ItemCondition FoundCorrection RequiredCorrected (Y/N)Reinspection Result
Kickout flashing installation and direction
Step-flashing piece dimensions and bend
Fastening zone and quantity
Course-by-course lap sequence
Wall-leg / WRB or counterflashing integration
Siding / trim clearance
Upper termination detail
Photographic documentation before concealment

Sidewall flashing decision: ______ (Proceed to Concealment / Conditional-Proceed / Stop-Work)     Date: ____________     Inspector name: ____________

Performance Check

With the sidewall flashing complete, review the Sidewall Flashing Inspection Record against the Acceptance Standards table and confirm the kickout flashing is installed and correctly directed, every step-flashing piece matches the specified dimensions and bend, fastening is confined to the approved zone on every piece, the course-by-course lap sequence has no skipped or doubled course, the wall drainage layer or counterflashing correctly integrates with every upper leg, siding clearance is maintained along the full run, the upper termination ties into the approved detail, and photographs of the full sequence are attached to the record. Issue and sign the sidewall flashing decision before siding, trim, or counterflashing conceals this work.

Chapter Closeout

You have completed the sidewall step-flashing sequence for this roof: identifying the flashing locations (RF-055), installing individual step-flashing pieces (RF-056), lapping each piece with the surrounding shingle courses (RF-057), protecting the wall transition with kickout flashing (RF-058), integrating the wall drainage layer or counterflashing (RF-059), and inspecting the completed sequence before concealment (RF-060).

You now have a documented, photographed step-flashing assembly that carries roof and wall water safely to the exterior at this sidewall. That record carries directly into the next chapter, where a wall transition running across the roof slope is flashed using headwall and apron flashing rather than the course-by-course step method used here.

Store the completed flashing record and photographs with the project record. Chapter 11 and the Chapter 20 capstone require this record for any remaining wall-flashing work on this structure.